Heat and Mass Balance Index: S.N. Topics Page Nos
Heat and Mass Balance Index: S.N. Topics Page Nos
INDEX
BOILER EFFICIENCY
5 38 - 42
CALCULATIONS
If the Heat Value of Coal is 4000 kCal/kg, = 2396 / 4000 = 0.599kg of coal
then Coal Rate i.e. coal required to generate
one unit of electricity (1 kWH)
If the losses increase, the heat rate will also increase and the coal required will also
increase, thereby increasing the cost of generation.
In thermal power plant, Chemical Energy of fuel is converted to electrical energy. The
conversion cycle is based on Thermodynamic Vapor Cycle, called Rankine Cycle.
Conversion takes place through various stages and different processes are involved for
the purpose. Due to the various limitations nature has imposed, such as Irreversibility in
the process, heat losses to atmosphere, Friction losses, Heat Transfer losses, to name a
few, efficiency of conversion is always less than 100%. In addition to these losses, some
heat energy is rejected because, steam temperature and pressure drop to such low values
(after doing work in Turbine), that further conversion to useful work is not possible. Due
to all these reasons, energy input is much more for one kWh electrical energy output
from the Generator. If the Chemical / Electrical conversion process should have been
100% efficient, 860 Kcal heat energy input should have given one kWh electrical energy
out put at Generator terminals. This ratio of Electrical Energy Output over a certain period
of time to Chemical Energy input to the Plant over the same period is called Heat rate.
In modern plants, designed for High temperature and pressure Steam admission to
Turbine, efficiency and heat rate can be around 36% and 2400 Kcal/ KWh respectively.
total output power solutions Manohar Tatwawadi Page 3
The term “Heat rate” is defined in many ways as follows:
Net Unit Heat rate: It is the ratio of energy input to Boiler in terms of Heat energy of
fuel, for one kWh of electrical energy output at Bus Bars, i.e. after UAT. If the out put
and input is considered for a period of an hour, then it is Net Unit Heat rate for one
Hour. Similarly, it can be calculated over a period of a Day, a Week, a Month or a Year.
In this case, it is the sent out energy that is considered, hence, consumption of electrical
energy for driving the plant’s auxiliaries is also accounted for.
Gross Unit Heat rate: It is the ratio of energy input to Boiler in terms of Heat energy of
fuel, for one kWh of electrical energy output at Generator Terminals. In this case,
auxiliary consumption is NOT accounted for.
Net Turbine Cycle Heat rate: It is the ratio of heat energy contained in steam admitted
to Turbine for one kWh of electrical energy output at Generator Terminals. In this case,
auxiliary consumption and losses in Boiler are NOT accounted for.
Operating Heat rate: It is the heat rate calculated by considering the inputs and outputs
from the plant only when it is synchronized with the grid. In this case, the fuel input
required for steam conditioning, from light up to synchronization is not considered. Also
auxiliaries consumption during the period of plant shut down is not considered.
The plant is designed to generate electricity at certain design heat rate. Deviations from
design values give a valuable information regarding the operational and maintenance
practices. Also, by comparison with the historical data, decisions can be taken while
making investments on the maintenance and renovation. Also, problem area can be
identified and analyzed for improvements. A deviation in Gross Turbine Cycle heat rate
tells us about energy conversion scenario in turbine, including condenser and
regenerative feed heating process. If Net average unit heat rate deviates from that of
design, it tells us how much extra amount of energy is put in and how much money is
“wasted”.
Net Unit Heat rate, for given time period, is calculated by the formula,
(Coal Consumption × Its Calorific Value) +( Oil Consumption × Its Calorific Value)
------------------------------------------------------------------------------------------
Generation measured at Bus Bars
To measure coal consumption accurately is very difficult. Also the calorific value of coal
varies and its continuous, on line measurement is not possible.
Hence, in normal practice, unit heat rate is calculated by the simpler method:
Unit Heat rate = Turbine Cycle Heat rate / Boiler Effi. calculated by loss method.
((Sp. Enthalpy of S.H. Steam at Boiler Outlet Total Steam Flow Rate to H.P.T.) –
(Sp. Enthalpy of Feed Water at economizer inlet Feed Water Flow rate at
economiser inlet))
+ (Sp. Enthalpy of R.H. Steam at Reheater outlet – Sp. Enthalpy of C.R.H. steam
at Reheater inlet) Reheat Steam Flow
+ (Sp. Enthalpy of S.H. Steam at Boiler Outlet – Sp. Enthalpy of S.H. spray)
S. H. Attemperator Flow
Values of temperature, pressure and flow rate are known from instrumentation and
specific enthalpy can be known from Steam tables. The value of generation is known
from the Energy Meters. If reading of energy meter connected to Generator terminals is
considered in this formula, the heat rate obtained is Gross Heat rate and if that from Bus
Bar energy meter is considered, then it is the net heat rate.
For method of calculation of Boiler efficiency by loss method pl. refer the chapter on the
topic.
5) Condenser Vacuum
7) Boiler efficiency
Tm1 is Mean temperature of steam admission = (h1 - h4s) / (s1 - s4s). (3)
h1 & s1 are specific enthalpy and entropy of steam at admission temperature and
pressure, h4s and s4s are the Sp. Enthalpy & entropy of feed water at Economiser inlet.
2) Condenser Vacuum plays a very important role in efficiency of the Rankine Cycle. If
vacuum is less than design value, i.e. if Condenser absolute pressure is more than
design value, corresponding saturation temperature is more, thus Heat is rejected at
Higher Temperature (T2 in expression 1 is less than design) and cycle efficiency
drops. This increases Heat rate. Also the of the L.P.T. backpressure increases, thus
reducing the conversion of Heat Energy to work in Turbine. This increases specific
steam rate thus increasing fuel consumption. In Condenser, only latent heat is
rejected, hence condensate temperature is always at saturation temperature. If
condenser pressure is less than design value, temperature of condensate shall also be
less. This causes low feed water temperature, thus increasing the heat rate. Following
table shows effect of deterioration of condenser vacuum on heat rate.
In the Power Plant, there can be many reasons for low temperature of Steam at Boiler
and Reheater outlet. Passing spray water control valves and motorized valves,
inadequately tuned temperature control system, fouled surfaces of the Super Heaters are
some of the reasons. These reasons become more dominant when the plant is operating
at loads below maximum rating. Throttling of steam flow due to partially shut valves is
the major reason for low pressure of steam at Turbine admission.
1) Air ingrace in condenser: Air ejection system of the condenser has the capacity
to remove non-condensable gases present in the steam in normal operation. As
the condenser is operated at less than atmospheric pressure, it is prone for air
leaking in to it. Sealing systems, such as Turbine Gland Sealing, Water sealing of
the evacuation system Valves, are provided to prevent the air ingrace. If Gland
sealing steam pressure and temperature and Valve Gland sealing water
pressure are not maintained properly, atmospheric air enters the condenser in
large quantity. Evacuation system can not remove the excess air and hence
condenser pressure increases. Condensers are also provided with many tapping
points for instrumentation. Many of these tapping points are used only for
carrying out acceptance tests. Once these tests are over, the temporary
instrumentation connected to condenser is removed. If any of such tapping
point remains open by oversight, air enters the condenser. There is also a chance
of cracks developed on the connection between L.P.T. casing and condenser.
Damaged gaskets on flanged joints, leaking vent valves provided on Pressure
gauges, cracked impulse lines, passing vacuum breaker valves, atmospheric
vent or drain valves on C.E.P. inlet piping, if are open, also cause air ingrace.
Evacuation equipment, such as Steam Ejectors, Electrical Vacuum Pumps are
provided with airflow measuring devices. Any increase in the flow rate
indicates air ingrace. Condenser air leaks can be identified by manual inspection
while the plant is on load. Helium Leak Detectors can also check air leaks. When
the unit is shut down, condenser leaks can be detected by filling Condenser with
D.M. Water up to certain high level. But this test needs lot of prior preparation.
Q= U * A * ΔTm (1)
ΔTi - ΔTf
Where ΔTm = ---------------------- (2 )
Ln (ΔTi / ΔTf)
In the installed system, Mass flow rate of water (depends on the C.C.W pumping
capacity) and Heat Load (Mass of steam from LPT exhaust) becomes constant. And as
per equation 3 above, heat removal capacity solely depends on (T2 - T1). Temperature of
Cooling Water, T2, at Condenser outlet can increase only up to the value decided by
design T.T.D. for the condenser,
Design value for T.T.D. in Condensers is generally 2.5° C, as designing condenser for
TTD below this is not viable. Hence, ultimately, the heat removal becomes directly
dependent on Cooling Water Inlet temperature (assuming other factors to be constant
for the given case). Increase in this temperature will cause reduction in mass of steam
getting condensed. In such cases, some steam remains in vapour form, causing
Condenser Pressure to increase. Similarly, even if Cooling Water temperature is within
design limits, but its mass flow rate reduces, same scenario can be expected.
In Cooling Towers, evaporative cooling of Hot water takes place. Air, sucked by the
C.T. Fan, flows in cross flow direction to water flow, comes in contact with air, causing
evaporation of water. The heat energy required is taken from Water, thus cooling it. The
rate of evaporation is dependent on Relative Humidity of air and its dry bulb
temperature C.T. design is made considering yearly average value of R.H. found from
historical data.
If the R.H. and Dry bulb temperature of ambient air is high, evaporation is low and
hence Water temperature does not drop to the design values. This situation may arise
during some periods of the year and is not controllable. The controllable reasons are;
5. Sensible heat gain by cold water when it flows from C.T. to C.W. Pump sump.
1) C.W. Flow rate required for maintaining Condenser Vacuum at rated generation
from the plant are calculated by designers. Accordingly C.W. Pump rating is calculated.
Velocity of cooling water through condenser tubes is the controlling factor. The pumps
selection is based on calculated values of Hydraulic Resistance of the C.W. Lines,
Condenser tubes, elevation to which hot water should reach etc. Hydraulic resistance
of the C.W. circuit increases due to following reasons:
i. Number of Plugged condenser tubes more than considered while designing the
system
ii. Reduction in Tube cross sectional area due to scaling in the tube or deposit of
mud, algae or organic growth within the tubes
vi. Heavy and undetected leakage from the under ground piping.
Scaling and fouling, corrosion, and organic growth on condenser tubes reduces the
ability of heat transfer between Steam and cooling water. Ingrace of ambient of air in to
the condenser, which blankets the tube surface. Air has very low thermal conductivity
and it causes drop in Heat Transfer coefficient.
i. Calcium Carbonate
v. Magnesium salts
Preventive Measures:
The concentration of salts takes place because of evaporation of water in the cooling
towers. Even if softened water is used, concentration of these salts increases in closed
circulation system. One of the ways to reduce the concentration is taking fresh water in
to the cooling pond to make up for the evaporated water. But by this method, huge
quantity of make up water is required. Another way is to softening. But soft water has
greater tendency for corrosion. Maintaining pH of water between 6.0 to 8.0 by feeding
acid in the system. But there are many disadvantages such as control of pH, safety in
handling huge quantity of acid etc. On line circulation of sponge balls through
condenser tubes, and occasional acid cleaning of the condenser tubes are other ways to
prevent scaling.
Microbial Growth: Microorganisms enter cooling towers through air, make up water and
dust. The major problems are Algae, Fungi and Bacteria. Chlorine is usually adequate to
prevent the growth. But, it is effective only if pH is 8.3 or below. Free chlorine of 0.2 to
0.5 ppm is sufficient. Beyond 8.3 pH Chlorination does not satisfactory results.
Feed water temperature is another factor, which decides the efficiency of Rankine Cycle,
as is evident from expression 1 above. Tm1 decreases if temperature of feed water at
Boiler outlet is low. High availability of feed water heating system and also its optimum
performance are important factors. Reasons for poor performance of feed heaters are:
4. Heater getting bypassed frequently due to High water level of because of inefficient
heater level control instrumentation
*********
Radiation 0.19
Unaccounted 0.40
Efficiency 87.9
Controllable losses are 1) Dry Flue Gas loss and 2) Unburnt Carbon. Losses due to
Moisture in fuel and air are uncontrollable. Ambient air, when introduced in the boiler,
also carries with it water vapors. Hydrogen in Coal reacts with Oxygen in air and forms
moisture. Along with flue gas, water vapors also receive heat energy produced from
combustion of fuel. This energy is lost to atmosphere through Chimney.
Flue gas loss and Unburnt Carbon loss are the controllable losses. Effect of deviation of
some of the parameters on Heat rate :
3. Fly ash,
4. Oxygen,
5. Water Vapours.
Temperature of flue gas leaving air pre heaters is maintained at 135 to 140° C. Total Heat
content in the flue gas is =
(Volume of flue gas in m³/sec Sp. Heat of the flue gas Specific Weight Flue gas
temperature)
When boiler is operated with Optimum air supply and temperature of flue gas at APH
outlet must is maintained within the design limits, flue gas loss is at its minimum.
Primary Air + Secondary air is the total Combustion air supplied to Boiler. Depending
on the Coal Analysis and required velocity of air + coal mixture through coal pipes,
manufacturers specify P.A. Flow through coal mill in relation to Coal Feeding.
Combustion Air requirement for the Boiler: Requirement of air for combustion of coal
varies as per the constituents of coal being fired. If it is less than required, incomplete
combustion takes place leading to high unburnt carbon loss. If it is more than required,
combustion can be complete but Flue gas quantity increase leading to higher flue gas
losses.
2. All the coal nozzles must admit equal mass of fuel in furnace and hence , primary air
velocity through pipes must be equal and as P.A. flow to mill should be
proportional to mill loading as specified by the manufacturer
4. Secondary air must enter combustion chamber from pre determined places only.
5. Secondary air must enter the furnace at predetermined velocity from all elevations.
6. Diffusers on the coal nozzles must be in proper condition to ensure that the jet of
air/coal mixture, emanating from nozzle, is well distributed.
When all these conditions are satisfied, then only efficient combustion in the
furnace, supplied with 20 % excess air is ensured. Fuel admission and combustion
system has following equipment to ensure these conditions.
2. Fuel air dampers (named after the coal elevations i.e. A, B, C, D etc) on all the Four
Corners should be open only for the elevations that are in service. Position of these
dampers must be equal for all the corners. Regulation of these dampers is as per the
quantity of coal feeding measured as Coal Feeder speed. Dampers of the elevations
AA. FF, BC and DE should open equally for all Four Corners. These dampers are
regulated to maintain Furnace – Windbox D.P. to the value specified by the
manufacturer. Dampers AB, CD and EF are regulated as per Fuel Oil pressure for Oil
elevation in service. For the oil elevation not in service, dampers regulate as per the
Furnace – Windbox D.P.
3. Orifice plates in Coal Pipes: To ensure that all burners (nozzles) at all coal elevations
admit equal mass per sec in the furnace, two requirements should be fulfilled.
Primary air flow velocity in each of the pipe must be equal and fuel/ air ratio in all
pipes should be the same. Inserting the Orifice plates, thus equalizing the hydraulic
total output power solutions Manohar Tatwawadi Page 15
resistance of all the pipes equalizes pipe velocity. Cold air flow tests are conducted
on coal mills at regular intervals. Results from these tests give valuable information
of condition of Orifice plates and partially or fully choked up pipes. If coal mill is
operated with Primary air flow rate less than that specified, velocity of coal air
mixture drops below 20 mtr/sec, causing separation of coal particles from stream
and consequent settlement in pipes, resulting partial choke up. If the temperature of
coal / air mixture at coal mill outlet drops below 60° C, there is a possibility of
condensation of water vapor which also result in separation of coal particles and its
settlement.
4. Mill air flow control dampers: For ensuring the coal / air ratio equal, P.A. flow rate to
mill should be as per mill loading and hence regulated by feeder speed. Coal mill
manufactures give the P.A. Flow rate and mill loading characteristics.
5. Mill temperature control system: By ensuring coal air mixture at 77° C, adequate
dryness of coal is ensured, which is one of the important requirements for proper and
efficient combustion.
6. Furnace – Windbox DP Control system: Velocity at which secondary air enters the
furnace is determined by Furnace – Wind box differential pressure. For every boiler,
value of Furnace – Wind box differential pressure is specified for different loading
conditions. By sticking to the specified values, it is ensured that velocity of secondary
air is as per the combustion reaction requirement. For this purpose, opening of
Secondary Air dampers of the wind box is controlled by automatic control loop for
Furnace – Windbox DP. Set point for this loop is generated as per the boiler load as
indicated in the enclosed Fig.1.
7. Corner Firing: For achieving efficient and sustained combustion at desired rate,
Oxygen in Air must reach the Coal particles at that rate. Oxygen molecule reach
burning coal particles by a process called Diffusion. Ratio of Concentration of
Oxygen at particle surface to that in surrounding gas mixture decides rate of
diffusion. This rate is highest when Coal particle is surrounded by air which contains
21 % Oxygen. Furnace atmosphere is made of mixture of Coal, Air, Flue Gases and
Ash particles. To ensure that coal particles will always remain surrounded by air,
place of air admission, velocity at which air is admitted and turbulence in the furnace
are of prime importance. First two requirements are fulfilled as discussed above.
Tangential firing fulfills requirement of turbulence.
9. Pulverization of coal for design particle size: The above discussions deal with the
importance of Fuel firing equipment and air supply to boiler. Role of particle size is
as important as that of proper supply and distribution of air in the furnace. As
explained, care is taken that coal particles will always be surrounded by air in the
furnace. In furnace, very small size air “Packets” are interspersed in the
homogeneous mixture of gases. Total oxygen required for complete combustion of
the individual particle depends on mass of particle, which in turn depends on the
size to which particle is pulverized. Smaller is the size of particle, smaller the
quantity of Oxygen required for its complete combustion. Hence, by ensuring that
70% of Coal passes through 200 Mesh, it will always remain surrounded by air
“packet” which will contain enough Oxygen. But, it is also important that size
distribution of balance 30 % coal should be:
Other Factors:
Following factors also cause deterioration of plant performance, thus increasing heat
rate. Many times, these factors are not measurable directly by plant’s instrumentation.
But, their effect can be known from regular tests.
In Trisector Airheaters, air leakage, through seals, in to flue gas takes place. Due to
rotating rotor, the air side and flue gas side sectors are sealed by radial as well as axial
seal plates. Deterioration of sealing arrangement increases air leakage increasing I.D.
Fans loading. Leakage of ambient air in to flue gas through damaged ducts and through
E.S.P. Hoppers is another reason of increased loading fo the I.D. Fans. The extent of both
the leakages can be so high that I.D. Fan loading reaches its maximum, leading to either
restriction on Generation or in worst case, purposeful reduction of Secondary air. By
measuring Oxygen at Air Heater outlet and ESP outlet monitoring of extent of air
leakage is possible.
1. Soot blowing
2. Steam ejectors
3. Opening of C.B.D.
6. Steam used for Oil heating and steam tracing of oil lines.
To certain extent, steam consumed for Soot Blowing, Oil heating and Ejectors and
There is no direct effect of attemperation flow in heat rate deviation. But increased
sprey flow rate indicates deterioration of Boiler Conditions.
Auxiliary Consumption:
2) Condenser Performance
4) Combustion of fuel in Boiler with Optimum air supply, thus reducing Dry
Flue Gas loss and Unburnt Carbon loss.
5) Auxiliary Consumption
7) Duct Leakage
140 mm Wcl.
Furnace –
Windbox DP
40 mm Wcl.
40 % 70 %
Boiler Load
CO in flue gas
In ppm
100 ppm
********
From station to station the C.W. Temp for the condenser cooling changes and therefore
the vacuum conditions and the exhaust temperature also changes accordingly. A
specimen calculation shown has been done for the values at 652000 kgs of steam per
hour flow at 130 kg/cm2 absolute pressure and 5550C superheat Temperature. Similar
such calculations can be done at different loads for calculation of heat rate of the turbine
regenerative feed water heating cycle at those particular loads.
While calculating the Turbine Heat Rate following assumptions have been made in the
original drawings, giving the values of Enthalpy and other Properties.
1. Under cooling in the drain coolers of Heater No 6 and heater No 7 has been taken
as 100C. The effect of drain cooler of Heater No 5 has been ignored.
2. Wherever a dash has been given in place of reading, the equipment is inoperative
in that range.
3. The values of temperatures mentioned are approximate. Whenever the steam is
wet (especially at the LP Exhaust), instead of giving the temperature, dryness
fraction has been mentioned in the temperature column.
4. When press in Heater No 5 approaches 10.5 Kg/cm 2 absolute, drain from Heater
No 6 is diverted to Deaerator bypassing Heater No 6 and drain of Heater No 5 is
diverted to Heater No 4.
5. The Specific Heat Rate does not include the consumption of steam in the main
Ejector.
Similar such calculations for the turbine heat rate can also be carried out for over load
working of TA set at 215.78 MW and at 211.05 MW Loads, at 670 T/hr steam flow and
with 3% makeup water added to the Hotwell of Condenser and at different cooling
water temperatures ranging from 300C to 360C at Condenser inlet. A separate calculation
can also be done to calculate the turbine heat rate when HP Heaters are out of service at
206.135 MW Load.
These figures should however, be not taken as guaranteed performance figures and will
vary from station to station depending upon the actual working conditions, age of
stations etc.
Before calculating the Turbine Heat Rate we shall first consider the stage by stage
efficiency of the Turbine Cycle.
A Complete Turbine Cycle single line schematic diagram is as per attached drawing,
wherein the parameters for Steam, Condensate and Feed water are marked for full load.
Similar such chart can be worked out by inserting the values for the parameters
calculated from BHEL Drawing No C-210-130/TDC-210-60.2. The Turbine Cycle
Diagram indicates the direction of flow of various fluids involved.
2.1 Ejector:-
Ejector is supplied with steam from Deaerator (d4) at 4.5Kg/cm 2 having 1550C Temp
and the condensate from hotwell passes through the same, which is pumped by the
condensate extraction pump to the further feed water regenerative heating cycle. The
ejector drain is recovered back to the flash chamber on the condenser. Calculations have
been made assuming the efficiency of 99.8% for the Ejector from which the Enthalpy /
Temperature for the drain from the Ejector to the Flash Chamber is derived.
total output power solutions Manohar Tatwawadi Page 22
2.2 Gland Steam Condenser GC1:-
T - 100 Dr
F - 1660 Fl
Gland Steam 480106(47.18-45.07)*100
Condenser Effy. = =
1260(728.20-100)+400(659.83-100)
The Gland Steam Condenser GC1, which is next to the Ejector in the regenerative feed
water heating cycle, sucks steam and air mixture from outermost HP, IP and LP Turbine
glands. The necessary required vacuum of about 100 mm is established in the Gland
Steam Condenser by an Ejector, which is provided with steam (d2) from the Deaerator.
The condensate (gd1) is recovered back to the flash chamber on the condenser. From the
calculations it is seen that the efficiency of the Gland Steam Condenser No 1 is 99.7%.
Condensate T - 61.05
LPH 1 T - 47.18
to GC 2 F - 480106 F - 480106
T - 65.93 Drain
F - 11989 cham
(hd1)
480106(61.05-47.18)*100
Effy of LPH No 1 = = 99.8%
11989(622.05-65.93)
The Feed water Heater 1 (LP Heater No 1) is fed with Extraction Steam (e1) from the
Extraction No 1 on LP Turbine and the heater drain (hd1) is fed to the flash chamber on
condenser. The condensate after GC1 flows through Heater No 1. From the calculations
shown in the sketch the efficiency comes to 99.80%.
Condensate T - 101.52
LPH 2 T - 68
to LPH 3 F - 555281 F - 48
T - 105.78 Drain to
Drip Pump F - 75175 Condensa
(hd2)
480106(100.86-68.10)*100
Effy of LPH 2 = 25369(678.41-105.78)+49806(130.26-105.7
The steam from IP Turbine Extraction No 2 (e2) is fed to the feed water heater LP Heater
No. 2. The drain (hd2) is pumped back with the help of Drip Pump into the main
condensate flow path before the condensate entry to Heater no 3 as shown. This also
increases the temperature of condensate from 100.860C to 1o1.520C at the entry in Heater
No 3. From the calculations as above the efficiency of LP Heater No 2 comes to 99.8%.
Condensate T - 125.27
LPH 3 T - 10
to LPH 4 F - 555281 F - 55
T - 130.26
Drain to
F - 49806 (hd3)
555281(125.27-101.52)*100
Effy of LPH 3 = 21033(715.68-130.26)+28773(161.73-130.2
Heater No 3 is provided with steam from IP Turbine Extraction No 3 (e3) and the drain
from heater no 4 (hd4) is also fed back to heater No 3. It may also be noted that the
amount of condensate passing through heater No 3 increases in quantity by the amount
of drain from heater No 2 (hd2). Heater no 3 drain is fed back to LP Heater No 2. The
calculated efficiency of LP Heater No 3 comes to 99.8%.
Condensate T - 156.52
LPH 4 T - 12
to F - 555281 F - 55
Deairator
T - 161.73
Drain to
F - 28773 (hd4)
555281(156.52-125.27)*100
Effy of LPH 4 = 23838(762.69-161.73)+4935(782.31-161.73
LP Heater No 4 is fed with Extraction steam from IP Turbine (e4). Leakage steam from
HP and IP Glands (g3) is also fed to the LP Heater No 4. Drain from LP Heater No 4 is
fed back to LP Heater No 3. HP Heater No 5 drain (hd5) is cascaded to LP Heater No 4
below 150 MW load. For loads more than 150 MW HP Heater No 5 drain normally goes
to Deaerator. In the calculations at full load, HP Heater No 5 drain (hd5) is not
considered as fed to Heater No 4. The calculated Efficiency comes to 99.7%.
2.8 Deaerator:-
T - 166.71
to HPH5 F - 652000
(555281(166.71-156.52)+4830(820.28-659.83))*
Deaerator Effy =2300(820.28-166.71)+93256(181.51-166.71)+5984(802
166.71)
Dearator is supplied with heating steam from Extraction tapped from either Extraction
no 5 or Extraction No 6 (ed). Extraction No 5 is taken from IP Turbine and Extraction No
6 is taken from HP Turbine at HP Exhaust. For loads below 150 MW, deaerator heating
steam supply (ed) is derived from Extraction No 6, which is changed over to Extraction
No 5 at loads above 150 MW. Auxiliary steam supply to the main Ejector, Gland steam
ejector and sealing steam of Turbine Glands is changed over from auxiliary PRDS to
Deaerator.
The Deaerator pegging steam supply is initially given from auxiliary PRDS, which is
changed over from auxiliary source to Extraction No 6 at about 90 to 100 MW Load.
The gland leakage from ESV and IV is fed to the deaerator. Heater No 5 and Heater No 6
Drains (hd5 or hd6) are also fed to the deaerator. Actually HP Heaters are taken in
service after 60 to 70 MW Load is taken on the turbine. Heater No 5 Drain (hd5) goes to
It may be noted that the total quantity of feed water supplied from feed water tank to
boiler feed water pump is equal to main steam flow to the HP Turbine.
In this connection, it may be noted that heat added by Boiler Feed water pump due to
Mechanical churning of water has been also taken into consideration, which is equal to
4179320 Kcal.
T=166.71
Flow=
T - 181.51
Drain to
F - 93256
652000(189.69-173.12)*100
Effy of HPH 5 = 16640(802.92-181.51)+76616(198.05-181.5
HP Heaters are taken into service in block after a load of 60 to 70 MW is taken on the
turbogenerator. HP Heater No 5 is supplied with steam from Extraction No 5 (e5) taken
from IP Turbine. Heater No 5 Drain (hd5) goes to Heater No 4 below 150 MW, which is
changed over to Deaerator at loads more than 170 MW. Heater No 6 Drain (hd6) is
cascaded to Heater no 5. From the heat balance calculations the efficiency of HP Heater
No 5 comes to 93.7%.
652000(228.80-189.69)*100
Effy of HPH 6 =
40391(732.99-198.05)+31844(238.65-198.05)+43
Heater No 6 is supplied with steam from Extraction No 6 (e6) from HPT Exhaust. It is
cold reheat steam. The spindle leakage steam from HPT (g5) is also fed to Heater No 6.
Heater No 7 Drain (hd7) is cascaded to Heater no 6 and Heater no 6 drain (hd6) is
cascaded to Heater No 5. From the calculations the efficiency is 99.7%.
Feed Water to
Economiser T – 253.94 HPH 7 T – 22
F - 652000 F-
T – 238.65
Drain to
F - 31844
652000(253.94-228.80)*100
Effy of HPH 7 = 31844(755.97-238.65)
Heater No 7 is provided with Extraction steam from HP Turbine (e7). The drain (hd7) is
cascaded to Heater No 6. Feed water at the outlet of the heater is finally fed to back to
the boiler through the feed water regulating valve. From the calculations the efficiency
comes out to be 99.5%.
2.13 Condenser:-
Make up
20 T T–3
F–2
Steam to circ.water Ratio= 0.00178
P- 22, T – 43
0 CEP
T. T. D.. =11 C Effy = 80% F–480106, E
210 MW Turbine has two condensers connected in parallel. The total quantity of the
condensed steam exhausted from the LP Turbine is mixed with drains from Ejector
consisting of condensate of steam from Deaerator(d4) and GC1 condensate of steam
from HPT and IPT.
The steam from LPT at a Pressure of 0.0889Kg/cm2 and quantity 460008 kg/hr is
condensed by cooling water quantity 270000 m3 which equals to 27000000 kg/hr and
hence the circulating water required for cooling 1 kg of steam is 27000000/460008 = 58.6
kg.
The total heat loss to cooling water = Steam from LPT Exhaust * Enthalpy of water at
Hotwell
= (251173568/0.8)/27000000 = 110C
From the calculations shown it will be seen that if 270000 m3/h water flow is maintained
for the circulating water through the condenser having 80% efficiency the terminal
temperature difference for the circulating water will be of the order of 11 0C.
Total Heat Supplied to the Turbine in kcal QM*(MSE - FWE) + QR*(RHE - CRHE)
Heat Rate =
Total Generation in KWH W
QM = Main Steam Flow = 652000 Kg/hr
4) EXTRACTIONS
A small quantity of Leakage steam from ESV & IV spindle leaks to Deaerator and gland
steam condenser, which is also utilized for feed water regenerative heating. The
condensate derived thereby is also added in the system. The heat content of this
auxiliary steam is neglected.
Out of the above heat given to the extractions, total heat regained by feed water
regenerative heating cycle:-
Turbine Heat Input - (Heat Extracted from all Ext.)+(Heat Lost in Regen. Heating)+ (
Heat Lost to CW)
211902
= 2159 Kcal/kwh
At normal specified steam pressure and temperature of Main Steam and Reheat Steam
Specific Steam Consumption of this turbine is as below:-
******************
A MAIN STEAM
1 MAIN STEAM 130 130 130 130 130 535 535 535 535 535
COLD REHEAT
2 (CRH) 28.07 26.4 22.52 18.96 12.22 327 322 311 301 286
HOT REHEAT
3 (HRH) 24.19 23.2 20.17 17.22 11.46 535 535 535 535 535
STEAM AFTER
3.1 IPT 1.369 1.299 1.134 0.971 0.6725 183 184 184 185 190
STEAM BEFORE
3.2 LPT 1.343 1.274 1.118 0.9519 0.6594 183 183 183 183 183
LPT EXHAUST TO
4 COND 0.0889 0.086 0.0798 0.0739 0.0637 0.9529 0.9549 0.9001 0.9663
EXTRACTION
B STEAM
e7 TO HEATER NO 7 42.18 39.77 34.38 29.06 19.68 381 375 364 354 349
e6 TO HEATER NO 6 28.07 26.7 22.58 18.96 12.22 327 322 311 301 286
e5 TO HEATER NO 5 12.96 12.27 10.65 9.068 6.2 444 444 444 444 446
ed TO DEAERATOR 12.96 12.27 10.65 9.068 12.22 444 444 444 444 286
e4 TO HEATER NO 4 6.911 6.545 5.694 4.858 3.334 364 364 364 365 365
e3 TO HEATER NO 3 2.974 2.808 2.453 2.097 1.44 264 265 265 265 271
e2 TO HEATER NO 2 1.369 1.299 1.134 0.971 0.6729 183 184 184 185 190
g2 Gland Cooler 2 0.361 0.343 0.308 0.265 0.197 346 337 329 318 296
g3 TO HEATER 4 6.911 6.545 5.694 4.853 3.334 403 400 393 386 383
FROM SPINDLES
g4 TO DEAERATOR 7.5 479
g5 TO HEATER 5 28.07 26.4 22.98 18.96 12.22 464 457 448 438 433
A MAIN STEAM
1 MAIN STEAM 819.94 819.94 819.94 819.94 819.94 652000 616000 531000 449000 304000
COLD REHEAT
2 (CRH) 732.99 730.57 727.11 723.41 720.69 566369 534409 484930 395441 259703
HOT REHEAT
3 (HRH) 845.83 846.22 846.86 847.54 848.82 566369 534409 484930 395441 259703
STEAM AFTER
3.1 IPT 678.41 678.84 679.34 680 682.82 470857 447226 390074 333899 230723
STEAM BEFORE
3.2 LPT 678.41 678.84 679.34 680 682.82 470857 447226 390074 333899 230723
EXHAUST STEAM
4 TO COND 589.18 590.08 592.41 595.31 606.03 230024 218790 191648 134954 115604
EXTRACTION
B STEAM
e7 TO HEATER NO 7 755.97 753.53 750.42 746.79 746.64 31844 29654 24925 20263 13294
e6 TO HEATER NO 6 732.99 730.57 727.11 723.41 720.65 40391 37134 29752 23261 4638
e5 TO HEATER NO 5 802.92 803.23 803.88 804.52 808.2 16440 13129 6605 545
ed TO DEAERATOR 802.92 803.23 803.88 804.52 720.69 5984 7937 11610 14306 18728
e4 TO HEATER NO 4 762.69 763.02 763.73 764.56 767.84 23838 22311 18460 14945 3108
e3 TO HEATER NO 3 715.68 716.07 716.63 717.2 720.32 21033 19547 16312 13584 8488
e2 TO HEATER NO 2 678.41 678.84 679.36 680 682.32 25369 13756 19679 16276 10038
e1 TO HEATER NO 1 622.05 622.43 623.07 623.78 626.45 11989 10787 7919 5132 634
C SERVICE STEAM
TO GLAND
d1 SEALING 659.83 2930
TO EJECTOR OF
d2 GC1 659.8 400
LEAKAGE INTO
d3 LPT 659.83 570
TP MAIN
d4 EJECTOR 659.83 1500
LEAK OFF
D STEAM
TO GLAND
g1 COOLER 1 728.2 728.22 728.29 728.36 728.48 1260
TO GLAND
g2 COOLER 2 756.8 752.66 748.77 743.1 732.92 4949 4733 4225 3735 2863
g3 TO HEATER 4 782.31 780.58 777.65 774.47 773.97 4935 4663 4020 3399 2301
FROM SPINDLES
g4 TO DEAERATOR 820.28 820.29 820.32 820.35 820.39 2300
g5 TO HEATER 5 806.5 803.66 799.78 795.63 795.4 4381 4140 3568 3017 2043
210 MW Parameters at different regimes at CW Temp 30 0C
Tag PARAMETERS ENTHALPY KCAL/KG QUANTITY IN KG/HR
No Regime IN KW 211902 202200 176669 151400 101200 211902 202200 176669 151400 101200
E CONDENSATE
5.0 HOTWELL 43.16 42.53 41.11 39.66 36.92 460008 437577 383296 329907 231289
5.W CEP SUCTION 43.16 42.53 41.11 39.66 36.92 480106 456529 398599 341934 237891
5.D BEFORE EJECTOR 43.16 42.53 41.11 39.66 36.92 480106 456529 398599 341934 237891
5.A AFTER EJECTOR 45.07 44.54 43.41 43.35 40.79 480106 456529 398599 341934 237891
5.1 AFTER GC1 47.18 46.76 45.96 45.32 44.86 480106 456529 398599 341934 237891
5.2 AFTER HEATER 1 61.05 59.92 57.08 53.77 46.35 480106 456529 398599 341934 237891
5.3 AFTER GC2 68.1 66.99 64.29 61.17 54.47 480106 456529 398599 341934 237891
5.4 AFTER HEATER 2 100.86 99.31 95.9 91.07 81.32 480106 456529 398599 341934 237891
BEFORE HEATER
5.5 3 101.52 99.97 96.12 91.69 81.87 555281 526534 463675 390683 376826
5.6 AFTER HEATER 3 125.27 123.83 118.85 113.82 102.33 555281 526534 463675 390683 376826
5.7 AFTER HEATER 4 156.52 154.33 148.83 143.18 129.23 555281 526534 463675 390683 376826
F FEED WATER
6.0 BFP SUCTION 166.71 652000 616000 531000 449000 304000
AFTER FEED
7.0 PUMP 173.12 652000 616000 531000 449000 304000
AFTER HP
7.1 HEATER 5 189.61 187.14 180.76 173.75 173.12 652000 616000 531000 449000 304000
AFTER HP
7.2 HEATER 6 228.8 225.28 216.632 207.35 185.82 652000 616000 531000 449000 304000
AFTER HP
9.0 HEATER 7 253.94 250.11 241.1 231.11 209.73 652000 616000 531000 449000 304000
G DRAINS
gd1 FROM GC1 100 1660
FROM HEATER
hd1 NO 1 65.93 64.8 61.86 58.6 54.14 11989 10787 7919 5132 634
gd2 FROM GC2 72.94 71.78 69.26 65.97 59.38 4949 4733 4225 3735 2868
FROM HEATER
hd2 NO 2 105.78 104.24 100.34 96.01 86.23 75175 70275 65076 48749 29935
FROM HEATER
hd3 NO 3 130.26 128.32 123.83 118.77 107.25 49806 46519 45397 32473 19897
FROM HEATER
hd4 NO 4 161.73 159.51 153.97 148.72 134.2 28773 26974 29085 18639 11409
FROM HEATER
hd5 NO 5 189.51 186.91 180.38 173.22 93265 84059 6605 545
FROM HEATER
hd6 NO 6 198.05 195.43 188.86 181.64 180.99 76616 70930 53245 46541 19976
FROM HEATER
hd7 NO 7 238.65 234.98 225.92 216.29 194.08 31344 29654 24925 20263 13294
HEATERS DATA
AT LOADS 211902 202200 176669 151400 101200 TTD
*********************
As per Control
1 Avg Flue Gas o/l Temp 0C T
Room
As per Control
2 Ambient Temp - Dry bulb 0C t
Room
As per Control
3 Ambient Temp - Wet bulb 0C
Room
As per Control
4 O2 at APH Inlet % O2
Room
As per Control
5 CO2 at APH inlet % CO2
Room
As per Control
6 N2 at APH inlet % N2
Room
7 Unburnts in Bottom ash % UBA As per Lab
8 Unburnts in Fly ash % UFA As per Lab
As per
9 CO at APH Out ppm CO
measurement
Effy(Post) – Effy(Pre)
3. Reduction in fuel consumption = 100*
Effy(Pre)
4. Saving in fuel per day = Fuel consumption per day * Reduction in fuel
consumption
5. Cost of fuel saved per day = Saving in fuel per day* Cost of fuel
****************************