Sample Projects For Project Management Assignment

The document outlines the project management plan for constructing a house in Oman City. It discusses the project background, objectives, team members and their roles. It also outlines the project stages and key deliverables, including define, design, develop and deliver. It provides details on project time management, including the work breakdown structure, Gantt chart, network diagram and critical path. Finally, it discusses the project budget and quality plan. The overall goal is to construct the house by July 30, 2019 within the budget of OMR 130,000.

Uploaded by

manoj kumar Das
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
94% found this document useful (16 votes)
28K views28 pages

Sample Projects For Project Management Assignment

The document outlines the project management plan for constructing a house in Oman City. It discusses the project background, objectives, team members and their roles. It also outlines the project stages and key deliverables, including define, design, develop and deliver. It provides details on project time management, including the work breakdown structure, Gantt chart, network diagram and critical path. Finally, it discusses the project budget and quality plan. The overall goal is to construct the house by July 30, 2019 within the budget of OMR 130,000.

Uploaded by

manoj kumar Das
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 28

PROJECT

MANAGEMENT
[Document subtitle]
Table of Contents
Introduction................................................................................................................................ 2
Project Background and Objectives...................................................................................2
Project Background.............................................................................................................. 2
Project Objectives................................................................................................................. 3
Project Team Members and their key roles....................................................................3
Project Stages and Key Deliverables................................................................................ 4
Project Time Management.................................................................................................... 7
Work Breakdown Structure............................................................................................... 7
Gantt chart............................................................................................................................13
Network Diagram............................................................................................................... 18
Critical Path.......................................................................................................................... 19
Project Budget.........................................................................................................................20
Project Quality Plan............................................................................................................... 23
Project Quality Responsibilities.....................................................................................23
Quality Criteria.................................................................................................................... 23
Quality Methods.................................................................................................................. 24
Project Risk Register............................................................................................................. 26
Conclusion................................................................................................................................ 27
References........................................................................ Error! Bookmark not defined.

1
Introduction

This project is about "House construction" project management plan. The

project management plan covers different aspects of house development

project. The first thing discloses in the paper is project background and

objectives. It will serve as a guide for the readers to understand the scenario

of the whole project. Moreover, it also covers the role of its key deliverables

and stakeholders. The roles and responsibilities of project team members are

discussed in respect of project key deliverables. Moreover, the paper also

covers an important part of project management plan which is project time

management. The main motive behind the discussion of project time

management is to understand project work breakdown structure, Gantt chart,

network diagram and critical path as well. At last, the project covers the

budget and quality plan for the project. All these aspects are studied under

the study of previous research sources. Moreover, the project time

management and project budget are prepared through the use of advanced

software which is MS project and MS Excel. Both of these tools are an

important source of the plan the overall schedule of a particular project.

Project Background and Objectives

Project Background

The project is about the preparation of a complete house at Oman City. The

premises shall be handed over to the owner no later than 1st August 2019.

The contract price for the project will remain OMR 130,000. Generally, the

2
house will prepare as per the requirements of the owner. It will include a

ground floor with four different rooms, one kitchen, and one washroom set.

Apart from this, it will also include construction of the first floor with 3

different rooms and one set of the kitchen as well as washrooms. The house

will properly cover with latest tiles and appropriate design and structure. It

will involve the ground works, materials, structure, project management,

interior, services, signoff, and exterior systems. Moreover, it also has a pool

and garden for the entertainment of family members.

Project Objectives

The project objective is to prepare a well-organized house Design

Complete the project on 30th July 2019.

Accomplish the project within the budget of OMR 130,000.

Project Team Members and their key roles

The project involves a large number of project team members. It is because

the home needs to construct within the one year from its initial starting date.

The key project team member involved in the project is following:

Owner: The owner is the person who responsible for the whole management

and evaluation of his or her house. The owner will sponsor the Housing

construction team members to build his or her house (Alwan, 2017). He or

she will remain responsible for providing necessary funds.

3
Design-Builder: These are the team members who will remain responsible

for the overall structural design of the project and will oversee the activities

done by the labor and another person.

Architect: The architect will prepare the effective blueprint of the owner

house so that he or she can live effectively with all facilities.

Civil Engineer: These are the individual who directly responsible for the

evaluation of construction work. They will guide the team members in

performing their tasks and responsibilities (Banihashemi, 2017). This group

involves electrical, structural, project manager, mechanics, and various other

people.

Landscape: The landscaping team is responsible for landscaping task. It

involves the construction of yard, garden and pool which will perform by plan

mechanics, and other labors (Clevenger, 2017).

Project Stages and Key Deliverables

The project stages and its key deliverables can understand with the help of

the 4D model of project management. It is an exciting and appropriate

concept for the management of housing and other complex projects

(Burtonshaw-Gunn, 2017).

4
(Kerzner, 2017)

Define

The "Housing Construction" project is conducted with a sole aim of prepares

an attractive and best design house with the presence of a garden, pool, and

two different floors. It will start on the 1st of May 2018 and finish on 30th July

2019. It will consume the construction process of one year and three months.

In order to accomplish the project as per predetermined timeline, the project

management team will keep strict towards their goals and deadline as well.

Design

The design of the house will be unique and different from other nearby

houses. The project will integrate with following design:

Spacious kitchen with plenty of storage

5
Creation of keeping rooms

Master bath

Bedroom on both floors (Mubarak, 2015)

Covers entrance

Attractive design pool with best tiles

Garden with plenty of plants

Development

The project development will perform as per the below-mentioned procedure:

6
From the above-mentioned figure, it can clarify that the implementation

process of the house will proceed accordingly. The contractor will remain

responsible for the continuous evaluation of Groundworks, materials,

structure, and project management procedure of the project so that any

delay can avoid effectively (Marsh, 2015).

Deliver

The project delivery will perform by sharing the project quality and progress

report (Merschbrock, 2015). It will give surety to the client about the project

specifications. At this stage, the owner takes the responsibility of his or her

home and makes necessary payments if anything left.

Project Time Management

Work Breakdown Structure

Mubarak (2015) said that the work breakdown structure represents the

overall activity involved in the accomplishment of a project. The work

breakdown structure for "Housing Construction" project is prepared through

the use of advanced software known as MS Project. It is an important method

of preparing work breakdown structure with required specifications

(Merschbrock, 2015). The work breakdown structure for housing construction

project can understand with a below-mentioned table:

Task Duratio Predecess Resource


Task Name Start Finish
Mode n ors Names

7
Auto House
310 Tue Mon
Schedu Construction at
days 5/1/18 7/8/19
led Oman

Auto
Conduct 100 Tue Mon
Schedu
Ground Work days 5/1/18 9/17/18
led

Auto
Concrete Tue Mon
Schedul 55 days Laborer
works 5/1/18 7/16/18
ed

Auto
45 Tue Mon
Schedu Excavation
days 7/17/18 9/17/18
led

Auto Plant
Tue Mon
Schedul Pool 15 days 3 Mechanic,
7/17/18 8/6/18
ed Site Joiner

Auto
Tue Mon
Schedul Foundation 30 days 5 Client
8/7/18 9/17/18
ed

Auto
Perform 90 Tue Mon
Schedu
Landscaping days 9/18/18 1/21/19
led

Auto Pool 40 days Tue Mon 5,6 Laborer

8
Schedul 9/18/18 11/12/1

ed 8

Auto Tue Mon


Plant
Schedul Yard 20 days 11/13/1 12/10/1 8
Mechanic
ed 8 8

Auto Tue
Mon Plant
Schedul Gardens 30 days 12/11/1 8,9
1/21/19 Mechanic
ed 8

Auto Tue
Arrange 80 Mon
Schedu 12/11/1
Materials days 4/1/19
led 8

Auto Tue
Project Mon
Schedul 25 days 12/11/1 9 Laborer
Management 1/14/19
ed 8

Auto
Tue Mon Plant
Schedul Storage 40 days 10
1/22/19 3/18/19 Mechanic
ed

Auto
Tue Mon
Schedul Delivery 10 days 12,13 Site Joiner
3/19/19 4/1/19
ed

Auto Give 86 Tue Tue

Schedu Structure days 9/18/18 1/15/19

9
led

Auto Fri
Tue Steel
Schedul Timber 44 days 11/16/1 6
9/18/18 structural
ed 8

Auto Mon Tue

Schedul Masonry 22 days 11/19/1 12/18/1 16 Site Joiner

ed 8 8

Auto Wed
Tue Steel
Schedul Steel 20 days 12/19/1 17
1/15/19 structural
ed 8

Auto
Design House 61 Wed Wed
Schedu
Interior days 1/16/19 4/10/19
led

Auto
Wed Wed Painter and
Schedul Lining 26 days 18
1/16/19 2/20/19 Decorator
ed

Auto
Thu Wed
Schedul 10 days 20 Laborer
Kitchen/Bathroom 2/21/19 3/6/19
ed

Auto
Thu Wed
Schedul Storage 10 days 21 Roofer
3/7/19 3/20/19
ed

10
Auto
Thu Wed Painter and
Schedul Decorating 15 days 22
3/21/19 4/10/19 Decorator
ed

Auto
Arrange 48 Thu Mon
Schedu
Services days 2/21/19 4/29/19
led

Auto
Thu Wed
Schedul Plumbing 5 days 23 Laborer
4/11/19 4/17/19
ed

Auto
Thu Mon
Schedul Electrical 8 days 25 Electrician
4/18/19 4/29/19
ed

Auto
Thu Tue
Schedul Data 4 days 20 Site Joiner
2/21/19 2/26/19
ed

Auto
Wed Mon
Schedul 9 days 27 Site Joiner
Entertainment 2/27/19 3/11/19
ed

Auto
Tue Wed
Schedul Security 12 days 28 Client
3/12/19 3/27/19
ed

Auto Pool 17 days Thu Fri 29 Roofer

11
Schedul 3/28/19 4/19/19

ed

Auto
Perform 56 Mon Mon
Schedu
Cladding days 4/22/19 7/8/19
led

Auto
39 Mon Thu
Schedu Roofing
days 4/22/19 6/13/19
led

Auto
Mon Thu
Schedul Tiling 19 days 30 Roofer
4/22/19 5/16/19
ed

Auto
Fri Thu
Schedul Insulation 20 days 33 Roofer
5/17/19 6/13/19
ed

Auto
56 Mon Mon
Schedu Walls
days 4/22/19 7/8/19
led

Auto
Mon Thu Plant
Schedul Exterior 24 days 30
4/22/19 5/23/19 Mechanic
ed

Auto Fri Mon


Insulation 32 days 36 Electrician
Schedul 5/24/19 7/8/19

12
ed

Auto
Mon Thu
Schedul Joinery 14 days 30 Client
4/22/19 5/9/19
ed

Auto
Fri Thu Painter and
Schedul Paint 15 days 38
5/10/19 5/30/19 Decorator
ed

Auto
Thu Thu
Schedul Project closure 0 days 39 Client
5/30/19 5/30/19
ed

Activity list

WBSID Activity Predecesso Duration in Resource


Task Name
rs Weeks Type

House

Construction at

Oman

Conduct 1

Ground Work

1.1 Complete
Concrete
foundation
works
s

13
1.2 Complete

Excavation Excavatio

ns

Pool 1.2.1

Foundation 1.2.2

2 Complete

Perform landscapi

Landscaping ng

package

Pool 2.1

Yard 2.2

Gardens 2.3

3 Perform

effective
Arrange
material
Materials
managem

ents

3.1 Perform

Project project

Management manageme

nt

Storage 3.2

14
Delivery 3.3

Give 4 Complete

Structure structure

Timber 4.1

Masonry 4.2

Steel 4.3

5 Effective

completio
Design House
n of
Interior
house

interior

Lining 5.1

5.2

Kitchen/Bathroom

Storage 5.3

Decorating 5.4

6 Get best
Arrange
house
Services
services

Plumbing 6.1

Electrical 6.2

Data 6.3

15
Entertainment 6.4

Security 6.5

Pool 6.6

7 Exterior

cladding

Perform systems

Cladding and

decoratio

Roofing 7.1

Tiling 7.2

Insulation 7.3

8 Ensure

effective
Walls
design of

walls

Exterior 8.1

Insulation 8.2

Joinery 8.3

Paint 8.4

9 Perform
Project closure
project

16
closing

facilities

Gantt chart

The below-mentioned figures represent the Gantt chart for the “Housing

construction” Project. It is also prepared through the effective use of MS

project management software.

Figure 1

Figure 2

17
Figure 3

Network Diagram

The Network Diagram for the “Housing Construction project” can understand

through the below-mentioned figures:

Figure 1

18
Critical Path

The Critical Path for the “Housing Construction project” can understand

through the below-mentioned figures:

Figure 1

19
Figure 2

Figure 3

Project Budget

The project budget can understand through the below-mentioned table

prepared by using the MS Excel:

Budget
Task Name
(OMR) Total (OMR)

House Construction at 128600

20
Oman

Conduct Ground

Work

Concrete works 49600 49600

Excavation

Pool 23200

Foundation 23200 46400

Perform Landscaping

Pool 54400

Yard 17400

Gardens 18000 89800

Arrange Materials

Project Management 3000

Storage 5000

Delivery 2000 10000

Give Structure

Timber 124000

Masonry 60000

Steel 41000 225000

Design House

Interior

Lining 29600

21
Kitchen/Bathroom 42200

Storage 9900

Decorating 54000 135700

Arrange Services

Plumbing 5000

Electrical 6000

Data 7000

Entertainment 9000

Security 7500

Pool 14000 48500

Perform Cladding

Roofing

Tiling 38600

Insulation 14900 53500

Walls

Exterior 47200

Insulation 14800

Joinery 33600

Paint 27000 122600

Project closure 6000 6000

22
On the basis of the above-mentioned project schedule, it can clearly

understand that the project can finish within the predetermined budget. It

will consume the total cost of OMR128, 600.

Project Quality Plan

Project Quality Responsibilities

The project owner delegated the project quality responsibility to

management levels of the project. In order to construct a good house, the

project contractor, supervisory team, and engineering manager will remain

responsible. The project contractor will ensure that the project outcomes

effectively represent the owner specifications (Kerzner, 2018). On the other

hand, the project manager will oversee the speed, efficiency, and economical

completion of the overall project to avoid any unnecessary delay. Moreover,

the engineering manager will ensure the project quality by continuous

evaluation of project execution plan, construction process, and engineering

codes and standards (Nicholas, 2017).

Quality Criteria

The quality of new house will judge on the basis of below-mentioned aspects:

Quality assurance Criteria Key aspects

In General Age of the building

Building layout

Building size and type

23
The condition of Structure

Interior (Oakland, 2017)

Structure Structural span

Construction Technology

Common Areas Building Entrance

Corridor, and Stairs

Building Lot Pool

Garden

Parking space

Presence and quality of

common areas like washroom,

kitchen, and bedroom (Sears,

2015)

Other Utilities (Public Water supply,

Garbage disposal, heating,

electricity, sewage, and

streets)

Fire Escape and Protection

Quality Methods

In order to evaluate the quality of the project, the two important methods

will follow here. These methods are following:

24
Process Checklists: At this stage, a list of critical tasks will prepare to

evaluate it against the predetermined work breakdown structure. This

will give information about any tendency in project accomplishment

and breakdown schedule (Tedla, 2018).

Comparison of project outcomes against standard Criteria: Here, the

project outcomes will compare the above-mentioned standard criteria

to find any problem.

Project Quality Register

QUALITY REGISTER FORM


Ref: Ve
Programme Name: Project Name: House Constru
Project Management

Quality Identifier: Product Identifier:


1 1.1

Product Title: Quality Method:


Ground works Quality review

Roles/Responsibilities: Result:
Quality reviews and Project audit team members Pass

Quality Records: DATES


Continuous Evaluation Planned

Quality 1st July

25
Activity

Sign-Off 30th July

Project Risk Register

The project is covered with a large number of risk factors. It can understand

through the below-mentioned risk register:

RISK REGISTER FORM


Ref: Vers
Programme Name: Project Name: House Construct
Project Management

Risk Identifier: Risk Description:


001 Failure to identify the project dependency on other team
members

Probability: Impact: Expected Value:


3 High High
Risk Response Category:
Reduce
Risk Response:
Outline dependency to avoid any confusion
Date Registered: Risk Author: Risk Owner: Risk Action:
16th August Project Management Project Project
Team Management Management Tea
Team

26
Conclusion

On the basis of the above-mentioned analysis, it can be concluded that the


success chances of the project are high than its failure. It is because the
owner needs not to hire a big team for its management. Moreover, the
project schedule and budget structure should effectively follow by the team
to avoid any unnecessary delay and cost overrun problem. This will enhance
the quality of generated project outcomes.