Transfer Truss
Transfer Truss
The
Transfer
Solution By Kurt D. Swensson, Ph.D., P.E., LEED AP
T
The Mansion on Peachtree contains many of the com-
plicating elements of typical mixed-use buildings using a stacked
configuration. The project includes a parking garage, elevated
motor court and garden, 142-key hotel, 15,000 gross sq. ft spa,
8,000 gross sq. ft banquet and meeting space, two restaurants, a bar,
three residential villas, and 41 high-rise luxury residential units.
The building is approximately 620 ft tall with a total of 46 occu-
pied levels. It uses a “wedding cake” scheme with steps in the floor
plan and column transfers at seven different floors. The design
stacks a 27-story residential building on top of a 15-story hotel
above a three-story parking deck. Only two of the columns from
the residential tower extend to the foundation, while 26 of the 38
tower columns transfer at the top of the hotel floors.
The project presented many design and construction challenges,
three of which had a significant impact on the transfer design.
1. Remove all interior columns from the hotel floors.
2. Maximize the number of saleable floors within the height limita-
tion while maintaining 12 ft, 3 in. clear height on the residential
floors.
3. Support a fast-tracked delivery process.
The combination of these requirements led to the use of struc-
tural steel transfer trusses at two of the seven transfer floors. At
these two levels, the transfers span more than 36 ft, support more
than 27 levels, and need to accommodate openings for utilities and
personnel. The use of traditional concrete beams was considered
for these conditions but was found to be unacceptable because
the resulting designs either increased the building height, limited
utilities and personnel movement, or could not accommodate the
fast track schedule.
Derek Owe
Project Challenges
Once the decision was made to use structural steel, the chal-
lenge was to determine the most efficient way to execute the plan.
The integral teamwork of the design team, owner, contractor, fab-
ricator, connection designer, and erector was the key to the suc-
cess of the plan. The following considerations were significant in
the analysis, design, and construction of the trusses—minimizing
transfer loads, controlling deflections, and minimizing impact on
the construction schedule.
Floor plan, left: Only two columns from the residential tower (shown
in red) and the concrete core extend to the foundation. All other 22
of the column loads from the top 27 floors are supported at the 16th
floor by steel transfer trusses and the four W40 sections at the corners
(shown in light blue). The supporting columns and walls below are
shown as dashed brown.
Controlling Deflections
Deflection criteria were developed accounting for the three-
dimensional behavior of the floor, the relative distance between
transferred columns, distance between transferred columns and the
core, and the allowance for tile on the floors above. The resulting
target deflection values varied from 0.25 in. to 0.5 in. for spans up
to 38 ft, 6 in. Analysis indicated that shortening in the compres-
sion chord was a significant contributor to the truss deflection. To
reduce the shortening the compression chords were designed to
act compositely with the 10-in. slab placed at that level. The result-
ing design reduced the weight of the top chord of the trusses by
The slab is being formed on the south side of the tower as truss erection between 60 to 70 lb per lineal ft.
continues on the north side. Integrated steel truss erection with slab place-
ment minimized the schedule impact of on-site truss erection. The only way
to transfer the column loads resulting from stepping the building in was to Constructability
use structural steel transfer trusses that are the full depth of the floor. Two major challenges shaped the construction of the trans-
fer system. The first was crane capacity, which was based on the
KSi Structural Engineers