JI 2027 JSA 039 Lifting and Rigging Activities by Tandem Lifting PDF

This JSA document outlines the lifting and rigging activities using tandem lifting for a project in North Kuwait. It identifies potential hazards such as non-compliance with procedures, poor task planning, poor crane positioning, and overloading the crane's rated capacity. Mitigation measures are provided to reduce the risks, such as permitting, inspections, lift planning, ensuring stable ground conditions, not exceeding capacity limits, and having riggers coordinate crane operation. The residual risks are lowered through implementing the controls.

Uploaded by

Yawar Qureshi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
83% found this document useful (6 votes)
9K views3 pages

JI 2027 JSA 039 Lifting and Rigging Activities by Tandem Lifting PDF

This JSA document outlines the lifting and rigging activities using tandem lifting for a project in North Kuwait. It identifies potential hazards such as non-compliance with procedures, poor task planning, poor crane positioning, and overloading the crane's rated capacity. Mitigation measures are provided to reduce the risks, such as permitting, inspections, lift planning, ensuring stable ground conditions, not exceeding capacity limits, and having riggers coordinate crane operation. The residual risks are lowered through implementing the controls.

Uploaded by

Yawar Qureshi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Form No.

JI 2027-FORM-HSE-002

Job Safety Analysis Petrofac


JSA No:
Activity: Lifting and Rigging activities by Tandem Lifting JI 2027-JSA-039
Project No:
Project: NEW GATHERING CENTRE, GC-29 IN NORTH KUWAIT
EF-1901
Site/Facility: Work Area: KOC Permit No & Date:

In Case of Emergency, contact KOC @ 160


Hard Hat, Safety Shoes, Safety Goggles/ Glasses, Hand Gloves, Overall, Dust Mask, Total Station &
PPE & Tools:
GPS, Hand Tools & Measuring tapes

SEQUENCE OF RISK
RESIDUAL CHECKED
POTENTIAL HAZARDS MITIGATION MEASURES RISK
JOB STEPS RATING
RATING Yes No
 Obtain required Permit to Work in compliance
with KOC SA.004 ( Permit to Work Procedure)
Non-compliance of KOC HSEMS 4 (D)  Ensure to comply with KOC, Mobile Equipment 2 (B)
procedures HIGH procedure KOC.SA.013, Lifting/ shifting and
LOW
Material handling (KOC-SA-029) and other
applicable procedures.
 Ensure all personnel have undergone Project
HSE Induction and EOD training
 Tool box talk
 Ensure the equipment is certified by company
as per KOC-SA-013- Mobile Equipment
Procedure and fit for the intended purpose as
required
 Ensure all lifting gears and shackles are
inspected with necessary authorized 3rd party
inspection certificates and color coded.
 Ensure all crane operator and riggers having
3rd party certification
 Ensure approved lifting method statement
along with position of crane drawing available
Pre - work for reference.
 Ensure both crane reeved on uniform or equal
Poor task planning 3 (C) falls wire rope with fully outrigger extended 2 (B)
MEDIUM condition. LOW
 Prefer the tandem lifting with equal capacity
cranes.
 Crane positioning area soil bearing capacity
test shall be done and ensure the stability of
the ground will withstand according the load
being lifted.
 Ensure adequate and sufficient lengthy metal
outrigger pad available to use.
 Ensures any safety devices installed on
lifting equipment shall be operational and
not over-ridden.
 Ensure loads for both cranes to be
calculated, including the range of permitted
tolerances, and documented. Speeds of
raising / lowering the load and slewing of the
cranes shall be documented in the Lift Plan
 Ensure ground is stable and properly
compacted as required
Lifting and
4 (D)  Do not position the equipment close to the 3(B)
Rigging by Poor positioning of crane during
HIGH trench/ excavation LOW
Tandem Lifting lifting operation
 Out rigger must have an outrigger pad of
adequate size and thickness

JI 2027-JSA-039 Page 1 of 3
Form No. JI 2027-FORM-HSE-002
 Do not exceed 80% of the rated capacity of
the crane for any loading/ unloading works
Overloading the crane rated and or as per manufacturer standards under
4 (D) 3(B)
capacity any circumstances
HIGH LOW
 Do not override any inbuilt safety devices or
take short cut during the lifting operations.
 Ensure that both the cranes SWL at the
specified boom length, working radius and
boom angle (as specified in the lifting plan) is
well above the half of the load being lifted.
 Conduct a dedicated tool box talk with the
crane operators and rigging supervisor about
how to carry out the tandem lifting in a safe
manner and both the cranes should be in
synchrononized operation by getting the signal
from the rigging supervisor / senior rigger
only.
 WSS/ Rigging supervisor to ensure that both
the cranes are positioned as mentioned in the
lifting plan and a trial operation carried out
Non sync .between the cranes during 4(D) 3(B)
without load to ensure that the swing radius
lifting activity LOW
HIGH and boom length are sufficient to carry out
the lifting activity without any hindrance by
the nearby structures / facilities.
 Senior rigger giving signal to both the cranes
shall have the competency in rigging and
signaling for the tandem lift and he shall be
positioned at location in such a way that he
can see both the crane operators during the
entire operation of lifting/ erecting the load
to position.
 Check that all sharp edges are protected with
softener pad.
 Check and ensure manufacturer approved
lifting trunnion or lifting part is using
 Conduct regular visual inspection of all lifting
gears and mechanism of crane prior to start
any lifting operation by a competent rigging
Lifting tackles and sling failure supervisor/ foreman
4 (D) 3(B)
during the operation  Ensure a full function test of all power,
HIGH LOW
Mechanical failure transmission, control, and safety systems to
be carried out prior to the commencement
of the lift, by competent personnel.
 Do not attempt any lifting operation on an
extreme weather condition i.e., heavy
Poor visibility / Heavy wind/ Sand 4 (D) sandstorm, strong wind, thick fog, rain, 3(B)
storm HIGH lightning etc. LOW
 No lifting operation during evening / dark time
as required

 Do not stand below the suspended load and


areas of potential impact.
 Provide proper sign boards, barricade the
lifting radius/ area where the activities are in 3(B)
Personnel injury 4 (D)
progress and remove all possible tripping LOW
HIGH
hazards in the lifting working area.
 Manual load handling shall not be used to stop
a swinging load and shall only be perform
below shoulder height.
 Close supervision by a competent rigging
supervisor
 Only one competent rigger (wearing
fluorescent vest) to do the signaling or rigging
activity. 3(B)
Incompetent lifting /rigging 4 (D)
HIGH  Provide adequately strong and long tag lines LOW
at both ends of the load

JI 2027-JSA-039 Page 2 of 3
Form No. JI 2027-FORM-HSE-002

Additional
Hazards

Worksite Supervisor
Reviewed by: Permit Applicant Approved by: Permit Issuer
Subcontractor / Contractor

Name: Name: Name:

Company: Company: Petrofac International Ltd Company: TECHNIP

Designation: Designation: Designation:

Signature:
Signature: Signature:

Date: Date: Date:

JI 2027-JSA-039 Page 3 of 3