Progress Report Standard For CPEC-JUL-2020
Progress Report Standard For CPEC-JUL-2020
Project Name Hakla to D.I.Khan Motorway PKG-2C Indus Bridge Rehmani Khel To Balian
Date: 16-Jul-20
Progress Qty
Activity BOQ Remaining
Activities Unit Prev. Achvd % age Plan To Actual To
ID Quantity To Date Var. Quantity
Total Today Completion date date
1 2 3 4 5 6 7=5+6 8 12 13=7 14=13-11 15
C1010 Formation of Embankment 601,619 CM 202,924 - 202,924 34% 499,770 202,924 -296,847 398,696
B1010 Piles Works 198 No. 184 184 93% 198 184 -14 14
B1040 Pier Works 198 No. 167 167 84% 198 167 -31 31
B1060 Casting of Girders 448 No. 175 175 39% 448 175 -273 273
B1060 Stressing of Girders 448 No. 192 192 43% 448 192 -256 256
B1060 Launching of Girders 448 No. 177 2 179 40% 448 179 -269 269
B1090 Construction of Diaphrams 1,980 No. 658 17 675 34% 1980 675 -1,305 1,305
A2040 NJB 1,086 CM 79.80 11.40 91.20 0.08 285 91 -194 995
B1120 Rip Rap Works including filter layers 826 SM - - - - 826 - -826 826
Ancillary Works
A2040 New jersey Barriers 8,484 M 2,227 -2,227 8,484
A2050 Metal beam Guard Rail works 6,600 M 1,049 -1,049 6,600
Quantities Executed
1 - Stressing of girders
6 - Casting of girders
Manpower & Material Summary
Sr. Vehicle Diesel Per m3
Type Activities Status
No ID Drawn Quantit Consumpt
1 Loader 950E 100 For launching of girders Rental
2 Excavator Ex200 100 For removing materials from span Rental
3 Generator 145 For camp
4 Excavator Ex200 300 For removing materials from span
5 Generator 70 For deck slab
6 Tractor 8794 10 For deck slab
7 Crane 3504 60 For launching of girders Rental
8 Tower light 45 For casting of diaphragms
9 Generator 85 For batching plant
10 Pickup 1941 30 For electrician staff
11 Dozer D85 100 For launching of girders Rental
12 Loader 966 100 For batching plant Rental
13 Loader 950 100 For launching of girders Rental
14 Generator 50 For girder yard
15 Pickup 8129 45 For go to mianwali
16 Pickup 845 10 For nespak
Shuttering plates for
17 Diesel 70
slab,girder
18 Trolla 27 30 Steel shifting for deck slab
19 Pickup 1942 10 For workshop staff
20 Diesel 100 For launching company
21 Transit mixture 336 20 For casting of diaphragms,barriers
22 Loader 930 50 For batching plant
23 Loader 950 100 For road work
24 Tractor 4258 11 For steel shifting for girders
25 Roller 50 For road work
26 Crane For steel shifting
27 Tractor 8803 15 For girder yard
28 Generator 20 For camp
29 Concrete pump 20 For casting of diaphragms,barriers
30 Transit mixture 4929 60 For casting of diaphragms,barriers
31 Generator 200 For batching plant
32 Transit mixture 89 50 For casting of girders
SUB TOTAL 2156
Manpower Status Report
Project CPEC-2C, 6.4 Km + Indus Bridge-Rehmani Khel To Kot Balian
Location Hakla (On M-1) To D.I.Khan Motorway
Package 2C
MANPOWER SKB Nos. MANPOWER SKB Nos.
Project Manager 1 WORK SHOP
STRUCTURE STAFF HTV Mechanic 3
Construction Manager 1 Asst.Mechanic 1
Engineer 1 Auto Electrician 1
Supervisor 2 Auto Electrician Helper 1
Foremen 1 Welder & Tiremen 1
Surveyor 3 OPERATOR STAFF
Surveyor Asst. /Helper 4 Loader operator 2
GUID BANK Excavator operator 2
Construction Manager 1 Crane operator 1
Foremen 2 Crane helper 1
Surveyor 3 Grader operator 1
Surveyor Asst. /Helper 2 Roller operator 2
ADMINSTRATION STAFF Generator operator 1
Admin 1 Dozer operator 1
Admin Asistant 1 Water pump operator 1
ACCOUNT STAFF DRIVER STAFF
Accountant 1 HTV driver 6
QUANTITY SECTION LTV driver 4
Quantity surveyor 1 Tractor driver 3
Cad operator 2 GENERAL STAFF
LIBORTORY STAFF Cook 3
Lab Technision 1 Office Boy 1
Asst.Lab Technision 1 Cook helper 2
STORE STAFF Washerman 1
Store keeper 1 Sweeper 1
Material supervisor 2
MANPOWER SUB-CONTRACTOR Nos.
BATCHING PLANT STAFF
Batching Plant Incharge 1 Sub-Contractor
Plant Operator 2 Sub-Contractor 3
Electrician 3 STRUCTURE STAFF
Plant Helper 1 Foremen 5
SECURITY STAFF WORKERS STAFF
Security incharge 1 Labours 119
Security guard 13