27, Navarathinanagar, BPL Complex Karaikudi - 630 001

This document provides an itemized estimation for the construction of a proposed building with the following details: 1. It lists 14 items of work including electrical work, plumbing work, and miscellaneous expenses. 2. For each item, it specifies the number, dimensions, volume, area, rates, and total estimated costs. 3. The total estimated cost for the construction is Rs. 99,300 based on a total area of 2,700 square feet, working out to a rate of Rs. 36.7 per square foot. However, the quoted rate is Rs. 40 per square foot.

Uploaded by

ganesh15
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
45 views1 page

27, Navarathinanagar, BPL Complex Karaikudi - 630 001

This document provides an itemized estimation for the construction of a proposed building with the following details: 1. It lists 14 items of work including electrical work, plumbing work, and miscellaneous expenses. 2. For each item, it specifies the number, dimensions, volume, area, rates, and total estimated costs. 3. The total estimated cost for the construction is Rs. 99,300 based on a total area of 2,700 square feet, working out to a rate of Rs. 36.7 per square foot. However, the quoted rate is Rs. 40 per square foot.

Uploaded by

ganesh15
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

27, Navarathinanagar, BPL Complex

Karaikudi – 630 001.

Detailed Estimation for construction of proposed building

Sl. Dimensions Volume Area Rate per Total


Item of work Nos
No L B D Cub. Ft Sq. ft cub.ft sq. ft Amount

1 Electrical work
(i) Light and fan points 150 points max 150 per point 22500
(ii) Heater, mixey, grinder
20 points max 400 per point
washin machine etc 8000
(iii) AC switches 5 points max 600 per point 3000
(iv) main wire lining 200 m run 20 per m 4000
(v) main box one number 3000 per box 3000
(vi) meter box one number 2500 per box 2500
(vii) bore wiring one number 3000 3000
(viii) sump tank motor one number 2500 2500
(ix) UPS and solar lining lumpsum 2500 2500
2 Plumping work
(i) water pipe line
(a) bore to tank 1 40 ft run 30 per ft 1200
(b) sump to tank 1 40 ft run 30 per ft 1200
(c) tank to ground floor 2 100 ft run 30 per ft 6000
(d) tank to first floor 2 90 ft run 30 per ft 5400
(e) solar heater to toilet 1 100 ft run 30 per ft 3000
(ii) wastewater line
(a) kitchen to disposal 1 150 ft run 35 per ft 5250
(b) bathroom to soak pit 1 150 ft run 35 per ft 5250
(c) toilet to septic tank 1 150 ft run 35 per ft 5250
(d) Teraaze to rainwater
1 150 ft run 35 per ft
harvesting 5250
14 Miscellaneous expenses
(i) electrical and plumping 15 days duration 500 per day 7500
(ii) other expenses lumpsum 3000
TOTAL COST 99300
TOTAL AREA 2700 sq.ft
RATE PER SQ.FT 36.7
QUOTED RATE 40 / sq.ft