Work Method Statement - Handling Loading Unloading and Stringing Pipes
Work Method Statement - Handling Loading Unloading and Stringing Pipes
S IRT E OIL
COMPANY Contract Number : 98 208-530-410
Project N° TP-210364 GT
Sheet 1/ 12
S IRT E OIL
COMPANY Contract Number : 98 208-530-410
Project N° TP-210364 GT
Sheet 2/ 12
CONTENTS
1 ABBREVIATIONS ....................................................................................... 3
2 DEFINITIONS ............................................................................................. 3
3 PURPOSE .................................................................................................. 4
4 RESPONSIBILITIES ................................................................................... 4
5 DESCRIPTION OF WORKS........................................................................ 6
5.1 Pipe Handover ..........................................................................................................6
5.2 Lifting of Pipe ............................................................................................................6
5.3 Transportation of pipe: ..............................................................................................8
5.4 Stringing: ...................................................................................................................8
5.5 Control of Stringing ...................................................................................................9
9 REPORTING ............................................................................................ 12
9.1 Daily activity report ..................................................................................................12
9.2 pipeline stringing report ...........................................................................................12
S IRT E OIL
COMPANY Contract Number : 98 208-530-410
Project N° TP-210364 GT
Sheet 3/ 12
1 ABBREVIATIONS
The following acronyms, abbreviations and meanings are used in this document:
Acronym Significance
API RP 5L1 Recommended Practice for Railroad Transportation of Line Pipe
JS-CP-0003 Pipeline and Buried In-Plant Piping Corrosion Coating
Inch (“) Unit of measure 1” = 25.4 mm
° Degrees (angular)
PM Project Manager
CM Construction Manager
PE Project Engineer
QA/QC Quality Inspector
QCP Quality Control Plan
PPE Personal Protective Equipment
HSE Health, Safety and Environments
2 DEFINITIONS
Definition Description
PROJECT Replacement of 11 Kilo meters of Brega - Misurata 34” Gas Pipeline (Brega-
Sidra section Km 5+100 to Km 16+595)
COMPANY SIRTE OIL COMPANY for Production, Manufacturing of Oil & Gas
CONTRACTOR Consortium between ALSHOLA ALMUDIA & SOLCOMEI forming awarding
entity of this CONTRACT
CONTRACT Means the document agreed and executed by the COMPANY and
CONTRACTOR
JOB SAFETY Risk assessment tools used to identify and control workplace hazards which
ANALYSIS helps integrate accepted safety and health principles and practices into a
(JSA) particular task or job operation
RISK Is the determination of quantitative or qualitative value of risk related to a
ASSESSMENT concrete situation and recognized threat (also called Hazard). Quantitative risk
assessment requires calculations of two components of risk(R): The magnitude
of the potential loss (L) and the probability (P) that the loss will occur
QUALITY A document that defines specific elements or processes of the scope of work
CONTROL that requires to be inspected.
PLAN (QCP)
S IRT E OIL
COMPANY Contract Number : 98 208-530-410
Project N° TP-210364 GT
Sheet 4/ 12
3 PURPOSE
The method statement defines the work involved pipe unloading, hauling and stringing for
construction of replacement of 11 kilometres of the Brega – Sidra 34” Gas Pipeline .
The procedure also provides the broad outline as to how the site works shall be executed,
controlled and delivered as per schedule with utmost importance to ensure that Pipeline
construction is performed in accordance with the relevant specifications and drawings
quality, H&S and Environmental requirements.
The purpose of this procedure is to ensure that the pipe transportation from Storage Yard in
Marsa el Brega to the work site has been made according to contract requirements.
4 RESPONSIBILITIES
CONTRACTOR shall be responsible for the execution of Loading , Unloading, Hauling and
stringing. Site works will be performed by experienced persons under the supervision of the
relevant person in charge.
Key personnel responsible for safe and effective execution of the pipe operation will include
but not limited to:
S IRT E OIL
COMPANY Contract Number : 98 208-530-410
Project N° TP-210364 GT
Sheet 5/ 12
Stringing Foreman:
Verifying the correct execution of stringing operation
Collaborate with QA/QC Engineer for records
Monitor the condition and timely inspection of equipment
Specify pipe stringing places and order for crane operators and riggers
Contractor Document Number: SRTPPL-PPL-ME-WP-001 Rev 02
PROJECT REPLACEMENT OF 34 INCH
Project: Work Method Statement For Handling & Staking
PIPELINE SECTION X 11 KM Pipes In Laydown Areas Transport And Stringing
S IRT E OIL
COMPANY Contract Number : 98 208-530-410
Project N° TP-210364 GT
Sheet 6/ 12
5 DESCRIPTION OF WORKS
As a first to beginning, the FOREMAN must be present at the pipe handling, loading,
unloading and stringing.
Prior to commencement, all services shall have been located, the safety supervisor must
check if flatbed truck designed for transportation are in proper condition. Truck loading bed
shall be flat and free from any object that can damage the pipes.
QC supervisor must check in addition of the condition and inspection of pipes, that all pipes
marking exist.
Defective pipes shall be marked and positively for return, also non-conformance reports are
filled out for these pipes.
S IRT E OIL
COMPANY Contract Number : 98 208-530-410
Project N° TP-210364 GT
Sheet 7/ 12
The Pipe Hook Standard comes with a shackle pin. The work should start with removing grease
and dirt from the Pipe Hook and Shackle so the equipment can be checked properly. A visual
check whether the Pipe Hook or shackle shall be performed for any damages .
Soft rubber padding between the pipes shall be used to protect pipe rubbing during traveling.
S IRT E OIL
COMPANY Contract Number : 98 208-530-410
Project N° TP-210364 GT
Sheet 8/ 12
5.4 STRINGING:
The truck driver shall enter the area of the ROW to transport pipes from the designated
access roads, or using the ROW as access road. The truck driver shall safely remove the tie
down straps as required during unloading. Lift one length of pipe from the truck and signal
the driver to move forward. At the stringing front, line pipe shall be offloaded individually by
means a crane to unload the pipe from the pipe trucks and to place them above sand bags .
Foreman is responsible for unloading and stringing of pipes at their designated locations
according to drawings .
Contractor will ensure that pipe will be positioned on sand bags to protect the external
coating.
The height of sand bags will be approximately 400mm – 500 mm from ground.
S IRT E OIL
COMPANY Contract Number : 98 208-530-410
Project N° TP-210364 GT
Sheet 9/ 12
Rolling, dropping, dragging the pipes along the ground shall not be allowed. Pipes shall be
string along pipeline route as per relevant alignment drawings.
Pipes shall not be placed end-to-end but rather parallel to each other and at an angle to the
trench axis. This is necessary in order to carry out the bevel facing operation prior to line up.
The optimum wall-to-wall distance of adjacent pipes will be identified by Contractor Pipe
Fitters and checked by Company Supervisor .
S IRT E OIL
COMPANY Contract Number : 98 208-530-410
Project N° TP-210364 GT
Sheet 10/ 12
The item issued to the worker must be periodically inspected and changed if it is
damaged or does not respect the specified conditions:
Helmet
Hand Gloves
Dust Mask (If Required)
Safety Glasses
Safety Shoes.
High Visibility vest.
Safety precautions shall be of paramount importance to prevent any danger to the public and
any operations carried out adjacent to public access shall be closely monitored by the Safety
Department.
During loading Unloading, Hauling and Stringing operations extreme care shall be taken to
provide a safe working environment and to avoid damage of coated pipe.
This will ensure that any potential emergencies during lifting ( loading / unloading )
operations and subsequent operations are dealt with Safety Company Requirements .
The emergency plan will include measures for:
Avoiding incidents, such as the release of hazardous materials, which might threaten the
safety of people .
CONTRACTOR recognize that their operations and activities have the potential to give
rise to emergencies and will seek to conduct its operations in such a way as to prevent
harm to its employees.
All drivers and equipment operators will be provided with a detailed Emergency Contact
Number List; this will detail where assistance may be reached when needed, during
personnel movements, loading, unloading and transporting of materials (i.e. Locations
and telephone numbers of Project Manager, Construction Manager , and site supervisor
HSE Manager …
S IRT E OIL
COMPANY Contract Number : 98 208-530-410
Project N° TP-210364 GT
Sheet 11/ 12
7 LIST OF EQUIPMENT
Stringing operations are performed under the direction by rigger appointed by
CONTRACTOR Foreman , which bear responsibility for safe execution of works.
The following equipment and tools will be used for stringing operations:
S IRT E OIL
COMPANY Contract Number : 98 208-530-410
Project N° TP-210364 GT
Sheet 12/ 12
9 REPORTING
Line pipe stringing shall record the pipe details together with the location where the pipe has been
strung as described in the Inspection Test Plan (ITP). Stringing activity must be completed and
submitted to QC for approval prior to welding.