Location Nos. Distribution: Scope of Maintenance Work (For All Powerplants)
Location Nos. Distribution: Scope of Maintenance Work (For All Powerplants)
Distribution
1no. 25kw,3 Nos. 10kw, 1
Dumka 5 No.5kw
Power Plant Koderma 1 100kw
*Exact location will Giridih 1 70kw
be shared later Chaibasa 1 20kw
**All are Hybrid
Ghatsila 1 15kw
Rooftop Power
Plant Jamtara 2 1 No.20kw, 1 No.5kw
Pakur 1 20kw
Khunti 1 15kw
Simdega 1 15kw
Location Nos.
Payment Terms :-
1. Payment will be disbursed to you through NEFT/RTGS after 15 days of
submission of all the reports of 1 quarter & receipt of your bill at
registered office
2. Total payment will be disbursed quarterly.
3. No payments will be made if any required documents are missing.