Parameter Determination For Modeling System Transients-Part VI - Circuit Breakers
Parameter Determination For Modeling System Transients-Part VI - Circuit Breakers
Abstract—A detailed dynamic arc model may be used to roughly transient recovery voltage (TRV) withstand capability for
evaluate the interrupting capacity of a breaker and its influence the breaker.
on the deformation of the interrupted current. In some cases 2) A more elaborate model considers the arc as a time-
the correct computation of the actual arcing time is of crucial
importance for assessing the first current-zero crossing of the varying resistance or conductance. The time variation
breaker. Arc models in conjunction with surrounding network is determined ahead of time based on the breaker char-
details are also used to understand complex arc instability prob- acteristic and perhaps upon the knowledge of the initial
lems. This paper recalls gas circuit breaker models and presents interrupting current. This model can represent the effect
data requirement for such models. The document includes some of the arc on the system, but requires advanced knowl-
illustrative examples and typical data.
edge of the effect of the system on the arc. Arc parameters
Index Terms—Circuit breakers (CB), modeling, power system are not always easy to obtain and the model still requires
transients, simulation. the use of precomputed TRV curves to determine the
adequacy of the breaker.
I. INTRODUCTION 3) The most advanced model represents the breaker as a dy-
namically varying resistance or conductance, whose value
TABLE I
MODELING GUIDELINES FOR CBs [3]
scribing arc behavior using parameters with different physical cooling power. An extra parameter is needed to specify the
interpretation. number of breaks per pole.
Basic descriptions of arc behavior were first described by Parameters for this model have been derived from experi-
Cassie and Mayr. mental tests and this model has been successfully used and val-
• The Cassie model is given by the following equation: idated in [5], [10], [12], and [13].
This model can be used to represent thermal failure near cur-
rent interruption and conductivity in the post-arc region. Re-
(1) sistance instability near current interruption can cause current
chopping. Although parameters for this model are best derived
It assumes an arc channel with constant temperature, cur- from short-line fault (SLF) breaking tests, it is, however, feasible
rent density, and electric field strength. Changes of the arc to provide some typical data. It has been observed through prac-
conductance result from changes of arc cross section; en- tical cases that the applicability range of (4) is actually longer
ergy removal is obtained by convection. than the near current-zero region.
• The Mayr model is given by the following equation: Although in some cases it is feasible to simulate arc model
equations using control diagram blocks and sufficiently small
time steps, the best solution is achieved using a hard-coded arc
(2)
model with sophisticated iterative techniques, as explained in
[5]. The highly nonlinear model of (4) still requires a small
This model assumes that changes of arc temperature are integration time step to correctly account for its time constants
dominant, and size and profile of the arc column are con- and achieve nonlinear solution method convergence. Such
stant. Thermal conduction is the main mechanism of en- a small time step (0.1 s typically) requires a prohibitive
ergy removal. computer time for statistical studies. Another difficulty is the
where is the arc conductance, is the arc voltage, is the availability of parameters from the breaker manufacturer. This
arc current, is the arc time constant, is the steady-state is why a simplified arc model must be used in statistical studies
power loss, and is the constant part of the arc voltage. The [10], [17]. Such a model combines a current-arc voltage char-
is in the region of 1 s and the is between 0.1 and acteristic per break and a time-dependent function
0.5 s . These parameters are not strictly constant for an to account for blast pressure, arc length, and arcing time.
actual arc, but observations indicate that during the brief time Contrary to the Avdonin equation, this simplified model cannot
around current-zero, these parameters vary sufficiently slowly account for thermal reignition, but it can correctly compute
to assume them to be constant. A combination of both models the breaker’s arcing time with a larger integration time step
gives the Cassie-Mayr model (typically 70 s). The functions and must be
provided by the manufacturer.
Other arc models are presented in the Appendix.
(3)
V. CONCLUSION
The resistance of a CB dynamic arc during the thermal period
can pass from zero to infinity in a few microseconds. Several
models have been developed and implemented for duplicating
the performance of a CB near current zero.
Modeling of such nonlinear behavior must be based on pa-
rameters determined from accurate measurements. Validation
must be also carried out with accurate models of the test cir-
cuits. In addition to the arc model, it is essential to correctly
model the network surrounding the breaker. Sensitivity analysis
approaches must be used to observe complex arc-network inter-
Fig. 6. Kilometric fault strength of the modeled arc.
action problems.
Some default values of arc model parameters are provided in
the literature. However, users must be warned about the validity
of these values; they should be considered as an initial estima-
tion or just a reference.
APPENDIX
OTHER ARC MODELS
1) The Urbanek model can represent arc interruption and
both thermal and dielectric failure [14]. Both current
chopping and reignition are also represented. It is charac-
terized by the following equation for the arc conductance:
(10)
[2] L. van der Sluis, W. R. Rutgers, and C. G. A. Koreman, “A physical arc [11] A. V. Avdonin et al., Some problems of EHV and UHV air-blast circuit
model for the simulation of current zero behavior of high-voltage circuit breakers, in CIGRE 1980 Session. Paper 13-04.
breakers,” IEEE Trans. Power Del., vol. 7, no. 2, pp. 1016–1022, Apr. [12] G. St-Jean, M. Landry, M. Leclerc, and A. Chenier, “A new concept in
1992. post-arc analysis to power circuit breakers,” IEEE Trans. Power Del.,
[3] CIGRE Working Group 13.01, “Applications of black box modeling to vol. 3, no. 3, pp. 1036–1044, Jul. 1988.
circuit breakers,” Electra, no. 149, pp. 40–71, Aug. 1993. [13] G. St-Jean and R. F. Wang, “Equivalence between direct and synthetic
[4] J. A. Martinez-Velasco, “Circuit breaker representation for TRV calcu- short-circuit interruption tests on HV circuit breakers,” IEEE Trans.
lations,” in EEUG Meeting, Hannover, Germany, Nov. 13–15, 1995. Power App. Syst., vol. PAS-102, no. 7, pp. 2216–2223, Jul. 1983.
[5] J. Mahseredjian, M. Landry, and B. Khodabakhchian, “The new EMTP [14] L. Blahous, “The problem of defining a test circuit for circuit breakers
breaker arc model,” in Proc. IPST, Seattle, WA, Jun. 22–26, 1997, pp. in terms of prospective voltage,” Proc. Inst. Elect. Eng., vol. 126, no. 12,
245–249. pp. 1291–1294, Dec. 1979.
[6] J. Kosmac and P. Zunko, “A statistical vacuum circuit breaker model for [15] , “Derivation of circuit breaker parameters by means of Gaussian
simulation of transients overvoltages,” IEEE Trans. Power Del., vol. 10, approximation,” IEEE Trans. Power App. Syst., vol. PAS-101, no. 12,
no. 1, pp. 294–300, Jan. 1995. pp. 4611–4616, Dec. 1982.
[7] M. T. Glinkowski, M. R. Gutierrez, and D. Braun, “Voltage escalation [16] E. Thuries, P. Van Doan, J. Dayet, and B. Joyeux-Bouillon, “Synthetic
and reignition behavior of vacuum circuit breakers during load shed- testing method for generator circuit breakers,” IEEE Trans. Power Del.,
ding,” IEEE Trans. Power Del., vol. 12, no. 1, pp. 219–226, Jan. 1997. vol. PWRD-1, no. 1, pp. 179–184, Jan. 1986.
[8] D. A. Woodford and L. M. Wedepohl, “Impact of circuit breaker [17] B. Kulicke and H. H. Schramm, “Clearance of short-circuits with de-
pre-strike on transmission line energization transients,” in Proc. IPST, layed current zeros in the Itaipu 500 kV substation,” IEEE Trans. Power
Seattle, WA, Jun. 22–26, 1997, pp. 250–253. App. Syst., vol. 99, no. 4, pp. 1406–1414, Jul./Aug. 1980.
[9] CIGRE WG 33.02, Guidelines for Representation of network elements [18] B. Khodabakhchian, J. Mahseredjian, M.-R. Sehati, and M. Mir-Hos-
when calculating transients, in CIGRE Brochure 39, 1990. seini, “Potential risk of failures in switching EHV shunt reactors in some
[10] Q. Bui-Van, B. Khodabakhchian, M. Landry, J. Mahseredjian, and J. one-and-a-half breaker scheme substations,” in Proc. IPST, New Or-
Mainville, “Performance of series-compensated line circuit breakers leans, LA, Sep. 28–Oct. 2, 2003.
under delayed current-zero,” IEEE Trans. Power Del., vol. 12, no. 1,
pp. 227–233, Jan. 1997.