Qualification Matrix Process PDF
Qualification Matrix Process PDF
Global HR Manager
receives *local data to
be added to Qualification
Matrix from Local HR
in each centre.
- Done weekly: End of - Qualification Matrix - Done latest 28th of the - Include a buffer of 14
Business every from the past 6 months month days
CPT HR recieves
**Basic data to be added Monday. to be archived.
to Qualification Matrix - Archived sheets saved
from Training. with the file name as
the date when the file is
*Local Data: archived.
- Refreshers
- Upskilling
- Checkout dates
- Any info affecting
local centre
- Security/SMS
training
**Basic Data:
- PK number
- Starter group
- Pass/Fail/Retest
- DoE
Version: 2.0 Issue Date: 13 November 2017 File Name: Qualification Matrix Process
Revision Date: 19 April 2018
Approved by: Executive Manager Human Resources
Location : I:\QMS\Processes\Qualification Matrix Process 1
Implemented by: HR Business Partner
Qualification Matrix Process
- Done by dedicated - For CPT floor: LCA will - Done End of Business
Team Manager in each give documentation to every Friday
centre TM and TM will give to
HR.
- For CPT BO: BO staff
to drop off document
directly at HR office.
- If refresher failed,
necessary re-training
and retesting done
NOTE:
- Should B-Level be
involved, this should be - For new CAL, Training to communicate license
added into a comments requirements to Local HR and Floor Ops. Quality
section in the quali- to cross-check license requirements as a 4-eye
matrix as well as the principle.
exceptions folder
- If license/refresher is
not done, RCA is done
into why it wasn’t done
and corrective action is
taken.
Version: 2.0 Issue Date: 13 November 2017 File Name: Qualification Matrix Process
Revision Date: 19 April 2018
Approved by: Executive Manager Human Resources
Location : I:\QMS\Processes\Qualification Matrix Process 2
Implemented by: HR Business Partner