CETRA 2018 Rail Structure Interaction of Bridge Across Balram River
CETRA 2018 Rail Structure Interaction of Bridge Across Balram River
Abstract
In long welded rails (LWR) considerable longitudinal forces may develop due to
temperature variation, train loadings like braking and traction, deck end rotation
due to vertical bending. Rail structure interaction (RSI) analysis is an important part
of bridge design to find the longitudinal stresses in LWR, longitudinal forces on the
substructure and deflection/displacement of the structure. This paper presents the
case study of an ongoing bridge project over Balram River, Gujrat India for
Dedicated Freight Corridor Corporation (DFCC). Total length of the bridge is 195m.
The analysis is carried out by a finite element based software package and as per
the endorsements given in the UIC 774-3 code. Stress developed in LWR largely
depends on the girder stiffness and the support stiffness (pier and foundation). In
general practice, the boundary condition is maintained as fixed on one abutment
and free on the other with all the spans being simply supported having one end free
and other end fixed. The large span of bridge and height of support increases the
flexibility of structure and poses difficulty to satisfy the stress and displacement
criteria mentioned as per UIC & IRS Codal provisions with this boundary conditions.
Excessive displacement of deck can result in deconsolidation of ballast and track
stability cannot be ensured. Use of expansion device may require proper
monitoring and demand for intensive maintenance. Different bearing articulations
were tried and a parametric revision was done to arrive at the optimum/economical
substructure and foundation stiffness and to satisfy the stresses and displacement
limits prescribed in UIC 774-3. It was found that the bearing arrangement with both
the abutments fixed and center pier rendered to be free, with these current
circumstances/assumptions were able to satisfy the stress and displacement
criteria as per Codal provisions and arrive at most economical substructure design.
Keywords: Rail structure interaction; long welded rail; Track bridge interaction;
simply-supported bridge.
As the rails are continuous over the structure, it will induce relative displacement in
the structure and the track due to temperature variation of bridge deck and
movement of train. Due to excessive displacement, additional stresses in rails and
longitudinal forces in rails may develop due to which stability of track and structure
are questionable. So to ensure the stability of track and ballast, controlling the
stresses and displacements are essential.
To ensure the safety of the structure & track, UIC 774 – 3R have given certain
criteria to be met which are listed below:
The maximum permissible additional compressive rail stress due to
temperature variation of the deck, braking/acceleration and deck-end
rotation is 72 N/mm2 (σrail ≤ 72 N/mm2).
2.1 Assumptions
I. Track & deck are been modelled as discrete elements with maximum
element length of 1.0m to generate more accurate results.
II. Nonlinear springs are being used to connect track and deck to represent
the actual behaviour of ballast and rail fastening system and stiffness of
ballast has been applied for these springs.
III. For this analysis pile is modelled up to the depth of fixity and given fixed
supports at the fixity point.
3. Loading
Following are the loads considered for the analysis as per UIC:
I. Temperature loads
II. Horizontal braking and acceleration forces due to Train loading
III. Vertical loads due to train loading
4. Analysis
Since the bridge is straight and simply supported spans with lesser span length,
simplified separate analysis has been carried out. Results are been summarized
separately for thermal variations, braking/traction and vertical bending and
combined finally to compare with the allowable stresses. Instead of doing moving
load analysis various static load cases were made by placing the train load at
different support locations in forward as well as reward direction. The total train
length was assumed to be 500m. In the first load case the train load starts from left
5. Case Study
5.1 Case 1
In this case the bearing arrangements are adopted in such a way that one abutment
is fixed and other abutment is free with all spans fixed at one end and free on the
other end (refer Figure 2a in Annexure 2). It was found that the proposed structural
arrangements are not sufficient to satisfy the stress criteria specified by IRS bridge
rules and results are summarised in Annexure 3.
5.2 Case 2
In this case the bearing arrangements are adopted such that the up track is fixed
and the down track is free at A1 and the up track is free and down track is fixed at
A2 (refer Figure 2a in Annexure 2). With this arrangement there was a reduction in
stress due to temperature variation but the stress due to breaking and traction was
found to be increasing which resulting in overall stresses crossing the permissible
limit. The results are summarised in Annexure 3
5.3 Case 3
In this case bearing arrangement is adopted such that both the abutments A1 and
A2 were kept fixed with centre pier P3 completely free and all the spans fixed at
one end and free on the other (refer Figure 2a in Annexure 2). This bearing
arrangement resulted in least compressive stress at the abutments and hence,
resulted in most economical design. The results are summarised in Annexure 3.
6. Results summary
Detailed results have been attached in the annexure and below have discussed the
comparison of the results for different cases. As it can be seen from the charts that
rail stress is exceeding the recommended value as per IRS Bridge rules fore Case
1 and Case 2. The absolute maximum displacement of the deck is coming to be
greater than 5mm limit prescribed in UIC 774-3R. Whereas the relative
displacement between the deck and the rail was found to be within limits for all the
three cases. Only case 3 for which both the abutments were kept fixed and the
centre pier as free satisfies both strength as well as the serviceability criteria.
Hence, this bearing arrangement was adopted for final construction.
7. Conclusion
With the requirement of LWR, the present study have been carried out with three
different cases and following are the conclusion drawn:
In case of long bridges if the stresses in the rail are beyond permissible
limits alteration of the bearing arrangement can be tried before going for
increase in structural dimensions or expansion device for rails.
As both the abutments are fixed a tensile stress is generated at both the
abutments due to vertical bending which negates the compressive stress
developed due to braking and traction.
Due to fixity at both the ends the stress due to temperature variation is
guided towards the free pier at the centre. Hence, the maximum stress
due to temperature and live load do not occur at the same location
resulting in reduction in overall stress.
8. References
1. UIC 774-3R October 2001: Track/Bridge Interaction – Recommendations for
calculations.