Work Procedure For Earth Work: Excavation 1.1
Work Procedure For Earth Work: Excavation 1.1
EXCAVATION
1.1 Resources to be used.
a. Machineries
i. Mini Backhoe
ii. Plate Compactor
iii. Rammer machine
b. Tools
i. Mammoty
ii. Pick Axe
iii. Wheel barrows
iv. Showel
v. Leveling Instrument
vi. Theodolite
vii. Staff
viii. Measuring Tape
ix. Steel pegs, strings and white lime
x. Steel pans
c. Human resource
i. Engineer
ii. Technical Supervisor
iii. Unskilled Labour
b. Excavation
Mini backhoe will be utilized for the excavation - See attached figure 01
The excavation depth will be checked using leveling instrument and the staff by
the technical supervisor.
Excavation sequence see attached figure No 02.
Bottom of excavation will be leveled manually to the required level and compact
using plate compactor.
Side of excavation will be kept at 45 degree angle up to 1m depth wherever
possible.
c. Protection
The excavation area will be demakated using barricade tape stretched on 12mm
steel bars, around the perimeter.
Sides of excavation will be protected using polythene sheets laid and fixed to the
soil using steel nails.
Excavated soil will be used for protection for rainy time around the building.
Excavated material will be stacked near by area for back filling.