Membina Jejantas Pejalan Kaki Di Sek. Men. Chabang Empat, Ft134/Sek.11, Tumpat, Kelantan

This document is a list of 32 drawings for a pedestrian walkway project in Sek. Men. Chabang Empat, FT134/Sek.11, Tumpat, Kelantan. It includes drawings for site plans, structure details, foundations, and utilities. The drafter is Meor and the drawings have a target completion date of April 2020, with a status of 100% completed.

Uploaded by

Kyoko Chan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
243 views3 pages

Membina Jejantas Pejalan Kaki Di Sek. Men. Chabang Empat, Ft134/Sek.11, Tumpat, Kelantan

This document is a list of 32 drawings for a pedestrian walkway project in Sek. Men. Chabang Empat, FT134/Sek.11, Tumpat, Kelantan. It includes drawings for site plans, structure details, foundations, and utilities. The drafter is Meor and the drawings have a target completion date of April 2020, with a status of 100% completed.

Uploaded by

Kyoko Chan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

MEMBINA JEJANTAS PEJALAN KAKI DI SEK. MEN. CHABANG EMPAT, FT134/SEK.

11, TUMPAT, KELANTA

SHEET
DRAWING TITLE
NO.

STANDARD DRAWING

1 List Of Drawings

2 General Notes

3 Site Office (Category 1)

4 Standard Road Markings 1

5 Standard Road Markings 1

6 Standard Road Markings 1

7 Standard Road Markings 1

8 Standard Road Markings

9 Pedestrian Fencing and Handrailing Details

10 Pelan dan Tampak Hadapan

11 Keratan & Butiran

12 Skema Warna Papan Tanda

Structure Drawing

13 General Layout Plan

14 General Arrangement

15 Foundation Layout

16 Micropile 300mm Dia.

17 Pier A1 & A2 - Concrete Details

18 Pier A1 & A2 - Reinforcement Details

19 Pier C1, C2, Landing 1 & Landing 2 - Concrete Details

20 Pier C1, C2, Landing 1 & Landing 2 - Reinforcement Details

21 1000mm H x 2500mm W x 19000mm L Precast Box Girder - Concrete Details

22 1000mm H x 2500mm W x 19000mm L Precast Box Girder - Reinforcement Details

23 Staircase - Concrete Details

24 Staircase Plan and Elevation - Concrete and Reinforcement Details (Upper flight)

25 Staircase Plan and Elevation - Concrete and Reinforcement Details (Lower flight)

26 Roofing Details

27 Drainage Details

28 Dowel Bar and Rubber Bearing Pad Details

29 Handrailig Details

30 Soil Investigation Borehole 1

31 Soil Investigation Borehole 2

32 Position of Utilities
HABANG EMPAT, FT134/SEK.11, TUMPAT, KELANTAN

TARGET STATUS
DRAWING NO. DRAFTER
DATE WEIGHTAGE (%, siap)

Meor 4/9/2020 1 1

Meor 1 1

Meor 1 1

Meor 4/9/2020 1 1

Meor 4/9/2020 1 1

Meor 4/9/2020 1 1

Meor 4/9/2020 1 1

Meor 4/9/2020 1 1

Meor 4/9/2020 1 1

Meor 1 1

Meor 1 1

Meor 1 1

Meor 4/9/2020 1 1

Meor 4/9/2020 1 1

Meor 4/9/2020 1 1

Meor 4/9/2020 1 1

Meor 4/10/2020 1 1

Meor 4/10/2020 1 1

Meor 1 1

Meor 1 1

Meor 1 1

Meor 1 1

Meor 1 1

Meor 1 1

Meor 1 1

Meor 1 1

Meor 1 1

Meor 1 1

Meor 1 1

Meor 4/11/2020 1 1

Meor 4/11/2020 1 1

Meor 1 1
32 32

100.00
CATATAN

% PENCAPAIAN

You might also like