DC Power Supply 3.1. DC Power System
DC Power Supply 3.1. DC Power System
DC POWER SUPPLY
3.1. DC Power System
DC supply is required for closing and tripping of circuit breaker, control board
indication, control and instrumentation communication and annunciation system etc.
Some of the important substation parts such as emergency lighting, relay system, and
automated control circuitry are operated through batteries. Batteries are also used to
provide illumination in certain and sensitivity area for otherwise work withstand still.
The size of the battery bank is depending on the voltage required for operation of the
DC circuit respectively.
A substation dc system consists of a battery of suitable voltage (number of
cells) and suitable size (Ampere-hour capacity) connected in parallel with a control
bus together with properly selected voltage regulated charging equipment.
At a single location where two distinct dc voltages are required, i.e., possibly
48 volts for microwave and 120 volts for substation operation, two separate batteries
and chargers is one option. Tapping a larger unit to obtain the smaller voltage is not
recommended. Another option to obtain different dc voltages is a dc to dc converter.
This is usually used for small loads and is available from the manufacturer.
The charging equipment consists of a full wave rectifier with regulated output
voltage. Normally, the charger operates continuously to furnish direct current to the
control bus for steady loads such as indicating lamps, holding coils, and relays, plus a
small current to maintain the battery at full charge.
Intermittent loads of short duration such as tripping or closing of circuit
breakers or automatic operations of other equipment are handled by the charger within
the limits of its capacity. Any excess load is supplied by the battery, which is
automatically recharged when the intermittent load ceases.
The control bus may be a dc bus in a switchgear assembly or, in the case of a
large substation, a dc or group of dc panels. DC voltage requirements for solid-state
relaying, event recorders, data acquisition, and other such devices are generally below
the voltage levels for circuit breaker trip coils. Actual requirements vary with
25
different vendors. Some types of equipment are provided with individual rectifiers,
rack mounted, changing 120 volts, 60 hertz ac, to 12, 24, or 48 volts dc. If the supply
fails, static switching changes the source to the main dc batteries and required dc
converter. An alarm indication is provided to indicate this status. Other equipment is
designed to be fed directly from the main batteries with ac/dc converters to supply the
static device voltage. 230 V DC and 110 V DC are used for protection and control
and 48 V DC is used for communication equipment.
Two of the most important components of a substation dc system are the main
battery and charger. These components should be sized correctly. Under sizing could
possibly mean a circuit breaker reclose failure and undue service interruption.
Oversizing, while not damaging, is expensive. However, the cost of the supply is a
fraction of total substation cost and the economics should be balanced with reliability.
At a minimum, the main battery should be sized to allow normal substation operation
for 8 hours.
affect the lifetime of the battery. The charger and distribution switchboard are
normally located in the same room, separate to the battery.
The main fuses of the battery are housed in separate plastic boxes, one for plus
connection and one for minus connection. These main fuse boxes should be placed
close to the battery itself.
the nominal float charge voltage of a cell is around 2.23 V and with Nickel-Cadmium
cells it is around 1.41 V.
These types of batteries are typically used for UPS Systems of very high rated
capacity, typically engaged for plant application, wherein maintenance and space is
not really an issue.
The battery sizing analysis of a duty cycle determines the required cell size for
each section. Depending on the load profile, it is not guaranteed that the last section
containing all periods will be limiting. For example, the cell size might be established
by the first minute of the duty cycle if many loads are energized at once. ANSI/IEEE
485 provides worksheets to assist with the calculation process. Battery manufacturers
provide similar worksheets.
The battery sizing methodology determines the cell size for the defined duty
cycle when the battery capacity is 100 percent and at the reference temperature of 25
°C (77 °F). For most batteries, end-of-life occurs when capacity falls to 80 percent of
the rated capacity. Also, depending on the installation, the actual battery temperature
might be well below 25 °C (77 °F), and battery capacity decreases as temperature
decreases. Apply correction factors to the calculated cell size to account for these
effects. The net result is that the selected cell size must be larger so that it can meet its
design requirements at end-of-life at the design low temperature.
Under ideal conditions, a battery can have 90 percent to over 100 percent
capacity when new. As the battery ages, its capacity will eventually fall to 80 percent,
which is the commonly accepted point at which the battery should be replaced. Below
this capacity, the rate of degradation can increase rapidly. As part of the battery sizing
process, size the battery so that it can fulfill the duty cycle requirements at its end of
life. Apply the following correction factor to the calculated cell size; the calculated
cell size is made 25 percent larger to ensure that it can supply the required load at end
of life:
The manufacturer specifies battery performance at the reference temperature
of 25 °C (77 °F). As the battery temperature falls below 25 °C (77 °F), battery
capacity decreases. As the battery temperature rises above 25 °C (77 °F), battery
capacity increases. If the expected operating temperature will be less than 25 °C (77
°F), adjust the cell size to account for the reduced capacity at the owner temperature.
For a different specific gravity, consult the manufacturer to confirm the
applicability of these correction factors. VRLA cells can have a completely different
temperature response; consult the manufacturer for the appropriate temperature
correction factors. Nickel-cadmium cells also require a manufacturer-provided
temperature correction factor for low temperature operation, but the correction factor
is not as large as for lead-acid batteries.
31
The aging and temperature correction factors account for inevitable aging and
temperature effects. The battery is sized for a particular duty cycle and depending on
the facility, load growth can occur over time. A design margin correction factor can
be applied to provide additional assurance that the battery will meet its future design
requirements. The design margin correction factor also adds a capacity margin to
allow for less-than-optimum battery operating conditions due to improper
maintenance, recent battery discharge, lower than expected operating temperatures, or
other effects. Simply stated, the design margin correction factor is an additional
margin to help ensure the battery has adequate capacity to perform its job. A design
margin of 10 percent to 15 percent is typical.
In summary, size the battery for the limiting portion of the duty cycle,
including corrections for performance at end of battery life and for the minimum
expected operating temperature. If needed, include an additional design margin.
that the voltage window is due to the nature of the battery when it is full and the
voltage drops.
or power plants need not be placed in a separate room. They are usually provided at or
near the facility control room or electrical switchgear facilities. However, when not
located in a separate room, barriers or some type of mechanical protection must be
provided to prevent inadvertent personnel or equipment contact and resultant damage.
Battery rooms should be provided with ventilation to limit the concentration of
hydrogen to 1% by volume. Periodic air flow measurements and explosion meter
(total combustible gas) readings are recommended in the general battery areas to
ensure adequate air movement to diffuse generation of hydrogen gas. “No Smoking,”
“No Sparks,” or “No Open Flame” signs should be posted on the outside of the door.
For further information refer to ANSI/IEEE 484, Recommended Practice for
Installation Design and Installation of Large Lead Storage Batteries for Generating
Stations and Substations.
Typical industry practice is to provide an explosion-proof rated fan in the
exhaust system for the battery room and classify the exhaust duct and a radius of
1.5 m (5 ft) from the exhaust vent as a classified area. Seismic protection should be
provided in areas with high seismic activity. Metal battery racks shall be grounded.
Concrete floors shall be painted with acid-resistive paint (alkaline resistive) for ni-cad
batteries. Electrical receptacles and light switches should be located outside of battery
areas.
Where drainage provisions are provided to the battery room, the fluid should
be first collected into a neutralizing tank before entering the oily water sewer system
(OWS) to prevent battery acids from affecting the sewer piping and for environmental
protection. Where sealed and unserviceable batteries are used, these requirements do
not apply, since no free hydrogen is released.
Fire detection capability is considered optional as the batteries themselves
have little combustibility and only a limited amount of cabling or charging equipment
is normally provided. A fire incident has a low probably of occurring, while historical
evidence indicates the buildup of hydrogen vapors (possibly by fan failure or battery
overcharging) and a minor room explosion as the likely incident to occur and damage
the contents of the room.