List of Amendments For "Guide To Application For Water Supply" (October 2019 Version)

This document lists 45 amendments made to the October 2019 version of the "Guide to Application for Water Supply". The amendments incorporate new requirements from various circular letters, rearrange sections for better comprehension, update submission requirements and timing, and make minor textual changes. Key amendments include new sections on anti-corruption requirements, essential plumbing design aspects, pretreatment of fittings, and water sampling procedures. Appendices were also added or revised to reflect the latest circular letters and technical requirements.

Uploaded by

peter
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
121 views

List of Amendments For "Guide To Application For Water Supply" (October 2019 Version)

This document lists 45 amendments made to the October 2019 version of the "Guide to Application for Water Supply". The amendments incorporate new requirements from various circular letters, rearrange sections for better comprehension, update submission requirements and timing, and make minor textual changes. Key amendments include new sections on anti-corruption requirements, essential plumbing design aspects, pretreatment of fittings, and water sampling procedures. Appendices were also added or revised to reflect the latest circular letters and technical requirements.

Uploaded by

peter
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

List of Amendments for “Guide to Application for Water Supply” (October 2019 version) 

 
Location 
No. of Amendment  Highlight of major amendment 
(Section) 
Amendment 1  ‐ All appendix numberings are changed from Roman numerals to Arabic numerals. 
Amendment 2  Preface  New  paragraph  is  added  to  incorporate  the  content  related  to  Awareness  of  Anti‐corruption  and  Probity 
Requirements as per ICAC’s recommendation. 
Amendment 3  1.2  Minor textual changes to the content of “works of a minor nature”. 
Amendment 4  2  New  paragraph  is  added  to  provide  the  “essential  aspect  of  plumbing  design”  for  applicant’s  and  designers’ 
reference. 
Amendment 5  3.1  New paragraph is added to incorporate the context of Circular Letter No. 1/99. 
Amendment 6  3.2.1A  New sub‐section is added to incorporate the requirements stated in Circular Letter No. 6/2018 for the submission 
requirements of Form WWO 1149. 
Amendment 7  3.3.1  Content in Section 4.7.1 is rearranged to Section 3.3.1 to state the requirements of pretreatement of fittings/use 
of low leaching rate fittings (with the introduction of GA* fittings) for online re‐plumbing works. 
Amendment 8  3.10  New section is added to incorporate the context of Circular Letter No. 6/2018. 
Amendment 9  3.11  New section is added to incorporate the context of Circular Letter No. 5/2018. 
Amendment 10  3.12  New section is added to incorporate the context of Circular Letter No. 2/2019. 
Amendment 11  4.1  To incorporate the requirements stated in Circular Letter No. 6/2018 for  the submission requirements of Form 
WWO 1149. 
Amendment 12  4.1.1 – 4.1.2   To incorporate the requirements  stated in  Circular Letter  No.  6/2018 for the submission requirements of 
Form WWO 1149. 
 To amplify the requirements of adopting low leaching rate products other than GA*. 
Amendment 13  4.1.3    New sub‐section is added to incorporate the context of Circular Letter No. 2/2019. 
Amendment 14  4.2  The notes at the end of 1st paragraph is deleted as it is not required. 
Amendment 15  4.2.1 – 4.2.2  Minor changes to the timing of MIT submission so that the MIT with meter reading after satisfactory systematic 
flushing and water sampling are carried out (i.e. before issuance of Part V(b)) shall be provided on the MIT and 
submitted  to  WSD.    The  meter  readings  after  satisfactorily  systematic  flushing  shall  be  provided  as  initial 
readings of the water meters in MIT shall be provided. 
Amendment 16  4.2.3  New sub‐section is added to incorporate the context of Circular Letter No. 7/2017 Part (B).    The context of Part 
(A) had been included in Section 3.6. 
Amendment 17  4.2A  New sub‐section is added to incorporate the context of Circular Letter No. 2/2019. 
Amendment 18  4.3.1.2  Minor  changes  to  the  provide  clearer  wording  for  the  requirement  of  submitting  systematic  flushing 
record/pretreatment record together with Form WWO 46 Part IV. in unoccupied/occupied buildings   
Amendment 19  4.3.2A  New sub‐section is added to incorporate the context of Circular Letter No. 2/2019. 
Amendment 20  4.3.3  To incorporate the requirements stated in Circular Letter No. 6/2018 for  the submission requirements of Form 
WWO 1149. 
Amendment 21  4.3.3A  New sub‐section is added to incorporate the context of Circular Letter No. 2/2019. 
Amendment 22  4.4.1   To  incorporate  the  requirements  stated  in  Addendum  to  Circular  Letter  No.  9/2017  for  the  required 
systematic flushing record in different type of projects. 
 To incorporate the context of Circular Letter No. 2/2012 as Appendix 25. 
Amendment 23  4.4.1A  To  provide the procedures for cleansing, disinfection and  water  sampling  requirement for fresh water flushing 
and fire service supply of new buildings. 
Amendment 24  4.4.2  To incorporate the context of Circular Letter No. 2/2012 as Appendix 25. 
Amendment 25  4.5   Minor  changes  to  the  timing  of  MIT  submission  so  that  the  MIT  with  meter  reading  after  satisfactory 
systematic flushing and water sampling are carried out (i.e. before issuance of Part V(b)) shall be provided 
on the MIT and submitted to WSD. 
 Update the timing to effect water supply (“7‐day requirements”) from the “date of disinfection” to “date of 
water sampling with satisfactory results”. 
Amendment 26  4.5.1  New section is added to incorporate the context of Circular Letter No. 1/2019. 
Amendment 27  4.6  Minor changes to the timing of collection of 24‐hr stagnation water samples for data acquisition and evaluation. 
Amendment 28  4.7.1  Its original content is relocated in Section 3.3.1 and 4.3.1.2 for better comprehension. 
Amendment 29  4.8  To incorporate the requirements stated in Circular Letter No. 6/2018 for  the submission requirements of Form 
WWO 1149. 
Amendment 30  5.1 – 5.2  Minor textual changes to reflect that WWO 46 Part V will not be issued anymore and WWO 46 Part V is equivalent 
to issuance of WWO 46 Part V(b). 
Amendment 31  6  The term “Efficiency Office” is used instead of mentioning “former Efficiency Unit”. 
Amendment 32  7.1  The Form WWO 46 “Part V(b)” is added to  reflect that  the meaning in the original text “approved Form WWO 
46” is equivalent to Form WWO 46 Part V(b). 
Amendment 33  8  Minor textual changes to reflect that WWO 46 Part V will not be issued anymore and WWO 46 Part V is equivalent 
to issuance of WWO 46 Part V(b). 
Amendment 34  Appendix 1  The  “Checklist  for  Vetting  Plumbing  Proposal”  is  revised  to  reflect  the  updated  version  of  “Technical 
Requirements of Plumbing Works in Buildings” (Oct 2019) 
Amendment 35  Appendix 1A  To include the list of essential aspects of plumbing design for reference of plumbing designers/applicants. 
Amendment 36  Appendix 2   To incorporate the requirements  stated in  Circular Letter  No.  6/2018 for the submission requirements of 
Form WWO 1149. 
 Provide further information on the required content of each drawings submission 
 To incorporate the requirements stated in Circular Letter No. 2/2019 
 To incorporate the requirements stated in Addendum to Circular Letter No. 9/2017 
 Minor change to the timing of MIT submission. 
Amendment 37  Appendix  3,  To  incorporate  the requirements stated in Circular Letter No. 6/2018 for  the submission requirements of Form 
6, 7  WWO 1149. 
Amendment 38  Appendix 17  To incorporate the requirements stated in Addendum to Circular Letter No. 9/2017. 
Amendment 39  Appendix 18  The title is changed so that the record form is for new village house. 
Amendment 40  Appendix  New appendix is added to incorporate the requirements stated in Addendum to Circular Letter No. 9/2017. 
18A   
Amendment 41  Appendix 19   To provide the sampling requirements and sampling protocols for fresh water flushing and fire services fresh 
water system. 
 To update the party responsible for carrying out water sampling and analysis.    Water sampling and analysis 
at  all  locations  (including  at  connection  point)  and  for  any  pipe  size  can  be  carried  out  by  accredited 
laboratories.    LPs can also request Water Science Division of WSD to carry out water sampling and analysis 
at connection point of any pipe size. 
 To update and incorporate the context of Circular Letter No. 2/2012. 
Amendment 42  Appendix 22  New appendix is added to incorporate the context of Appendix 2 of Circular Letter No. 7/2017. 
Amendment 43  Appendix 23  New appendix is added to incorporate the context of Appendix 3 of Circular Letter No. 7/2017. 
Amendment 44  Appendix 24  New appendix is added to incorporate the context of Appendix 4 of Circular Letter No. 7/2017. 
Amendment 45  Appendix 25   New appendix is added to incorporate the context of Circular Letter No. 2/2012.   
 Update  the timing to  operate  the new  inside service (“7‐day requirements”) stated in Circular Letter No. 
2/2012 from the “date of successful disinfection” to “date of water sampling with satisfactorily results”. 
Amendment 46  Appendix 26  New appendix is added to incorporate the context of Appendix A of Circular Letter No. 2/2019. 
 