Grid Code Compliance For Integrating 50 MW Wind Farm Into Dhofar Power Grid
Grid Code Compliance For Integrating 50 MW Wind Farm Into Dhofar Power Grid
net/publication/343893919
Grid Code Compliance for Integrating 50 MW Wind Farm into Dhofar Power
Grid
CITATIONS
7 authors, including:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Omar H. Abdalla on 26 August 2020.
1
Oman Electricity Transmission Company, Oman
2
Helwan University, Egypt
3
Rural Area Electricity Company, Oman
4
Masdar, Abu Dhabi
5
Tractebel Engineering, Dubai
* [email protected]
Abstract: This paper addresses the impact of the first 50 MW wind farm project on the Dhofar network. The
wind farm consists of 20×2.5 MW wind turbines and will be integrated into the 132 kV Dhofar network which is
connected with the Maim Interconnected System through the Petroleum Oman Development grid. A model of the
entire power system of Oman is developed for steady-state and dynamic studies using DIgSILENT software.
Two types of generators are considered: doubly-fed induction generator and asynchronous generator with fully
rated converter technology. Simulation results are presented including load flow, short-circuit, contingency and
stability analyses. No adverse effects ware identified due to the wind farm connection to the Dhofar
network. The currently applicable Grid Codes in most Gulf Cooperation Council (GCC) countries are focused
on the connection of conventional synchronous generators but recently increasing number of non-synchronous
renewable generators are being commissioned in the region. The results of this analysis can provide a basis in
the future for updating existing OETC Grid Code elements and for assessing future non-synchronous
connections.
152
th st
Proceedings of the 12 GCC-Cigre International Conference and the 21 Exhibition for Electrical Equipment, GCC-Power,
Paper A 204, pp. 152-161, 8-10 November, 2016.
elements are necessary for the connection of AVR has been considered on the 132/33 kV
renewable generation due to the technologies transformer and a station controller have been
deployed being non-synchronous plants. All system defined as shown in Figure 1. The AVR of the
studies of the paper were performed by using the 132/33 kV OLTC transformer (tap range -19/+1) is
DIgSILENT professional software version 15.2. used to control the 33 kV collector bus bar. The
33/0.69 kV transformers of the wind turbine (tap
The paper is structured in the following sections: range -2/+2) have been considered as not equipped
Section 2 provides a detailed overview of the with AVR and on fixed position for the study. The
Dhofar 50 MW wind farm and the basic station controller controls the reactive power
requirements for meeting compliancy under the outputs of the wind farms. It is set to control either:
Connection Condition of Schedule 2, and control the power factor, reactive power or voltage at the
structure. Section 3 presents the results of power point of common coupling. Each of the three
factor/reactive power/voltage control at the Point of control modes can be selected.
Common Connection (POC). Section 4 describes
the fault ride through performance of the wind farm Two different technologies have been deployed for
while Section 5 describes the power-frequency assessment; these are the Double Fed Induction
control performance of the wind farm. Section 6 Generator (DFIG) and Full Rated Converter (FRC)
presents a high-level overview of the power quality wind turbines. The requirements of the Connection
requirements. Section 7 summarizes the main Conditions of Schedule 2 Draft 5 for power
conclusions. factor/reactive power/voltage control are shown in
the Figure 2 and Figure 3. The dotted line indicates
2. Technical Requirements and Wind a constant power factor of 0.95 lead and lag during
Farm Layout the entire MW output of the wind farm (Points A-
D-E). Thus for example at rated power output; the
The Dhofar wind farm consists of 20 x 2.5 MW corresponding reactive power output (Q/Pmax) will
wind turbines consisting in total of three arrays. be + 0.33 lag and - 0.33 lead (This corresponds to
Each wind turbine has a 33/0.69 kV transformer 50 MW with ± 16.5 MVAr range) which indicates
which feeds the power into the 33kV wind farm a 0.95 lead/lag requirement. For reactive power
cable network. The total power of the wind park is control (Points A-B-C-D-E), the requirement is that
then collected at the 33kV collector substation, of a constant MVAr output (Q/Pmax) of - 0.33 lead
which then exports the power to the 132 kV and + 0.33 lag, which corresponds to ± 16.5 MVAr
network in Dhofar via a 132/33kV transformer. For over the operating range of Pmax to 0.2 Pmax. Any
all intents and purposes the point of connection is MW output below 0.2 Pmax is subject to a ± 0.606
at the 132 kV busbar within the wind farm gradient.
substation. For the Grid Code compliance study, an
153
th st
Proceedings of the 12 GCC-Cigre International Conference and the 21 Exhibition for Electrical Equipment, GCC-Power,
Paper A 204, pp. 152-161, 8-10 November, 2016.
The wind farm must be capable of providing its full being able to control is leading capability from 0 to
reactive range for lead and lag over a voltage range + 0.33 pu lag. If the system voltage of is above 1.06
of 0.9 to 1.1 pu, as shown in Figure 3. If the voltage pu, it will only require to provide its maximum (Q /
is in the range of 0.94 to 1 pu, it must be capable of Pmax) lead limit.
providing up to its (Q / Pmax) limit of + 0.33 lag, but
being able to control its leading capability from 0 For the Fault Ride Through requirements: the fault
to - 0.33 pu lead. Below a system voltage of 0.94 will be at the POC using a three phase to ground
pu, it will only require to provide its maximum (Q / fault lasting for 500 ms, where the voltage recovery
Pmax) lag limit. If the system voltage is between the must reach 90% of its nominal voltage within 3
range of 1 to 1.06 pu, it must be capable of seconds and remain connected. Figure 4 shows the
providing up to its (Q / Pmax) limit of -0.33 lead, but requirements of the fault ride through at the POC.
154
th st
Proceedings of the 12 GCC-Cigre International Conference and the 21 Exhibition for Electrical Equipment, GCC-Power,
Paper A 204, pp. 152-161, 8-10 November, 2016.
155
th st
Proceedings of the 12 GCC-Cigre International Conference and the 21 Exhibition for Electrical Equipment, GCC-Power,
Paper A 204, pp. 152-161, 8-10 November, 2016.
It can be seen that in both cases all wind turbines Both wind farm technologies are capable of
remain connected even if the voltage at the point of meeting the technical connection requirement of
connection responds to the voltage profile of the Connection Condition Schedule 2 Draft 5 [3]. The
connection condition. This was carried out for 60% power reduction/increase based on the droop
different grid strengths and all gave rise to similar setting is 19.5 MW and 9 MW respectively. This is
results. This suggests that both wind farm based on the assumption that there is sufficient
technologies (via their specified control system) are wind speed for this operation. Both technologies
compliant against the technical criteria for fault technically meet the requirements within 5 seconds
ride through. and it is sustained for 30 seconds.
5. Power Frequency Control It should be noted that the FRC meets the response
faster due to the control system being deployed,
Primary response analysis was carried out against while the DFIG has a slower response to reach its
the equivalent grid and the Dhofar network model. default full MW output steady state value. This is
Under the Dhofar network model, every generator predominately due the control system deployed, its
on the system will respond to a step response to response and ramp rates being used, but in theory
both voltage and frequency: based upon their can be set to meet a faster steady state value.
control characteristics. Thus an equivalent model
ensures that the wind farm is tested to its full The Dhofar network model was used to study the
capability under a frequency deviation. The results wind farm response with other generators on the
of the DFIG & FRC models are shown in Figure 8 system. The loss of approximately 30 MW was
and Figure 9 to a frequency step change using the considered sufficient for demand disconnection
equivalent grid. during the winter period, while the largest unit loss
was considered adequate for generation loss.
156
th st
Proceedings of the 12 GCC-Cigre International Conference and the 21 Exhibition for Electrical Equipment, GCC-Power,
Paper A 204, pp. 152-161, 8-10 November, 2016.
The results for the loss of generation and demand Dhofar network. Similar responses were recognised
are studied. Figure 10 shows the system response by both wind farm technologies (DFIG and FRC).
to a loss in demand. The top graph shows the From the results it can be seen that the wind farm
system frequency, the middle shows the active responds well to the Dhofar network model
power of the wind farm and the bottom graph accompanied by other generators.
shows the response of the other generators in the
157
th st
Proceedings of the 12 GCC-Cigre International Conference and the 21 Exhibition for Electrical Equipment, GCC-Power,
Paper A 204, pp. 152-161, 8-10 November, 2016.
Figure 10: Primary Frequency (Under frequency) capability with respect to the Dhofar network
Modelling Requirements:
A generic 132 kV tower has been used to improve
the accuracy of the power system model for the
power quality assessment. This enables the lumped
overhead line parameters to be converted to an
Impedance matrix based on phases, height and Figure 11: Generic 132 kV Tower dimension
tower type. The modelling is essential for all the
158
th st
Proceedings of the 12 GCC-Cigre International Conference and the 21 Exhibition for Electrical Equipment, GCC-Power,
Paper A 204, pp. 152-161, 8-10 November, 2016.
DIgSILENT software is used to calculate the (c) Power Factor Correction: This is the total
natural impedance matrix in ohm/km leading for a power factor correction of the demand and
double circuit three phase line construction with a of the low voltage network.
one earth wire [6]. Twin YEW 400 mm2 conductor (d) Resistive MW is the total amount of
132 kV line, has the following characteristics and resistive damping applicable at harmonic
has been used as reference. The sequence phasors frequencies.
(PPS-Positive phase sequence, NPS-Negative
phase sequence and ZPS-Zero phase sequence) per Voltage Unbalance: Figure 12 shows the negative
circuit per tower can be determined as: phase sequence voltages calculated for an intact
network, under a planned outage condition with
V1 PPS Z11 Z12 Z13 Z14 Z15 Z16 I1 PPS and without Dhofar wind farm at maximum
V I
1 NPS Z 21 Z 22 Z 23 Z 24 Z 25 Z 26 1 NPS
conditions. It can be seen that under all conditions
V1 ZPS Z 31 Z 32 Z 33 Z 34 Z 35 Z 36 I1 ZPS specified that under a planned outage, the level of
voltage unbalance increases for all sites from its
V2 PPS Z 41 Z 42 Z 43 Z 44 Z 45 Z 46 I 2 PPS intact pre-fault values. The SFZ substation tends to
V2 NPS Z 51 Z 52 Z 53 Z 54 Z 55 Z 56 I 2 NPS
have the highest reading, predominately due to high
V2 ZPS Z 61 Z 62 Z 63 Z 64 Z 65 Z 66 I 2 ZPS power flows as well as being the connection point
of Octal Petrochemicals. However in all conditions
V, Z, I are the voltage, impedance and current the level of voltage unbalance is below 1%, making
phasors, while the numerical subscripts relates the it compliant against the Grid Code. The worst
self and mutual impedance between each phase of condition for the Dhofar WF Substation is when the
each circuit. PDO interconnector is out of service, as this leads
to a 0.25% increase in NPS voltage at Dhofar WF
The complete overhead line model is based upon a Substation.
frequency dependant distributed model, as this
gives rise to the highest accuracy for the impedance
matrix which is ideal for all studies listed [6]. The
frequency dependant model is based on the
Bergeron´s method in where the characteristic
impedance and propagation constant has to be
determined.
159
th st
Proceedings of the 12 GCC-Cigre International Conference and the 21 Exhibition for Electrical Equipment, GCC-Power,
Paper A 204, pp. 152-161, 8-10 November, 2016.
Table (2): Flicker Severity Results. used to calculate the voltage (%) distortion at each
Wind IEC harmonic level. The results for the FRC are shown
Flicker C(ΨK,va) Compliant
Farm Limit below based on standard harmonic injections for
Pst: 33kV 1.11 0.085 0.6/0.8 YES this type of technology.
Pst: 132kV 1.11 0.1087 0.6/0.8 YES
160
th st
Proceedings of the 12 GCC-Cigre International Conference and the 21 Exhibition for Electrical Equipment, GCC-Power,
Paper A 204, pp. 152-161, 8-10 November, 2016.
161