Work Procedure For Earth Work: Excavation 1.1

The document provides work procedures for earth excavation. It outlines the resources needed including machinery, tools, and human resources. It describes the method of excavation including setting out the work area, using a mini backhoe for excavation while checking depth, leveling and compacting the excavated area, protecting excavated sides, and finally backfilling the area with existing soil once approved.

Uploaded by

aruan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
101 views2 pages

Work Procedure For Earth Work: Excavation 1.1

The document provides work procedures for earth excavation. It outlines the resources needed including machinery, tools, and human resources. It describes the method of excavation including setting out the work area, using a mini backhoe for excavation while checking depth, leveling and compacting the excavated area, protecting excavated sides, and finally backfilling the area with existing soil once approved.

Uploaded by

aruan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

WORK PROCEDURE FOR EARTH WORK

EXCAVATION
1.1 Resources to be used.
a. Machineries
i. Mini Backhoe
ii. Plate Compactor
iii. Rammer machine

b. Tools
i. Mammoty
ii. Pick Axe
iii. Wheel barrows
iv. Showel
v. Leveling Instrument
vi. Theodolite
vii. Staff
viii. Measuring Tape
ix. Steel pegs, strings and white lime
x. Steel pans

c. Human resource
i. Engineer
ii. Technical Supervisor
iii. Unskilled Labour

1.2 Method of Excavation


a. Setting Out
 A setting out will be done for every excavation using Theodolite by the engineer
with assistants.
 The working drawings will be used for setting out work.
 Setting out will be marked using timber pegs, strings and lime mark on soil.
 Levels will be maintained with “…..katha ”
 Setting out will be checked by Engineer before excavation.

b. Excavation
 Mini backhoe will be utilized for the excavation - See attached figure 01
 The excavation depth will be checked using leveling instrument and the staff by
the technical supervisor.
 Excavation sequence see attached figure No 02.
 Bottom of excavation will be leveled manually to the required level and compact
using plate compactor.
 Side of excavation will be kept at 45 degree angle up to 1m depth wherever
possible.

c. Protection
 The excavation area will be demakated using barricade tape stretched on 12mm
steel bars, around the perimeter.
 Sides of excavation will be protected using polythene sheets laid and fixed to the
soil using steel nails.
 Excavated soil will be used for protection for rainy time around the building.
 Excavated material will be stacked near by area for back filling.

1.3 BACK FILLING


 After getting prior approval from engineer, existing soil will be used for backfill.