Rate Analysis Part 1
Rate Analysis Part 1
F.Y. 2076/077
Item: Site Clearance
Refference: 1(4)
2
Unit : 1m
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos
2) Unskilled Nos 0.03 520.00 15.60
Total 15.60
B Materials
Total 0.00
C Tools and Plants
3% of labour 0.47
Total 0.47
Total of A+B+C NRs. 16.07
15% Contractors Profit & Overhead NRs. 2.41
RATE ANALYSIS
F.Y. 2076/077
Item: Earthwork excavation in foundation including 10m lead &1.5m lift
Refference: 2(2)
3
Unit : 1m
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos
2) Unskilled Nos 0.8 520.00 416.00
Total 416.00
B Materials
Total 0.00
C Tools and Plants
3% of labour 12.48
Total 12.48
Total of A+B+C NRs. 428.48
Total 0.00
RATE ANALYSIS
F.Y. 2076/077
Item: Wooden Formwork
Refference: 8-2-ka
2
Unit : 10 m
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 1.72 720.00 1238.40
2) Unskilled Nos 2.57 520.00 1336.40
Total 2574.80
B Materials
1) Wood m3 0.526 53332.95 4675.5
2) Nail kg 2.5 102.3 255.75
Total 4931.27
C Tools and Plants
Total 0.00
Total 86123.95
C Tools and Plants
Total 0.00
RATE ANALYSIS
F.Y. 2076/077
Item: 1:1.5:3 PCC work
Refference: 7-4-kha
3
Unit : 1m
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 0.80 720.00 576.00
2) Unskilled Nos 7.00 520.00 3640.00
Total 4216.00
B Materials
1) Cement Mt. ton 0.40 15735.8 6294.32
2) Coarse Aggregate m3 0.86 2877.132 2474.33
3) Fine Aggregate m3 0.425 3042.867 1293.22
Total 10061.87
C Tools and Plants
Total 0.00
Total 0.00
RATE ANALYSIS
F.Y. 2076/077
Item: Wood work for doors & windows panelled shutter
Refference: 10(2)
2
Unit : 2.124 m
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 10.00 720.00 7200.00
2) Unskilled Nos 1.00 520.00 520.00
Total 7720.00
B Materials
1) Wood m3 0.084 204106.50 17144.95
2) Hinges 4" No 6.00 25.00 150.00
3) Tower bolt 6" No 1.00 80.00 80.00
4) Handle 4" No 2.00 60.00 120.00
5) Locking set no 1.00 300.00 300.00
6) Screw LS 20.00 50.00
Total 17844.95
C Tools and Plants
Total 0.00
Total of A+B+C NRs. 25564.95
15% Contractors Profit & Overhead NRs. 3834.74
TOTAL NRs. 29399.69
Total 0.00
Total of A+B+C NRs. 18645.21
15% Contractors Profit & Overhead NRs. 2796.78
TOTAL NRs. 21442.00
RATE ANALYSIS
F.Y. 2076/077
Item: 50 mm thick 1:2:4 PCC flooring work
Refference: 11-1-ga
2
Unit : 10 m
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 1.25 720.00 900.00
2) Unskilled Nos 2.50 520.00 1300.00
Total 2200.00
B Materials
1) Cement Mt. ton 0.17 15735.80 2675.09
2) Coarse Aggregate m3 0.46 2877.13 1323.48
3) Fine Aggregate m3 0.23 3042.87 699.86
Total 4698.43
C Tools and Plants
Total 0.00
Total 0.00
RATE ANALYSIS
F.Y. 2076/077
Item: 20 mm thick 1:4 Cement/sand Plaster on ceiling
Refference: 12-4-kha
2
Unit : 100 m
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 14.00 720.00 10080.00
2) Unskilled Nos 23.75 520.00 12350.00
Total 22430.00
B Materials
1) Cement Mt. ton 0.81 15735.8 12746.00
2) Fine Aggregate m3 2.2 3042.867 6694.31
Total 19440.31
C Tools and Plants
Total 0.00
Total 12908.45
C Tools and Plants
Total 0.00
RATE ANALYSIS
F.Y. 2076/077
Item: Two coat of cement paint on wall
Refference: 13-4-kha
2
Unit : 100 m
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 5.00 720.00 3600.00
2) Unskilled Nos 5.00 520.00 2600.00
Total 6200.00
B Materials
1) Cement Paint Kg 48.50 71 3443.50
Total 3443.50
C Tools and Plants
Total 0.00
Total 3443.50
C Tools and Plants
Total 0.00
RATE ANALYSIS
F.Y. 2076/077
Item: Two coat of enamel paint over a coat of primer
Refference: 13-5-ka/kha/ga
2
Unit : 100 m
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 12.00 720.00 8640.00
2) Unskilled Nos 8.00 520.00 4160.00
Total 12800.00
B Materials
1) Primer Ltr 8.10 414.00 3353.40
2) Enamel Ltr 16 551.00 8816.00
Total 12169.40
C Tools and Plants
Total 0.00
Total 15872.00
C Tools and Plants
Total 0.00
RATE ANALYSIS
F.Y. 2076/077
Item: Glazed Porceline tile flooring on wall
Refference: 11(7)
2
Unit : 10 m
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 13.00 720.00 9360.00
2) Unskilled Nos 4.50 520.00 2340.00
Total 11700.00
B Materials
1) Tile m2 11.00 1420.32 15623.52
2) Cement Mt 0.056 15735.80 881.20
3) Sand m3 0.152 3042.87 462.52
4) White Cement kg 3.228 22.06 71.21
Total 17038.45
C Tools and Plants
Total 0.00
Total 26637.23
C Tools and Plants
Total 0.00
RATE ANALYSIS
F.Y. 2076/077
Item: 1:2:4 PCC
Refference: 7-2-gha
3
Unit : 1m
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 1.00 720.00 720.00
2) Unskilled Nos 4.00 520.00 2080.00
Total 2800.00
B Materials
1) Cement Mt. ton 0.32 15735.80 5035.46
2) Coarse Aggregate m3 0.85 2877.13 2445.56
3) Fine Aggregate m3 0.445 3042.87 1354.08
Total 8835.09
C Tools and Plants
Total 0.00
Total 2034.22
C Tools and Plants
Total 0.00
RATE ANALYSIS
F.Y. 2076/077
Item: M.S. Grill Work with 1 coat enamel paint
Refference: 12-B-ii
Unit : 1000 kg
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 14.000 720.00 10080.00
2) Unskilled Nos 4.000 520.00 2080.00
Total 12160.00
B Materials
1) M.S. Grill Work kg 1000.00 104.50 104500.00
2) Oil (Keresone) ltr 5.00 65.49 327.43
3) Enamel Paint ltr 12.230 551 6738.73
Total 111566.16
C Tools and Plants
3% of labour cost 364.8
Total 364.80
Total 12.18
C Tools and Plants
Total 0.00
RATE ANALYSIS
F.Y. 2076/077
Item: 7/22 copper wire for light point wiring
Refference:
Unit : 1m
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 0.010 720.00 7.20
2) Semiskilled Nos 0.015 670.00 10.05
3) Unskilled Nos 0.020 520.00 10.40
Total 27.65
B Materials
1) 7/22 Copper Wire m 1.00 28.48 28.48
Total 28.48
C Tools and Plants
Total 0.00
Total 10.34
C Tools and Plants
Total 0.00
RATE ANALYSIS
F.Y. 2076/077
Item: Supplying and fixing dome light
Refference:
Unit : 1 nos
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 0.050 720.00 36.00
2) Semiskilled Nos 0.050 670.00 33.50
3) Unskilled Nos 0.050 520.00 26.00
Total 95.50
B Materials
1) Dome light Nos 1.00 374 374.00
Total 374.00
C Tools and Plants
Total 0.00
Total 208.00
C Tools and Plants
Total 0.00
RATE ANALYSIS
F.Y. 2076/077
Item: Supplying and fixing 2 gang switch socket with 4"x4" metal box
Refference:
Unit : 1 nos
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 0.050 720.00 36.00
2) Semiskilled Nos 0.100 670.00 67.00
3) Unskilled Nos
Total 103.00
B Materials
1) 4"x4" metal box Nos 1.00 65.00 65.00
2) 2 gang switch socket Nos 1.00 242.00 242.00
Total 307.00
C Tools and Plants
Total 0.00
Total 374.00
C Tools and Plants
Total 0.00
RATE ANALYSIS
F.Y. 2076/077
Item: Supplying and fixing 4 gang switch socket with 4"x4" metal box
Refference:
Unit : 1 nos
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 0.050 720.00 36.00
2) Semiskilled Nos 0.100 670.00 67.00
3) Unskilled Nos -
Total 103.00
B Materials
1) 4"x4" metal box Nos 1.00 65.00 65.00
2) 4 gang switch socket Nos 1.00 441.00 441.00
Total 506.00
C Tools and Plants
Total 0.00
Total 506.00
C Tools and Plants
Total 0.00
RATE ANALYSIS
F.Y. 2076/077
Item: Supplying and fixing 4"x6"PVC junction box
Refference:
Unit : 1 nos
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 0.050 720.00 36.00
2) Semiskilled Nos 0.100 670.00 67.00
3) Unskilled Nos -
Total 103.00
B Materials
1) 4"x6" PVC junction box Nos 1.00 192.00 192.00
Total 192.00
C Tools and Plants
Total 0.00
Total 0.00
RATE ANALYSIS
F.Y. 2076/077
Item: Supplying and fixing sub distribution TPN DB Double Cover with 6-32 amp MCB
Unit : 1 nos
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 0.050 720.00 36.00
2) Semiskilled Nos 0.750 670.00 502.50
Total 538.50
B Materials
1) 8 way TPN D-B Nos 1.00 2061.00 2061.00
2) 6-32 Amp MCB's SSP Nos 1.00 309.00 309.00
Total 2370.00
C Tools and Plants
Total 0.00
Total of A+B+C NRs. 2908.50
15% Contractors Profit & Overhead NRs. 436.28
TOTAL NRs. 3344.78
RATE PER No. NRs. 3344.78
RATE ANALYSIS
F.Y. 2076/077
Item: Water Closet European type Pan ISI with low level cistern complete set
Unit : 1 nos
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 3.00 720.00 2160.00
2) Unskilled Nos 3.00 520.00 1560.00
Total 3720.00
B Materials
1) Water Closets European type
pan ISI Nos 1 6384.00 6384.00
2) P or S trap. Nos 1 138.00 138.00
3) 10.0 ltr.porcelain clay low
level flushing cistern
complete accessories Nos 1 2607.00 2607.00
4) 32mmx600mm size flushing
CP pipe Nos 1 400.00 400.00
5) 1.5x45 cm(½" x18") PVC pipe
connector Nos 1 195.00 195.00
6) screw, etc. LS 25.00 25.00
Total 9749.00
C Tools and Plants
Total 0.00
Total of A+B+C NRs. 13469.00
15% Contractors Profit & Overhead NRs. 2020.35
TOTAL NRs. 15489.35
RATE PER No. NRs. 15489.35
Prepared by: Checked By:- Approved By:
RATE ANALYSIS
F.Y. 2076/077
Item: 55x40cm Porcelain clay white glaze Wash basin complete set
Unit : 1 nos
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 2.00 720.00 1440.00
2) Unskilled Nos 2.00 520.00 1040.00
Total 2480.00
B Materials
1) 55x40cm Porcelain clay white
glaze Wash basin Nos 1 1900.00 1900.00
2) Bracket Nos 1 230.00 230.00
3) 32 mm pvc bottle trap
including 32mm CP waste
coupling with CP chain and
rubber plug etc. Nos 1 1000.00 1000.00
4) 15 mm fancy type CP pillar
cock Nos 1 1950.00 1950.00
5) 1.5x45Cm (½"x18") PVC
pipe connector Nos 1 195.00 195.00
6) Screw etc LS 25.00 25.00
Total 5300.00
C Tools and Plants
Total 0.00
Total of A+B+C NRs. 7780.00
15% Contractors Profit & Overhead NRs. 1167.00
TOTAL NRs. 8947.00
RATE PER No. NRs. 8947.00
RATE ANALYSIS
F.Y. 2076/077
Item: 46.5x35.5x26.5 cm White glaze flat back Urinal
Refference:
Unit : 1 nos
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 2.00 720.00 1440.00
2) Unskilled Nos 1.00 520.00 520.00
Total 1960.00
B Materials
1) 46.5x35.5x26.5 cm White
glaze flat back Urinal Nos 1 2100.00 2100.00
2) Waste coupling 32mm Nos 1 195.00 195.00
3)
½" x18" Pvc pipe connector Nos 1 195.00 195.00
4) Screw etc. LS 1 25.00 25.00
Total 2515.00
C Tools and Plants
Total 0.00
Total 0.00
RATE ANALYSIS
F.Y. 2076/077
Item: Solid Cocrete Block Paving
Refference: 11-(10)
2
Unit : 10 m
S.N. PARTICULAR UNIT QUANTITY RATE AMOUNT REMARKS
A Labour
1) Skilled Nos 1.5 720.00 1080.00
2) Unskilled Nos 4.5 520.00 2340.00
Total 3420.00
B Materials
1) Concrete Block Nos 250 19 4750.00
2) Cement Mt. ton 0.056 15735.8 881.20
3) Sand m3 0.152 3042.867 462.52
Total 6093.72
C Tools and Plants
Total 0.00
Total 19440.31
C Tools and Plants
Total 0.00