Installation and useManualOIL TRANSFORMER PDF
Installation and useManualOIL TRANSFORMER PDF
INDEX
1. GENERAL 02
2. OUTLINE OF THE TRANSFORMER AND THE ACCESSORIES 04
3. STANDARD COMPONENTS AND ACCESSORIES 05
4. RECEPTION, HANDLING, STORAGE 08
4.1 Reception 08
4.2 Handling 08
4.3 Storage 11
5. INSTALLATION 11
5.1 Standard installation conditions 11
5.2 Ventilation 11
5.3 Insulating distances 13
5.4 Earthing connections 13
5.5 LV and HV connections 13
5.6 Regulation of transformation ratio 15
5.7 Parallel connection of transformers 12
6. TRANSFORMER PROTECTIONS 16
7. COMMISSIONING 17
1. GENERAL
This document aims to guide users on the properties of power and distribution transformers insulated
with mineral, silicone or vegetable oil.
Two types of transformers are considered:
I. Plug-in HV terminals
II. Thermometer, to install on the thermometer pocket
III. RIS or equivalent for hermetically sealed transformer
IV. Buchholz Relay for breathing transformer
V. Safety valve
VI. PT100 thermo-resistance (to install in the thermometer pocket)
Picture 05: LV Bushing (Mono block) Picture 06: HV Bushing (Mono block)
Picture 07: Pressure Relief Valve (PRV) Picture 08; Oil Temperature Indicator (OTI) Picture 09; Oil Drain Valve
Picture 10: Off Circuit Tap Switch Picture 11: Magnetic Oil Gauge (MOG)
4.1 Reception
The transformer is generally supplied totally assembled and ready to be connected to the medium and
low voltage line.
According to the specification, the transformer is shipped with a polythene protection, or packed into
wooden cage, for protection against dust and little shocks, or finally packed into a wooden case for
over-sea shipments.
On receipt of the transformer, both at the client's plants or at site, it is necessary to carry out the
following checks:
Check there are no signs of damage on the packing or on the transformer occurred during
the transport.
The characteristics of the transformer detailed on the rating plate must correspond to those of
the shipping documents and with those of the test report, which is attached to the transformer.
Check each transformer is complete with the accessories foreseen in the contract (wheels,
bushing, etc.).
IMPORTANT:
In case any a anomalies are found, please contact immediately to EUROGULF TRANSFORMER
FZE. If within 5 days there will be no notification of anomalies or defects, it can be considered that the
transformer has been delivered in perfect conditions. The manufacturer, therefore, cannot be
considered responsible neither for what could happen to the transformer during service nor for the
eventual consequences.
4.2 Handling
During the transport or the handling, it is recommended to use only the special lifting eyes and tow
attachments ((Picture 12 & 13).
IMPORTANT: The transformer cannot be moved pushing the cooling fins or radiators or tank.
Ropes must be arranged so as not to interfere with the radiators or cooling fins.
Lifting can be made using the appropriate hooks remembering to use ropes long enough so that H is
never less than L (Picture 12).
Always use all the existing hooks and not only one of them.
Example of handling
4.3 Storage
5 INSTALLATION
The maximum height of installation must not exceed 1000 m above sea level.
When the transformer is in service, the ambient temperature of the room must be within the following
limits:
• Minimum temperature: -25°C
• Yearly average temperature: +20°C
• Monthly average temperature: +30°C
• Maximum temperature: + 40°C
In case the height of the place of installation and/or the ambient temperature values are higher than the
ones specified above, it is necessary to specify it at the ordering stage since a particular dimensioning of
the transformer depends upon these values.
5.2 Ventilation
The electric current passing through the windings and the effect of the core magnetizing current
produce electrical losses resulting in localized heating of the windings and core.
The transformer is designed in such a way that natural cooling maintains the transformer temperature
under the maximum values foreseen by the standards.
In order to avoid temperature accumulation in the room where the transformer is installed, it is
necessary to provide suitable ventilation.
Each EUROGULF make transformer is equipped with a thermometer pocket where a thermometer
with contacts may be installed (optional accessory).
The suggested values for setting the contacts are following (oil temperature):
Description Alarm °C Trip °C
Natural cooling
In the room where the transformer is installed, it is necessary to install air louvers sufficient
to dissipate the heat generated by transformer during service, in order to guarantee the
standard service conditions and to prevent exceed the over temperature limits of the transformer.
Therefore the room must be provided with a louver on the lower part S, in order to guarantee an
appropriate fresh air flow; and a louver S’ on the upper part of the opposite wall, in order to
extract the hot air (Picture 16)
In order not to obstruct cooling is necessary that the transformer is installed at a distance not less than
30 cm from the walls and not less than 60 cm from other transformers.
Forced cooling
The forced cooling can be realized by means of installation of air extractor located in the upper part
of the room controlled by a suitable thermostat or directly by a transformer thermal protection relay,
with a suggested flow of approx. 3.5 to 4 m3/min for each kW of total losses at 120 °C (if the losses are
at 75°C, they must be multiplied by 1.15).
ATTENTION: an insufficient air circulation, besides reducing the nominal life of the transformer,
causes over heating which, in the worst cases, can determine the intervention of the thermal protection
relay.
The transformer, also with plug-in bushing, must be protected against direct contacts.
EUROGULF is not responsible for the transformer installation. The installation must be carried out
according to the standards in force, to the applicable laws and to the present instructions.
The following points must be taken into consideration when the installation is carried out:
• Connect the earthing conductors to the relative earth points on the metallic parts of the
transformer and cable boxes.
• Connect the low voltage neutral to earth when required or when required by the protection
system to earth.
Cables and the bus bars which are connected to the transformer must be duly fixed to avoid any
mechanical stress on LV and HV transformer terminals.
Both upper and bottom cable connections can be performed, being sure, however, to respect the
configuration showed in the drawings. In case the connections arrive from the bottom please ensure
that there is sufficient depth for the bending of the cables.
Cables and/or the bus bars which are connected to the transformer must enter in the cable boxes
only through suitable flanges specified at the ordering stage.
IMPORTANT:
In any case the cables and/or the bus bars must be duly fixed outside the cable boxes to avoid any
mechanical stress on the LV and HV terminals of the transformer and also on the cable boxes. After
the installation please check the correct degree of protection is maintained near the passageway of the
cables and/or the bus bars.
Note:
At the time of shipping, the position of the voltage off-loads tap-changer are located on the central tap.
In case of transformers with double ratio, please be sure that the position corresponding to the voltage
of the system feeding the transformer is properly connected.
Note:
At the time of shipping, the position of the voltage off-load tap-changer are connected on the position
of the higher primary voltage.
Important:
In case of transformers with double ratio, please be sure the tap corresponding to voltage of the
system feeding the transformer it-self, is duly connected.
In case the position of the tap-changer has to be changed after the transformer has been put
into service the first time, it is recommended to put the transformer out of service and to connect
to ground the LV and HV circuits before approaching the transformer.
If the transformer must be connected in parallel with other transformers, please verify the total
compatibility of the voltage ratio and of the conditions stated by the IEC 60076-1 standards, and
particularly:
• Identical voltage ratio
• Identical frequency of functioning
• Identical vector group
• Identical short circuit voltage (Tolerance ± 10%)
• The rated power (kVA) of the biggest transformer should not be larger than twice the
smallest transformer
• The LV connections must be the same length from the LV terminals (of two different units) to
the switch junction
6 TRANSFORMER PROTECTIONS
• The thermometer is generally installed in the thermometric pocket on the cover of the tank. The
thermometer may be equipped with two settable contacts, one for alarm, and the other for trip.
The suggested values are written at paragraph 5.2.
• The integrated safety device for hermetically sealed transformer (RIS or equivalent) provides:
Two settable contacts for temperature, one for alarm and the other for trip. The suggested
values are written at paragraph 5.2.
one settable trip contact for pressure (The suggested value is 0.3 bar)
one trip contact for oil level
The protections setting and/or the choice of fuses HV and LV side, must be carried out taking into
consideration the primary and secondary rated currents stated in the transformer rating plate, taking
also into consideration that when we feed the transformer, a very high magnetizing current is
established on the primary, by means of variable starting from a minimum of 10 times the rated
current (in the worst conditions of insertion depending from the instant when the feeding circuit is
closed, from the electric characteristics of the feeding network, from the reactance and resistance
values of the circuit network-transformer, the insertion current can reach also 20 times the rated
current), even if the automatic switch located on the secondary is open and therefore without loading.
Therefore, it is necessary to duly set the relay of maximum current HV side, in current and time value,
by introducing a little delay (approx. some tens of ms), in such a way that the protection relay will not
operate.
Furthermore, EUROGULF suggest limiting the number of connections and disconnection of the
transformer on the network.
7 COMMISSIONING
Bushing
Mechanical parts
• Verify that the position of the tap-changer is inserted correctly. In case of double primary
voltages (Dual Ratio Transformer) , please check the feed to the transformer correspond to the
correct position.
• Check the correct functioning of the switches located as protection of the transformer on HV
and LV side.
• Check the correct setting and functioning of the overloading and short-circuit protection relay.
• Check the correct setting and functioning of the over-temperature protection relay and of the
thermometer.
• Check the functioning of the fans.
• Check the general conditions of the transformer and proceed with the measurement of the
insulating resistance (IR) by means of a Megger at 2500 V.
This measurement must be carried out with HV and LV terminals disconnected from the equipment, it
means before connecting the cables and/or the bus bars.
The values of the measured resistances must be approx. the following:
In case the measured values are lower, please contact EUROGULF after sale service.
ATTENTION:
In case a transformer is put into service after a long storage period, or after a long de-energised period, it
will be necessary:
Clean the HV/LV bushings from eventual dust and condensation by means of dry compressed
air jets and dry cloth.
if the transformer has been held in stock far more than six months in normal climates or far more
than a month in damp climates, check the dielectric strength of the insulating oil. Using the
procedure established by the IEC standard to check the dielectric strength of the insulating oil, if
the test is negative proceed to dry the dielectric oil of the transformer, otherwise contact
EUROGULF TRANSFORMER FZE.
It is recommended, finally, to carry out always a visual check of the transformer in order to verify any
unlikely presence on the surface the cooling ducts
Check that the reading on the level indicator approximately correspond to ambient temperature
(transformer with conservator or RIS for hermetically sealed).
If the insulating fluid needs to be topped up, only fluid with the same characteristic and not
containing PCBs must be used and with the required dielectric strength.
IMPORTANT
Insulation Class A B
[kV] [mm] [mm]
12 ≥15 70
17.5 ≥15 90
24 ≥15 100
36 ≥15 200
If the transformer is equipped with Silica gel Breather (transformer with conservator), check that the
salts of silica gel are orange/Blue. If they are neutral color, they have already picked up moisture and do
not fulfil their function as dehydrating air. It is necessary to remove the salts and regenerate the dryer by
placing them in an oven at 150°C until they are come back to orange/Blue color.
If the transformer is equipped with Buchholz relay (transformer with conservator) to avoid
unnecessary activation, proceed carefully with the leaking operation of the relay, acting on the taps
(see instruction relay). If during commissioning or in the first hours of the energization the Buchholz
relay should signal the formation of gas, in small quantities, first to believe that there is a fault in the
transformer and repeat the leaking operation.
7.7 Thermometer
If the transformer is equipped with the thermometer (Oil temperature Indicator (OTI) and Winding
Temperature Indicator (WTI) check the threshold of the alarm and trips are set at the operating
conditions. The setting temperature is provided to the manufacturers in according to transformer type
and the insulation class.
• Closing of HV switch
When the switch is closed the transformer gives out a sharp noise, which decreases in few ms until it
stabilizes.
Before closing the low voltage switch or make additional checks for parallel operation with other
transformers, it is necessary:
Check by means of a voltmeter the proper value between each two phases and of the
three wye-connected voltage.
Check the proper phases displacement and the correct vector group.
In case the values correspond to those stated in the rating plate, it is possible to proceed and complete
the commissioning or to carry out the checks for the parallel service.
In case the transformer has to run in parallel with another, it is also necessary:
Check the compatibility of the rating plates of both transformers
Verify the concordance of the phases by measuring the voltage between the phase "one"
of the transformer already in service and the phase "one" of the transformer to be
connectedin parallel by means of a voltmeter. The value of this result must be zero.
Continue in the same way for phase 2 and phase 3
• Closing of LV switch
IMPORTANT
We remind you that qualified technical personnel must carry out the operation, commissioning and
energization. Furthermore, during the voltage measurements and the phase displacement checks on the
upper terminals of the LV switches, you are recommended to use suitable instruments and suitable
insulating gauntlets.
For more accurate and complete checks, please contact our Assistance Service
Phone (+971)-065261116
Fax (+971)-065261114
E-Mail [email protected]