Project Controls: The Outlined Guide On Functional Implementation
Project Controls: The Outlined Guide On Functional Implementation
- Abbreviations ............................................................................... 2
Page 1 of 11
Project Controls-The outlined guide on functional implementation
Abbreviations
-WBS: -Work Break down Structure
-OBS:-Organizational Break down Structure
-CBS:-Cost Break down Structure
1.0 Introduction
The Project Controls development, implementation and management are of seemingly relevant and
coexist in project management to consciously improve work and efficiency of managed projects or
programs. The Project Controls implementation of work processes, procedures and application to plan,
monitor and control the work are intrinsically inevitable part of strategic projects subsequently meeting
the established business case. The document contents to outline the qualitative description of Project
Control Process and further the quantitative aspects in its Estimate, Budget & Schedule areas.
In actual scenario, organizations differs on it’s commitment towards the successfully performing the
Project Control Services and are widely tailored to meet organizational or project specific requirements.
The Project Controls practices are generally defined with common terminology and understandings to
include the below work process at minimum ;
Project Planning and Scheduling
Cost Estimating and Budgeting
Communication and Risk Management
Scope and Change Management
Project Performance Measurement and Assessment
Project Controls Implementation
Project Control Deliverables, Document Control and Reporting
History Repository and Close Out Documents
This Project Controls is integrated set of process used as the communication tool for exercising
successful project management enabling effective decision making in organizations.
Page 2 of 11
Project Controls-The outlined guide on functional implementation
of timely production of the project control documents and necessary reports that are required in order to
enable effective project delivery.
Interdisciplinary coordination and controls will be established accordingly to ensure consistent project
control management. The effective system will ensure seamless flow of information amongst various
disciplines with appropriate checks and controls.
4.0 Project Controls – The Functional Framework
4.1 Project Planning and Scheduling
In Project Controls functions, its Project Planning work process that determines project's objectives with
identification of the activities to be performed, methods and resources to be used for accomplishing the
tasks, assignment of responsibility and accountability, and further establishment of an integrated plan.
The integrated plan is represented further on time bounded logical framework which base the project
timeliness or the project schedule. The major phases in the planning and scheduling is outlined under
below heads.
Page 3 of 11
Project Controls-The outlined guide on functional implementation
Level 1: This represents the schedule for the project by its major components. A Level 1
schedule is normally displayed as a Gantt or bar chart and may include key milestones.
Level 2: Each schedule component is further subdivided for Level 2. Level 2 schedules are
shown as a bar chart although key constraints may also be displayed. Milestones are normally
included.
Level 3: The first Control level that a meaningful critical path network can be displayed and the
CPM schedule can be used to monitor and manage (control) the overall project work. Level 3 is
neither too summarized nor too detailed.
Levels 4-X: The level of schedule subdivision continues to whatever is appropriate detail as per
project control require to effectively manage the project. The project “rolling schedule” includes
a “look-ahead” period of time (30–180 days) and a “look-back” at recent completed work periods.
CPM (Critical path method) as tool the project detailed schedule will be drawn to effectively monitor the
progress of the project.A time-phased, logically linked, resource loaded, detailed schedule with
interpretation of the plan will be measured and assessed as Schedule Performance Baseline. The
baseline schedule will reflect the original Scope of Work, Contract Milestones, duration, inter-relationship
logic, work status and work backlog versus their scheduled targets for the different phases and the
critical path.
The project schedule will be updated periodically based on project requirements. Extracted forecast
schedules to meet requirements will be provided at project level and organizational level.
The schedule will be briefed and document as Schedule Basis Document to ensure the effective
implementation of schedule control plan. The documents and schedule will be validated accordingly
during integrated change control process upon requirements.
4.1.4 Resource Planning
Requirements are to set out by Project Controls for workface and workforce planning i.e. labor and
equipment to meet the effective execution of its projects.
Further to the resource estimate labor management planning is designed to facilitate the collection and
reporting of the project labor (home office, field office, engineering disciplines, and field trades). Time-
phased usage profiles and histograms based on the project schedule and estimate are developed as an
output for measuring actual hours / costs against the planned hours / costs to support the evaluation of
performance and prediction of final forecast hours / costs.
Equipment management planning is designed to facilitate the collection and reporting of the site
equipment. Usage profiles will be developed as an output for measuring actual costs against the planned
costs to support the evaluation of performance and prediction of final forecast costs.
4.1.5 Procurement Planning
The Project Controls during planning ensures through the procurement planning the information about
resources (e.g., labor, material, etc.) as required for the project ,is identified , incorporated in, as obtained
through the procurement process. Equipment Purchasing plan and contracting plan is communicated on
requirements.
Direct Costs
Page 4 of 11
Project Controls-The outlined guide on functional implementation
• Labour
• Material
• Equipment
• Subcontract
Indirect Cost
• Taxes
• Risk
- Profit
- Contingency
• Overhead
• Escalation
In general activity-based costing techniques ensure optimum control over unbalanced allocations.
Pricing includes charging techniques that various stakeholders in the plan (bidders, contractors, etc.)
apply to costs in the estimate to allow for overhead and profit, to improve cash flow, or to otherwise
address market conditions and serve their business interest.
Estimating ideally includes both expected cost and probabilistic cost distribution. As a predictive process,
historical reference cost data (where applicable) improve the reliability of cost estimating. Pricing the
cost estimate includes charging techniques that various stakeholders in the plan (bidders, contractors,
etc.) apply to costs in the estimate to allow for overhead and profit, to improve cash flow, or to otherwise
address market conditions and serve their business interests. The project estimate facilitates the bidding
and estimate basis document to avoid ambiguity.
Budgeting includes allocating the estimated cost of asset or project items into cost accounts against
which cost performance will be measured and assessed. Budgeting results in a baseline for cost control
performance assessment. Budgets are time-phased in accordance with the schedule or to address
budget ,cash flow constraints to meet the actual expenditures, revenue plans .
4.3 Communication and Risk Management
The project controls addresses communication and risk management throughout the life of the project.
The Project Management team describe both qualitative and quantitate aspects of risk. The process
facilitates to identify risk factors (risk assessment), further analyze and quantify the properties of those
factors (risk analysis), mitigating the impact of those factors on project performance. A risk management
plan (risk mitigation), and implementing the risk management plan (risk control) is exercised as required
on project.
4.4 Scope and Change Management
The project controls during the planning phase facilitate development of the scope management plan
which sufficiently ensures the committed scope is executed later on and establish a control to meet the
zero scope creep. Defined Work Breakdown Structure act as a tool to communicate the scope to the
project execution. Further scope validation functions outlines the the integrity of the control basis
(performance measurement baselines) as a valid baseline (i.e., it represents a project plan in alignment
with project objectives and requirements) for performance measurement.
The Project Controls address through the contents the methodology and processes for managing
changes (whether internal and/or external to the business plan, project or contract) throughout the
project regarding scope, quality, cost and time. Various types of changes and/or trends, as well as the
desired approval process are defined. Upon approval, the change will be methodically incorporated into
the revised performance measurement baseline.
Change management intends to cover the process addressed below at minimum:
Cost Performance
Schedule Performance
Resource Performance
Work Process & Productivity
Risk Factors
The observations along with schedule, resource, productivity, and work process and performance
assessments will forecast the project requirements and deliverables.
Forecasting
The proactive and systematic approach are followed by Project Controls in process of evaluating the
project control baselines in consideration of assessments of ongoing project performance. The
forecasting process intent to be used to assess each applicable element of the project, which may
include scope, schedule, budget, resources, and risks. This section address quantitative forecasting for
both cost and schedule values.
Cost Forecasting
The project requirements determine the best possible solution that identifies an accurate EAC,
and supports the mitigation of cost and schedule overruns that may surface
The below listed some standards methodologies
-Estimate at Completion= Actual Cost+ Estimate to Complete
-Estimate at Completion = Actual Cost Budget at Completion–Earned Value
-Estimate at Completion= Budget at Completion ÷ Cost Performance Index
The project team decides on the most Feasible to effectively control the project.
Schedule Forecasting
Total float management under tool Critical Path Method is used to gain effective control over
Scheduling tasks. The past performance, resources and remaining timeline, material and
Page 6 of 11
Project Controls-The outlined guide on functional implementation
equipment available, the sequenced schedule network are taken in to consideration while
forecasting the schedule.
The below listed some standards methodologies
-Schedule at Completion = Actual Duration + Remaining Duration.
-Schedule at Completion = Project Duration ÷ Schedule Performance Index.
5.0 Project Controls Implementation
The Project Controls Implementation is the process of integration of all aspects of the Project Controls
by setting project implementation basis; validating that the plans are comprehensive and consistent with
requirements and ready for control; initiating mechanisms or systems for project control; and
communicating the integrated project controls data to those responsible for the project’s work packages.
Project Controls implementation is governed by Project Implementation Basis. Project control process
are applied throughout the life cycle of project in phased manner as project work is implemented. As
through project implementation the project scope is defined and conceptualized as Project Plan. Project
Controls through set of established work process facilitate the further definition of Project Plan through
its estimate, schedule and cost budget at various phase as per project implementation basis.
Project Controls coordinates with Project Management Team to facilitate the project control functions
depending on the planning level required to meet the specific phases of the project. During planning
phase, a detailed schedule and cost budget is being developed and documented to facilitate project
team reviews so as to ensure effective project implementation. The Project Controls provides the
management with view of collective outcomes of cost and time at staged phases of the project. The
performance against the established schedule and cost base baselines is assed and evaluated. The
changes initiated through the integrated change control process is implemented through the project plan
upon validation and further through all the definitions of project control functions.
Appropriate review and validation process are established for communication interface. The following
list major supporting documents and general tools developed to support the implementation of Project
Controls functions,
Work Breakdown Structure
Schedule Basis
Schedule Management Procedure
Invoicing Procedure
Budget Plan
Progress Measurement Systems
Progress Control Curves
The Interims of WBS will be reviewed during execution and any modification will be discussed and
suitably implemented.
tool for assisting any personnel who are transitioning into the project and may be used in claims
situations to illustrate a change of scope.
weekly basis unless and otherwise stipulated by requirement of contract of involved parties. Reporting
format is governed by contract agreement or mutually agreed within both involved parties.
Progress Measurement System must cover the complete scope of work. The progress will be measured
and will be validated accordingly as per project specifications.
Each phase of project is monitored as a discrete package and the relative percentage weighting is
allotted to each phase based on the relative cumulative cost of that phase, in order to calculate the
“Overall” Progress. The overall weightings established will remain fixed unless there are changes in total
work scope of a large magnitude or the base contract has changed significantly
The Level I Progress Control Curve shall be a summation (Overall) Progress Control Curves for all
phases of project. The progress figures for each phase and their respective weightings shall be shown,
as well as the overall work figures, either in tabular format below the curve or separately as a progress
table.
Progress Curves (S-Curves)
Individual Progress Control Curves(S-Curves) for all phases to ease effective controls. The general
philosophy for construction in terms of the controls curves is as described below,
a. Subjected to project specification the engineering curve shall be supported by a table of the weighting
and progress figures for all engineering disciplines. Engineering disciplines shall include all disciplines
contributing to the engineering, procurement and contract services. A separate table shall be produced
showing progress figures per discipline in accordance with the WBS.
b. Subjected to project specification procurement curves shall be shown separately and overall for
equipment and bulk materials. They shall be generated from the relevant procurement schedules
whereby the weighting of equipment, bulk materials and procurement steps are used to describe planned
progress.
The curves shall be supported by a table of the weightings and progress figures for each equipment
group or bulk material category as appropriate. Additionally, curves shall also be produced showing
‘Order Placement’, Manufacturing, and ‘Shipping and Delivery to Site’ separately for Equipment and
Bulks where ever applicable.
c. Subjected to project specification fabrication curve shall be supported with the table of weightage for
shop fabrication.
c. Subjected to project specification the construction curve shall be fully supported by a table of the
weightings and progress figures for all of the direct construction disciplines. A separate table shall be
produced showing progress figures per discipline in accordance with the WBS.
The approved planned Progress Control Curves shall provide the baseline of the work and shall be fixed
for the duration of the work. All changes shall be superimposed on the original curves to reflect any
approved changed once incorporated within the current schedule and tracking tools.
Manpower Histogram
Project Controls develop histograms for direct and indirect manpower separately. The histograms shall
show the monthly planned manpower vs. the actual manpower and forecast shown if different from plan.
Page 9 of 11
Project Controls-The outlined guide on functional implementation
Manpower per man month shall be clearly indicated. A table detailing the breakdown by discipline/trade
shall be provided below the histogram or as a separate tabulation. During the execution of the work, the
actual manpower shall be compared with the planned and a forecast shall be produced to support any
progress curves as necessary.
6.0 Project Controls Deliverables Document Control and Reporting
Project Controls generate appropriate communication plan in line with project requirements to provide
the project team with an understanding of the outputs, i.e. deliverables that are required for the execution
and management of the project.
Project Controls deliverables support the team in their decision making process to support the
identification of threats and impacts to the project, and determine corrective action where necessary.
Project Controls delivers in general the below list of deliverables to support the effective delivery of the
project which is subjected to meet the project specifications;
Area Deliverable
Page 10 of 11
Project Controls-The outlined guide on functional implementation
Lessons learned, historical from past projects and previous phases / stages.
Budget and estimate, estimate basis
Final cost report
Baseline schedule, schedule basis
Final schedule
Final executive project report
Resource histogram(s), cash curves, progress charts
Final change order log, complete with costs, hours, and quantities
Final progress and performance report
Qualitative and quantitative metrics & analysis
Contractor evaluation report
Page 11 of 11