Progress Report Standard For CPEC-JUL-2020

This daily progress report provides an update on the Hakla to D.I.Khan Motorway PKG-2C project in Pakistan. It summarizes the progress made on various construction activities. Several activities related to approach roads, structures like the Indus Bridge, guide banks, drainage works and ancillary works are lagging behind original schedule. The report lists quantities completed to date against planned targets and remaining works for each activity. Overall, many construction tasks are 30-50% completed, with significant work still remaining to meet the revised completion deadline of June 30, 2020.

Uploaded by

M. Aamir Saeed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
86 views5 pages

Progress Report Standard For CPEC-JUL-2020

This daily progress report provides an update on the Hakla to D.I.Khan Motorway PKG-2C project in Pakistan. It summarizes the progress made on various construction activities. Several activities related to approach roads, structures like the Indus Bridge, guide banks, drainage works and ancillary works are lagging behind original schedule. The report lists quantities completed to date against planned targets and remaining works for each activity. Overall, many construction tasks are 30-50% completed, with significant work still remaining to meet the revised completion deadline of June 30, 2020.

Uploaded by

M. Aamir Saeed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

Daily Progress Report (CPEC-2C)

Project Name Hakla to D.I.Khan Motorway PKG-2C Indus Bridge Rehmani Khel To Balian

Project Commencement Date: 10-Dec-17 Weather

Revised Completion Date (EOT#1): 30-Jun-20 Fair Sunny

Original Cost of Project: 7,138 Million Cloudy Rainy

Date: 16-Jul-20

Progress Qty
Activity BOQ Remaining
Activities Unit Prev. Achvd % age Plan To Actual To
ID Quantity To Date Var. Quantity
Total Today Completion date date
1 2 3 4 5 6 7=5+6 8 12 13=7 14=13-11 15

Right Abutment Approach Road (3.2 Km)


C1000 Clearing & Grubbing and CNG 152,064 SM 152,064 - 152,064 100% 152,064 152,064 - -

C1010 Formation of Embankment 601,619 CM 202,924 - 202,924 34% 499,770 202,924 -296,847 398,696

C1020 Improved subgrade 29,526 CM 29,526

C2000 Granular Sub base 15,176 CM 15,176

C2010 Aggregate Base 30,019 CM 30,019

C2020 Asphaltic Base Course 9,860 CM 9,860

C3010 TST 23823.36 SM 23,823

C3020 Asphaltic Wearing Course 2560 CM 2,560

Left Abutment Approach Road (1.8 Km)


C1017 Clearing & Grubbing and CNG 85,536 SM 10347 -10,347 85,536

C1040 Formation of Embankment 338,411 CM 32901 -32,901 338,411

C1050 Improved subgrade 16,608 CM 1560 -1,560 16,608

C2040 Granular Sub base 8,537 CM 0 8,537

C2050 Aggregate Base 16,885 CM 16,885

C2060 Asphaltic Base Course 5,547 CM 5,547

C3010 TST 13400.64 SM 13,401

C3020 Asphaltic Wearing Course 1440 CM 1,440

Structures (Indus Bridge)


B0988 Coffer dam & Misc. 1 Job 0.9 - 0.9 90% 0.6 0.6 - 0

B1010 Piles Works 198 No. 184 184 93% 198 184 -14 14

B1040 Pier Works 198 No. 167 167 84% 198 167 -31 31

B1030 Transoms Works 66 No. 55 55 83% 66 55 -11 11

B1060 Casting of Girders 448 No. 175 175 39% 448 175 -273 273

B1060 Stressing of Girders 448 No. 192 192 43% 448 192 -256 256

B1060 Launching of Girders 448 No. 177 2 179 40% 448 179 -269 269

B1090 Construction of Diaphrams 1,980 No. 658 17 675 34% 1980 675 -1,305 1,305

B1090 Construction of Deck Slab 64 No. 20 20 31% 64 20 -44 44

B1092 Expansion Joints 1,195 M 1195 0 -1,195 1,195

A2040 NJB 1,086 CM 79.80 11.40 91.20 0.08 285 91 -194 995

B1120 Rip Rap Works including filter layers 826 SM - - - - 826 - -826 826

Construction of Right Guide Bank(RGB)


Embankment Works-Right Guide
D0999 528,000 CM 98,199 - 98,199 19% 528,000 98,199 -429,801 429,801
Bank(RGB)
D1000 Stone Work of Right Guide Bank 319,896 CM 45,168 45,168 14% 319,896 45,168 -274,728 274,728

Construction of Left Guide Bank(LGB)


Embankment Works-Left Guide
D1009 528,000 CM - 46,067 -46,067 528,000
Bank(LGB)
D1010 Stone Work of Left Guide Bank 319,896 CM - 0 319,896
Other Drainage & Erosion Works
D1020 Construction of Chutes 1,393 CM 273 -273 1,393
RCC Pipe Culverts-1070 &910 mm dia &
D1030 1,430 M 345 -345 1,430
encasements
RCC Pipe Culverts-1070 &910 mm dia &
D1031 0 M 0 0 -
encasements
D1040 Stone Gabions 17,469 CM 3,348 -3,348 17,469
Grouted Rip Rap & Grouted Stone
D1050 32,896 SM 6,608 -6,608 32,896
Pitching
D1060 Dry Stone Pitching 74,088 SM 14,882 -14,882 74,088

Ancillary Works
A2040 New jersey Barriers 8,484 M 2,227 -2,227 8,484

A2041 Pre cast Kerb Stone 8,564 M 8,564

A2050 Metal beam Guard Rail works 6,600 M 1,049 -1,049 6,600

A2060 Traffic Road Signs 510 Each 510

A2070 Pavement Marking 33,716 M 33,716

A2080 GI wire mesh Fence 13,734 M 13,734

A2090 Gantry Signs 4 Each 4


Provision of Service Ducts along the
A2100 80 CM 0 80
Road
A2110 Provision of ITS for project 0 PS -

A2120 Sprigging & Sodding of Grass on Slopes 57,750 SM 0 57,750

Quantities Executed

1 Concrete A-1 (Chutes) 1,473 CM 1,473


Concrete A-2 (Underground and On
2 1,171 CM 1,171
Ground)
Concrete A-3 (Underground and
3 53,844 CM 42,786 34 42,820 80% 11,024
Elevated)
4 Concrete B (Underground) 2,633 CM 841 841 31.94% 1,792

5 Concrete D-1 (Pre-cast) 27,007 CM 15,642 15,642 58% 11,365

6 Reinforcement 14,793 Ton 11,358 3 11,361 77% 3,432

7 Asphalt Concrete Ton -


Major activities involved

1-Launching of girders,casting of diaphragms

2-Stressing of girders is in progress

3-Steel fixing and shuttering of diaphragms is in progress

4-Steel fixing and shuttering of deck slab is in progress

5-steel fixing and shuttering of girders is in progress

6-Casting of barriers is in progress.

Plan For The Next Day

1 - Stressing of girders

2 - Scaffolding and shuttering of diaphragms is in progress

3- Scaffolding and shuttering of deck slab is in progress

4 - Steel fixing and shuttering of girders is in progress

5- Launching of girders is in progress

6 - Casting of girders
Manpower & Material Summary
Sr. Vehicle Diesel Per m3
Type Activities Status
No ID Drawn Quantit Consumpt
1 Loader 950E 100 For launching of girders Rental
2 Excavator Ex200 100 For removing materials from span Rental
3 Generator 145 For camp
4 Excavator Ex200 300 For removing materials from span
5 Generator 70 For deck slab
6 Tractor 8794 10 For deck slab
7 Crane 3504 60 For launching of girders Rental
8 Tower light 45 For casting of diaphragms
9 Generator 85 For batching plant
10 Pickup 1941 30 For electrician staff
11 Dozer D85 100 For launching of girders Rental
12 Loader 966 100 For batching plant Rental
13 Loader 950 100 For launching of girders Rental
14 Generator 50 For girder yard
15 Pickup 8129 45 For go to mianwali
16 Pickup 845 10 For nespak
Shuttering plates for
17 Diesel 70
slab,girder
18 Trolla 27 30 Steel shifting for deck slab
19 Pickup 1942 10 For workshop staff
20 Diesel 100 For launching company
21 Transit mixture 336 20 For casting of diaphragms,barriers
22 Loader 930 50 For batching plant
23 Loader 950 100 For road work
24 Tractor 4258 11 For steel shifting for girders
25 Roller 50 For road work
26 Crane For steel shifting
27 Tractor 8803 15 For girder yard
28 Generator 20 For camp
29 Concrete pump 20 For casting of diaphragms,barriers
30 Transit mixture 4929 60 For casting of diaphragms,barriers
31 Generator 200 For batching plant
32 Transit mixture 89 50 For casting of girders
SUB TOTAL 2156
Manpower Status Report
Project CPEC-2C, 6.4 Km + Indus Bridge-Rehmani Khel To Kot Balian
Location Hakla (On M-1) To D.I.Khan Motorway
Package 2C
MANPOWER SKB Nos. MANPOWER SKB Nos.
Project Manager 1 WORK SHOP
STRUCTURE STAFF HTV Mechanic 3
Construction Manager 1 Asst.Mechanic 1
Engineer 1 Auto Electrician 1
Supervisor 2 Auto Electrician Helper 1
Foremen 1 Welder & Tiremen 1
Surveyor 3 OPERATOR STAFF
Surveyor Asst. /Helper 4 Loader operator 2
GUID BANK Excavator operator 2
Construction Manager 1 Crane operator 1
Foremen 2 Crane helper 1
Surveyor 3 Grader operator 1
Surveyor Asst. /Helper 2 Roller operator 2
ADMINSTRATION STAFF Generator operator 1
Admin 1 Dozer operator 1
Admin Asistant 1 Water pump operator 1
ACCOUNT STAFF DRIVER STAFF
Accountant 1 HTV driver 6
QUANTITY SECTION LTV driver 4
Quantity surveyor 1 Tractor driver 3
Cad operator 2 GENERAL STAFF
LIBORTORY STAFF Cook 3
Lab Technision 1 Office Boy 1
Asst.Lab Technision 1 Cook helper 2
STORE STAFF Washerman 1
Store keeper 1 Sweeper 1
Material supervisor 2
MANPOWER SUB-CONTRACTOR Nos.
BATCHING PLANT STAFF
Batching Plant Incharge 1 Sub-Contractor
Plant Operator 2 Sub-Contractor 3
Electrician 3 STRUCTURE STAFF
Plant Helper 1 Foremen 5
SECURITY STAFF WORKERS STAFF
Security incharge 1 Labours 119
Security guard 13

SKB Manpower Total 93 Sub-Contractor Toal 127


Site Photos

[PHOTO DESCRIPTION] [PHOTO DESCRIPTION]