PA DH Well Work Plan-2016 Rev 07 (After PVN Meeting) 2

The document presents a plan for permanently plugging and abandoning (P&A) wells in the Dai Hung oil field in 2016. It discusses the approved P&A works, well information, layout, proposed P&A procedures and diagrams for individual wells. It identifies key issues with the operations such as positioning rigs near subsea infrastructure and wells that have been suspended for a long time. It proposes solutions to these issues, such as using a jack-up rig with a high pressure riser instead of a semi-submersible rig, and deploying a dynamic positioning (DP) vessel to aid positioning. The document provides timelines, budgets and recommendations for executing the P&A operations safely and efficiently.

Uploaded by

Them Bui Xuan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
104 views34 pages

PA DH Well Work Plan-2016 Rev 07 (After PVN Meeting) 2

The document presents a plan for permanently plugging and abandoning (P&A) wells in the Dai Hung oil field in 2016. It discusses the approved P&A works, well information, layout, proposed P&A procedures and diagrams for individual wells. It identifies key issues with the operations such as positioning rigs near subsea infrastructure and wells that have been suspended for a long time. It proposes solutions to these issues, such as using a jack-up rig with a high pressure riser instead of a semi-submersible rig, and deploying a dynamic positioning (DP) vessel to aid positioning. The document provides timelines, budgets and recommendations for executing the P&A operations safely and efficiently.

Uploaded by

Them Bui Xuan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 34

PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC

P&A PLAN FOR DAI HUNG FIELD IN 2016

1
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC

CONTENT

 Approved P&A works


 Well Information
 Well Lay out and distances
 Proposed Well P&A Diagram
 General procedure / Operation time plan
 Operation main issues
 Proposed solutions with time and cost comparison
 Budget
 Conclusion & Recommendation

2
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC

APPROVED P&A WORKS

3
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC

APPROVED P&A WORKS

PERMANENT PLUG AND ABANDONMENT WORKS FOR DH FIELD IN


2016 WERE APPROVED IN MCM#8 AS BELOW:

4
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
WELL INFORMATION

5
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
WELL LAY-OUT AT DH FIELD

DH‐01

DH‐02
6
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
WELL TO WELL DISTANCES

7
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
PROPOSED WELL P&A DIAGRAM FOR DH-9X
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
PROPOSED WELL P&A SCHEMATIC FOR DH-5X
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
PROPOSED WELL P&A SCHEMATIC FOR DH-10X
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
PROPOSED WELL P&A SHCEMATIC FOR DH-11X
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
GENERAL P&A OPERATION PROCEDURES
• Moving rig and positioning the rig over the well location,
• Prepare for P&A operations
• Re-establish guide line in to guide posts.
• Jump ROV to observe and monitor.
• Retrieve corrosion cap.
• Run BOP and pressure test connection against top cement plug
(BOP has been pressure tested in stump prior to running).
• Run in hole to drill out the top cement plug.
• RIH with cement stinger and tag bottom. Spot 100m cement plug
on top. WOC and perform weight and pressure test.
• Run CBL to check cement bond quality behind 9 5/8” casing.
• Run and set BP #1 at 50m below TOC.
• Run in hole 9 5/8” casing cutter and cut this casing at above TOC,
(care should be taken while cutting by soft close annulus BOP for
the potential of any gas bubbles behind casing).
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
GENERAL P&A OPERATION PROCEDURE
• Retrieve 9 5/8” cut casing
• Spot 100m T cement plug (13 3/8” x 9 5/8”).
• Run CBL to check cement bond quality behind 13 3/8” casing
• Run and set BP#2 at ~200m.
• Cut 13 3/8” casing at ~ 140m.
• Retrieve 13 3/8” cut casing
• Combination cut 20”x30” casing at 3m below the mudline
• Retrieve 20”x30” cut wellhead together with TGB
• Run cement stinger to top of BP #2.
• Mix and spot 15.8ppg cement slurry until cement return to seabed.
• Survey seabed by ROV for debris free. Recover ROV.
• De-anchoring/ De-positioning.
• Move rig to the other well location.

Note: Weight & Pressure tests for cement plugs will be performed as per the regulation
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
OPERATION TIME PLAN
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
OPERATION MAIN ISSUES
- RIG POSITIONING OVER SUBSEA WELLHEADS, PIPELINES AND
FACILITY OF THE DAI HUNG FIELD:

 JACK-UP RIG : ISSUE WITH JACKING UP/DOWN AND LEG PENETRATION


 SEMI-SUB RIG: ISSUE FOR RUNNING ANCHORS OVER COMPLICATED SS PIPELINE S
 TOOK ~ 5 DAYS (2 DAYS-PLAN) FOR ANCHORING/POSITION ON DH-10PST WITH
OCEAN QUEST RIG

- RE-ENTRY OPERATIONS:

 SOME WELLS HAVE BEEN SUSPENDED FOR LONG TIME (FOR EXAMPLE DH-5X
FROM YEAR 1994, DH-9X FROM YEAR 2004)
 LACK OF INFORMATION FOR WELLHEAD, CORROSION CAP, PGB…
 MARINE GROWTH COVERS ON SS TREE/WELLHEADS.

- WELL PERMANENT ABANDONMENT OPERATION:

 GAS ACCUMULATION IN CASING ANNULUS DUE TO POOR CEMENT QUALITIES-


WELL CONTROL ISSUE.
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC

OPERATION MAIN ISSUES (cont.)

• DH-8X P&A Operation,


July 2009.
• When recovering 9 5/8”
seal assembly of SSWH, the
well blew out.
• Rig was winched to safe
distance away from the gas
bubbles of DH-8X (180m).
• NPT ~ 105 hrs
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC

OPERATION MAIN ISSUES (cont.)

Corrosion cap and PGB of DH-4X in 2012 SS inspection


PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
OPERATION MAIN ISSUES (cont.) DH-10PST
- BOP GUIDE FUNNEL (9.5” ID) DID NOT FIT TO THE SS X-MAS
TREE HEAD (9.63” OD):
- HAD TO MODIFY THE BOP GUIDE FUNNEL
- NPT = ~ 4.5 DAYS
- ISSUE TO RETRIEVE THE INTERNAL TREE CAP (ITC):
- NPT = ~ 2 DAYS
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC

OPERATION MAIN ISSUES (Cont.): DH-10PST

19
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
OPERATION MAIN ISSUES (cont.)

DH-5X

GAS PIPELINE

DH-10X
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
OPERATION MAIN ISSUES (cont.)

DH-9X

DH-01 SEMI-SUB

DH-11X
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC

PROPOSED SOLUTIONS TO REPLACE SEMI-SUB RIG


FOR P&A WORK
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
JACK-UP RIG: MOVING IN & POSITIONING
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
JACK-UP RIG: PRE-LOADING/LEG PENATRATION
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
JACK-UP RIG: HIGH PRESSURE RISER

Length: 10m/joint.
10,000psi, Flange Conn.
ID =19.25” , OD= 23.58”
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
DP VESSEL
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
DP VESSEL
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
DP VESSEL
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
DP VESSEL
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
DP VESSEL
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
P&A WORK of SS WELLS BY FINA WITH VESSEL
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC

OPERATION TIME COMPARISON


PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC
RIG/VESSEL TYPE COMPARISON
Rig Type DP Vessel Jack-up Semi-sub

Rig/vessel day rate 150,000 USD/day 90,000 USD/day 100,000 USD/day


Vessel requirement 1 (01 small one- 8000 HP) 2 (01 big-10800 HP + 01 2 (02 big ones- 10800 HP)
small one- 8000 HP)
MGO daily consumption for
Rig 24 m3 12 m3 12 m3
Vessel 11.7 m3 26 m3 28.6 m3
Site survey Site survey
Soil boring Positioning
Additional services and Nil Excavation Special mooring
equipment to be required High pressure riser
SS wellhead connector
Cost impact with above Nil 860,000 USD per well 480,000 USD per well
additional services
Cement unit Cement unit Cement unit
Daily related equipment ROV unit ROV unit ROV unit
requirement Wireline unit Wireline unit Wireline unit
Fishing/cutting equipment Fishing/cutting equipment Fishing/cutting equipment
Estimated Operation Time 11.5 days per well 17 days per well 18.5 days per well
Rig positioning and Jacking Anchoring/Mooring in DH
up into a network of SS field with SS
Risk assessment Nil pipeline/wellhead. JU leg pipeline/wellhead
penetration issue.
PETROVIETNAM DOMESTIC EXPLORATION PRODUCTION OPERATION COMPANY LIMITED

PVEP POC

CONCLUSION AND RECOMMENDATION


- USING DP VESSEL FOR THIS P&A WORK WOULD BE ABLE TO
REDUCE THE OPERATION TIME AND THE P&A COST.
 PVEP POC WOULD LIKE TO PROPOSE USING THE DP DRILLING UNIT
INSTEAD OF NON-DP SEMI-SUB OR JU RIG.

- CARRY OUT SUBSEA WELLHEAD INSPECTION FOR DH-9X, 5X, 10X


AND 11X TO FIND OUT THE SSWH STATUS AND DO THE CLEAN-OUT
FOR SUBSEA WELLHEAD IF POSSIBLE.

- CARRY OUT SPECIAL MOORING ANALYSIS AND WELL CONTROL


STUDY FOR RISK ASSESSEMENTS & EQUIPMENT PREPARATION

- BASED ON THE RESULTS OF THIS MEETING, POC WILL SUBMIT THE


DETAILED P&A PROGRAM TO GET APPROVAL FROM PVN/PVEP.

- TIMING FOR THIS WORK WILL BE IN QII, 2016. THEREFORE, IF


APPROVED, OCS, ITB… NEEDS TO BE STARTED SOON .