Bts3900 GSM Commissioning Guide
Bts3900 GSM Commissioning Guide
BTS3900 GSM
V300R008
Commissioning Guide
Issue 03
Date 2008-07-15
Part Number
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 1/97
7/16/2019 BTS3900 GSM Commissioning Guide
Huawei Technologies Co., Ltd. provides customers with comprehensive technical support and service. For any
assistance, please contact our local office or company headquarters.
Website: http://www.huawei.com
Email: [email protected]
and other Huawei trademarks are the property of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective holders.
Notice
The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but the statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 2/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide Contents
Contents
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 3/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Contents Commissioning Guide
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 4/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide Figures
Figures
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 5/97
7/16/2019 BTS3900 GSM Commissioning Guide
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 6/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide Tables
Tables
Table 11-1
Terminal Possible
and causes and handling suggestions for failed communication between the Site Maintenance
the BTS.........................................................................................................................................11-2
Table 11-2 Meaning of the states of the LIU LED (UELP used)......................................................................11-4
Table 11-3 Meanings of the states of the LIU LED (UELP not used)...............................................................11-5
Table 11-4 Possible causes and handling suggestions for service dialing failure..............................................11-6
Table 11-5 Description of the DIP switch SW2 on the GTMU.........................................................................11-6
Table 12-1 BTS commissioning data sheet........................................................................................................12-1
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 7/97
7/16/2019 BTS3900 GSM Commissioning Guide
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 8/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide About This Document
Purpose
This document describes the procedures for commissioning and verifying the BTS3900 GSM
after it is installed. The commissioning and verification procedure ensures that the BTS3900
GSM operates as required. The procedures involve the following tasks: starting the Site
Maintenance Terminal System, running the BTS3900 GSM software, checking the transmission
and networking, commissioning the antenna system, checking the operating status of the
BTS3900 GSM, testing the services of the BTS3900 GSM, checking the BTS3900 GSM
environment, and typical FAQs for the commissioning.
Product Version
The following table lists the product version related to this document.
Intended Audience
This document is intended for:
l Field engineers
l Technical support engineers
Change History
For changes in the document, refer to Changes in BTS3900 GSM Commissioning Guide .
Organization
1 Safety Information
The general requirements for BTS3900 commissioning are the commissioning prerequisites and
commissioning resources.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 9/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
About This Document Commissioning Guide
Before starting the Site Maintenance Terminal, firstly, set the IP address of the Site Maintenance
Terminal PC; secondly, connect the Site Maintenance Terminal PC to the BTS; finally, log in
to the Site Maintenance Terminal.
This describes how to load the correct software version to the boards or modules in the BTS3900
cabinet and how to activate the board software.
The purpose of checking the transmission and networking is to ensure that the BTS3900
transmission cables and hardware are correctly installed. The items to be checked consist of the
transmission between the BBU and the DRFU, the transmission between the BBU and the BSC,
and the consistency between the actual networking and the data configuration.
This describes how to commission the antenna system. You must check whether the antenna is
connected properly and whether the Voltage Standing-Wave Ratio (VSWR) is normal. If an
RET antenna is configured, you must commission the RET antenna.
To ensure the normal operation of the BTS3900, you need to check the status of the BTS3900
LEDs, check the alarm information displayed on the Site Maintenance Terminal System, and
perform loopback tests on the boards.
9 Commissioning the BTS3900 Services
This describes how to test whether the BTS3900 supports CS services and PS services by using
an MS.
This describes the various environment alarms of the BTS3900. It also describes how to perform
environment monitoring for the BTS3900.
This describes the fault symptoms and cause analysis in the BTS commissioning.
The commissioning data sheet is used to record the process and result of the commissioning.
Conventions
1. Symbol Conventions
The following symbols may be found in this document. They are defined as follows
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 10/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide About This Document
Symbol Description
TIP Indicates a tip that may help you solve a problem or save your
time.
2. General Conventions
Convention Description
3. Command Conventions
Convention Description
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 11/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
About This Document Commissioning Guide
Convention Description
4. GUI Conventions
Convention Description
> Multi-level menus are in boldface and separated by the ">" signs.
For example,choose File > Create > Folder .
5. Keyboard Operation
Convention Description
Key1,Key2 Press the keys in turn.For example,pressing Alt,A means the two
keys should be pressed in turn.
6. Mouse Operation
Action Description
Click Select and release the primary mouse button without moving the
pointer.
Double-click Press the primary mouse button twice continuously and quickly
without moving the pointer.
Drag Press and hold the primary mouse button and move the pointer
to a certain position.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 12/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 1 Safety Information
1 Safety Information
The Danger, Caution, and Note items in the package of documents do not cover all the safety
precautions that must be followed. They only provide the generic safety precautions for
operations.
Symbols
DANGER
This symbol indicates that casualty or serious accident may occur if you ignore the safety
instruction.
CAUTION
This symbol indicates that serious or major injury may occur if you ignore the safety instruction.
NOTE
This symbol indicates that the operation may be easier if you pay attention to the safety instruction.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 13/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
1 Safety Information Commissioning Guide
The rules for installing and maintaining the device are as follows:
l Only the trained and qualified personnel can install, operate and maintain the device.
l Only the qualified specialists are allowed to remove the safety facilities, and repair the
device.
l Any replacement of the device or part of the device (including the software) or any change
made to the device must be performed by qualified or authorized personnel of Huawei.
l Any fault or error that might cause safety problems must be reported immediately to the
personnel in charge.
Grounding Requirements
The following requirements are applicable to the device to be grounded:
l Ground the device before installation and remove the ground cable after uninstallation.
l Do not operate the device in the absence of a ground conductor. Do not damage the ground
conductor.
l The unit (or system) must be permanently connected to the protection ground before
operation. Check the electrical connection of the device before operation and ensure that
the device is reliably grounded.
Safety of Personnel
Ensure the following:
The previous two requirements are suitable for the wireless fixed terminal.
l To prevent electric shock, do not connect safety extra-low voltage (SELV) circuits to
telecommunication network voltage (TNV) circuits.
l To prevent laser radiation from injuring your eyes, never look into the optical fiber outlet
with unaided eyes.
l To prevent electric shock and burns, wear the electrostatic discharge (ESD) clothing, gloves
and wrist strap, and remove conductors such as jewelry and watch before operation.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 14/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 1 Safety Information
Device Safety
l Before operation, the device must be secured on the floor or other fixed objects, such as
the walls and the mounting racks.
l Do not block ventilation openings while the system is running.
l When installing the panel, tighten the screw with the tool.
DANGER
l The high voltage power supply provides power for running the system. Direct contact with
the high voltage power supply or contact through damp objects may result in fatal danger.
l Non-standard and improper high voltage operations may result in fire and electric shock.
l The personnel who install the AC facility must be qualified to perform operations on high
voltage and AC power supply facilities.
l When installing the AC power supply facility, follow the local safety regulations.
l When operating the AC power supply facility, follow the local safety regulations.
l When operating the high voltage and AC power supply facilities, use the specific tools
instead of common tools.
l When the operation is performed in a damp environment, ensure that water is kept off the
device. If the cabinet is damp or wet, shut down the power supply immediately.
Thunderstorm
The following requirements are suitable only for the wireless base station or the device with an
antenna or GPS antenna.
DANGER
In a thunderstorm, do not perform operations on high voltage and AC power supply facilities or
on a steel tower and mast.
CAUTION
Ground the device before powering on the device. Otherwise, the personnel and device are in
danger.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 15/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
1 Safety Information Commissioning Guide
If the "high electrical leakage" flag is stuck to the power terminal of the device, you must ground
the device before powering it on.
Power Cable
CAUTION
Do not install and remove the power cable with a live line. Transient contact between the core
of the power cable and the conductor may generate electric arc or spark, which may cause fire
or eye injury.
l Before installing or removing the power cable, turn off the power switch.
l Before connecting the power cable, ensure that the power cable and label comply with the
requirements of the actual installation.
Fuse
CAUTION
To ensure that the system runs safely, when a fuse blows, replace it with a fuse of the same type
and specifications.
Electrostatic Discharge
CAUTION
The static electricity generated by the human body may damage the electrostatic sensitive
components on the circuit board, such as the large-scale integrated circuit (LIC).
In the following situations, the human body generates a static electromagnetic field:
The static electromagnetic field will remain within the human body for a long time.
Before contacting the device, plug boards, circuit boards, and application specific integrated
circuits (ASICs), wear a grounded ESD wrist strap. It can prevent the sensitive components from
being damaged by the static electricity in the human body.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 16/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 1 Safety Information
DANGER
Do not place the device in the environment that has inflammable and explosive air or fog. Do
not perform any operation in this environment.
Any operation of the electrical device in the inflammable environment causes danger.
1.4 Battery
Storage Battery
DANGER
Before handling the storage battery, read the safety precautions for the handling and connection
of the storage battery.
Incorrect operation of storage batteries may cause danger. During operation, ensure the
following:
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 17/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
1 Safety Information Commissioning Guide
Electrolyte overflow may damage the device. It will corrode the metal parts and the circuit
boards, and ultimately damage the device and cause short-circuit of the circuit boards.
General Operations
Before installing and maintaining the storage battery, ensure the following:
Short-Circuit
DANGER
Short-circuit of the battery may cause injury. Although the voltage of a battery is low, high
transient current generated by short-circuit will release a surge of power.
Keep metal objects away from the battery to prevent short circuit. If they have to be used,
disconnect the battery in use before performing any other operation.
Harmful Gas
CAUTION
l Do not use unsealed lead-acid storage batteries, because the gas emitted from it may result
in fire or device corrosion.
l Lay the storage battery horizontally and fix it properly.
The
goodlead-acid storage
ventilation battery
and take in use will
precautions emit flammable
against fire. gas. Therefore, store it in a place with
High Temperature
CAUTION
High temperature may result in distortion, damage, and electrolyte overflow of the battery.
o
When the occurs,
overflow temperature of the
handle the acid
battery exceeds 60 C, check whether there is acid overflow. If acid
immediately.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 18/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 1 Safety Information
Acid
CAUTION
If the acid overflows, it should be absorbed and neutralized immediately.
When handling a leaky battery, protect against the possible damage caused by the acid. Use the
following materials to absorb and neutralize acid spills:
Antacids must be used according to the instructions provided by the battery manufacturer.
Lithium Battery
CAUTION
l Replace the lithium battery with the same or equivalent type recommended by the
manufacturer.
l Dispose of the used battery according to the instructions provided by the manufacturer.
l Do not dispose of the lithium battery in fire.
1.5 Radiation
Electromagnetic Field Exposure
CAUTION
High power radio-frequency signals are harmful to human body.
Before installing or maintaining an antenna on a steel tower or mast with a large number of
transmitter antennas, the operator should coordinate with all parties to ensure that the transmitter
antennas are shut down.
The base transceiver station (BTS) has RF radiation (radiation hazard). Suggestions for the
installation and operation of BTSs are given in the following section. Operators are also required
to comply with the related local regulations on erecting BTSs.
l
The antenna
radiation should
exceeds thebestipulated
located invalue.
an area that is inaccessible to the public where the RF
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 19/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
1 Safety Information Commissioning Guide
l If the areas where RF radiation exceeds the stipulated value are accessible to workers,
ensure that workers know where these areas are. They can shut down the transmitters before
entering these areas. Such areas may not exist; but if they exist, the areas must be within a
range of less than 10 m around the antennas.
l Each forbidden zone should be indicated by a physical barrier and striking sign to warn the
public or workers.
Laser
CAUTION
When handling optical fibers, do not stand close to, or look into the optical fiber outlet with
unaided eyes.
Laser transceivers or transmitters are used in the optical transmission system and associated test
tools. Because the laser that is transmitted through the optical fiber produces a small beam of
light, it has a very high power density and is invisible to human eyes. If a beam of light enters
the eye, the retina may be damaged.
Normally, staring into the end of an unterminated optical fiber or broken optical fiber with the
unaided eyes from a distance of more than 150 mm [5.91 in.] will not cause eye injury. Eyes
may, however, be damaged if an optical tool such as a microscope, magnifying glass or eye
loupe is used to stare into the bare optical fiber end.
l
Only the trained and authorized personnel can perform the operation.
l Wear a pair of eye-protective glasses when you are handling lasers or optical fibers.
l Ensure that the optical source is switched off before disconnecting optical fiber connectors.
l Never look into the end of an exposed optical fiber or an open connector if you cannot
ensure that the optical source is switched off.
l To ensure that the optical source is switched off, use an optical power meter.
l Before opening the front door of an optical transmission system, ensure that you are not
exposed to laser radiation.
l Never use an optical tool such as a microscope, a magnifying glass, or an eye loupe to look
into the optical fiber connector or end.
l Only the trained personnel can cut and splice optical fibers.
l Before cutting or splicing an optical fiber, ensure that the optical fiber is disconnected from
the optical source. After disconnecting the optical fiber, use protecting caps to protect all
the optical connectors.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 20/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 1 Safety Information
CAUTION
When working at heights, ensure that the following requirements must be met:
Safety measures, such as wearing a helmet and a safety belt, should be taken.
l In cold regions, warm clothes should be worn before working at heights.
l Ensure that the lifting appliances are well prepared for working at heights.
Lifting Weights
CAUTION
Do not access the areas under the arm of the crane and the goods in suspension when lifting
weights.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 21/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
1 Safety Information Commissioning Guide
l Check the ladder before using it. Check the maximum weight that the ladder can support.
l Never overload the ladder.
l The slant angle is preferred to be 75 o. The slant can be measured with the angle square or
with arms, as shown in Figure 1-3. When using a ladder, place the wider end of the ladder
on the ground and take protective measures on the base of the ladder against slippage. Place
the ladder on a stable ground.
l The gravity of the body does not shift from the edge of the ladder.
l Keep balance on the ladder before performing any operation.
l Do not climb higher than the fourth highest step of the ladder.
If you tend to climb to the roof, the length of the ladder should be at least one meter higher than
the eave, as shown in Figure 1-4.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 22/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 1 Safety Information
CAUTION
Do not drill on the cabinet without permission. Inappropriate drilling on the cabinet may damage
the electromagnetic shielding and internal cables. Metal shavings from the drilling may result
in a short-circuit of the circuit board if they get into the cabinet.
l Before drilling a hole on the cabinet, remove the cables from the cabinet.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 23/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
1 Safety Information Commissioning Guide
CAUTION
When carrying the device by hand, wear the protective gloves to prevent injury by sharp objects.
Handling Fans
l When replacing a component, place the component, screw, and tool at a safe place to prevent
them from falling into the running fan.
l When replacing the ambient equipment around the fan, do not place the finger or board
into the running fan until the fan is switched off and stops running.
CAUTION
l Two persons should be available to move a chassis; one person must not move a heavy
chassis. When moving a chassis, keep your back straight and move stably to prevent a
sprain.
l When moving or lifting a chassis, hold the handle or bottom of the chassis. Do not hold the
handle of the installed modules in the chassis, such as the power module, fan module, or
board.
1.8 Others
Inserting and Removing a Board
CAUTION
When inserting a board, wear the ESD wrist strap or gloves. Insert the board gently to prevent
any bent pins on the backplane.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 24/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 1 Safety Information
CAUTION
Bundle the signal cables separately from the strong current cables or high voltage cables.
Cabling Requirements
At a very low temperature, movement of the cable may damage the plastic skin of the cable. To
ensure the construction safety, comply with the following requirements:
l When installing cables, ensure that the environment temperature is above 0oC.
l If cables are stored in the place below 0 oC, move the cables into a place at a room
temperature and store the cables for more than 24 hours before installation.
l Move the cables with care, especially at a low temperature. Do not drop the cables directly
from the vehicle.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 25/97
7/16/2019 BTS3900 GSM Commissioning Guide
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 26/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 2 General Requirements for BTS3900 Commissioning
The general requirements for BTS3900 commissioning are the commissioning prerequisites and
commissioning resources.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 27/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
2 General Requirements for BTS3900 Commissioning Commissioning Guide
Hardware Requirements
l The BTS3900 cabinet is installed and the cables are connected.
l The BTS3900 has passed the hardware installation check before it is powered on.
l The BTS3900 is powered on. For details, refer to Checking the Power-On Status of the
BTS3900 Cabinet and Checking the Power-On Status of the BTS3900 Components .
l The BSC is installed. The system commissioning is complete, and the system is running
normally.
Software Requirements
l The data of the BTS3900 is configured on the BSC side.
Tool
Table 2-1 lists the tools and instruments required for the commissioning.
Power meter One Mandatory. The power meter is used to measure the
output power of the TRX.
Site master One Mandatory. The site master is used to measure the
voltage standing wave ratio (VSWR).
Drive tester (such as TEMS One Optional. The drive tester is used to measure whether
or ANT) the antenna system is properly connected.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 28/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 2 General Requirements for BTS3900 Commissioning
GSM mobile station for test Two Mandatory. The mobile station is used to perform the
dialing test and to check whether the antenna system
is properly connected.
Serial port cable One Mandatory. The serial port cable is used when you
query as
listed thefollows:
board IP address. The auxiliary cables are
General light emitting diode Two Optional. The general LED is used to determine the
(LED) RX or TX end of the E1/T1 cable.
Site Information
Before the commissioning, you must obtain the following information on the BTS3900:
l Information on BTS networking and related configuration, including BTS type,
transmission mode, networking mode, and cell configuration
l BTS3900 data configured at the BSC
l DRFU software
l GTMU software
l GATM software
l PMU software
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 29/97
7/16/2019 BTS3900 GSM Commissioning Guide
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 30/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 3 BTS3900 Commissioning Procedure
Context
You can troubleshoot the problems that occur during the commissioning by referring to 11 FAQs
for BTS Commissioning.
Procedure
Step 1 Starting the Site Maintenance Terminal System
1. Set the IP Address of the Site Maintenance Terminal PC by referring to 4.1 Setting the IP
Address of the Site Maintenance Terminal PC.
2. Connect the Site Maintenance Terminal PC to the BTS by r eferring to 4.2 Connecting the
Site Maintenance Terminal PC to the BTS .
3. Log in to the BTS by referring to 4.3 Locally Logging In to the BTS.
If... Then...
The current software version is inconsistent Perform the operations described in Forcibly
with the expected software version, Loading Software and in Activating Board
Software
1. Check whetherthe
6.1 Checking theTransmission
transmission between
Betweenthe BBU
the and
BBU thethe
and DRFU is normal
DRFU . by referring to
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 31/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
3 BTS3900 Commissioning Procedure Commissioning Guide
2. Check whether the transmission between the BBU and the BSC is normal by referring to
6.2 Checking the Transmission Between the BBU and the BSC.
3. Check the consistency between hardware installation and data configuration by referring
to 6.3 Checking the Consistency Between Actual Networking and Data
Configuration.
Step 4 Commission the antenna system.
1. Measure the VSWR at the antenna port by referring to 7.1 Measuring the VSWR at the
Antenna Port.
2. Check the antenna connection by referring to 7.2 Checking the Antenna Connection.
3. Measure the output power of the TRX by referring to 7.3 Measuring the Output Power
of the TRX.
CAUTION
After the commissioning, you should release the site management rights on the Site Maintenance
Terminal System by referring to Releasing the Site Management Rights.
----End
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 32/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 4 Starting the Site Maintenance Terminal System
Before starting the Site Maintenance Terminal, firstly, set the IP address of the Site Maintenance
Terminal PC; secondly, connect the Site Maintenance Terminal PC to the BTS; finally, log in
to the Site Maintenance Terminal.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 33/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
4 Starting the Site Maintenance Terminal System Commissioning Guide
Prerequisite
The Site Maintenance Terminal PC is configured with the TCP/IP protocol.
Procedure
Step 1 Take the Windows XP operating system as an example. On the Windows XP operating system,
choose Start > Control Panel.
Step 2 Select Network Connections. A dialog box is displayed. Right-click the Local Area
Connection icon.
Step 3 Choose Properties on the shortcut menu,. The Local Area Connection Properties dialog box
is displayed.
Step 5 Click Properties . The Internet Protocol (TCP/IP) Properties dialog box is displayed.
Step 7 Enter the correct IP address, subnet mask, and default gateway. Ensure that the IP address of the
Site Maintenance Terminal PC and the IP address (192.168.0.72/255.255.255.0) of the BTS are
located in the same network segment, so that a local maintenance path can be set up.
----End
Prerequisite
The IP address and the subnet mask of the Site Maintenance Terminal PC are set. The IP address
of the Site Maintenance Terminal PC and the IP address (192.168.0.72/255.255.255.0) of the
BTS are on the same network segment.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 34/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 4 Starting the Site Maintenance Terminal System
Procedure
Step 1 Use the crossover cable to connect the Site Maintenance Terminal PC to the BTS. Connect one
end of the cable to the ETH port on the main control module of the main cabinet, and connect
the other end of the cable to the Ethernet cable port on the Site Maintenance Terminal PC.
Step 3 Run the ping target_name command to verify the network connection between the PC and the
BTS.
NOTE
If the information similar to that in the following example is returned, the LMT PC and the
GBAM can communicate normally. In this example, the IP address of the external network is
192.168.0.72.
Pinging 192.168.0.72 with 32 bytes of data: Pinging 192.168.0.72 with 32 bytes of
data: Reply from 192.168.0.72: bytes=32 time=1ms TTL=253 Reply from 192.168.0.72:
bytes=32 time=1ms TTL=253 Reply from 192.168.0.72: bytes=32 time=1ms TTL=253 Reply
from 192.168.0.72: bytes=32 time=1ms TTL=253 Ping statistics for 192.168.0.72:
Packets: Sent = 4, Received = 4, Lost = 0 (0% loss), Approximate round trip times
in milli-seconds: Minimum = 1ms, Maximum = 1ms, Average = 1ms
----End
Prerequisite
l The Site Maintenance Terminal PC is connected properly to the BTS.
l The Site Maintenance Terminal PC is installed with the latest site maintenance terminal
software.
Procedure
Step 1 Double-click btsm.exe to start the Site Maintenance Terminal System.
l If the communication between the Site Maintenance Terminal PC and the BTS is not set
up, the Communication failed dialog box is displayed, as shown in Figure 4-1. Go to
Step 2.
l If the communication between the Site Maintenance Terminal PC and the BTS is set up, a
window is displayed, as shown in Figure 4-2. The Local Maintenance Terminal is
successfully started.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 35/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
4 Starting the Site Maintenance Terminal System Commissioning Guide
Step 2 Click Yes.
The Set Communication Port Parameter dialog box is displayed, as shown in Figure 4-3.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 36/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 4 Starting the Site Maintenance Terminal System
Step 3 In the Select Communication Port area, click Network Port. In the Configure IP area, set the
IP address to 192.168.0.72.
Step 4 Click OK .
The Site Maintenance Terminal System window is displayed, as shown in Figure 4-2.
----End
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 37/97
7/16/2019 BTS3900 GSM Commissioning Guide
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 38/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 5 Running the BTS3900 Software
Context
To run the BTS3900 software, you must obtain the site management rights and check the current
board software version. If the board software version is improper, you must load the proper
software version and then activate it.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 39/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
5 Running the BTS3900 Software Commissioning Guide
Prerequisite
You have logged in to the BTS through the Site Maintenance Terminal.
Procedure
Step 1 In the left pane of the Site Maintenance Terminal System window, click Site. In the right pane
of the window, double-click Site Management Right.
The Site Management Right dialog box is displayed.
Step 2 Click Get. The result is displayed in the dialog box, as shown in Figure 5-1.
----End
Procedure
Step 1 In the left pane of the Site Maintenance Terminal System window, select Board. In the right
pane of the window, double-click Board Management.
The Board Management window is displayed, as shown in Figure 5-2.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 40/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 5 Running the BTS3900 Software
If... Then...
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 41/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
5 Running the BTS3900 Software Commissioning Guide
Step 4 Right-click the board, and then select Board Information from the shortcut menu.
The result is displayed in the Board Information dialog box, as shown in Figure 5-4 (the GTMU
is taken as an example).
----End
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 42/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 5 Running the BTS3900 Software
Prerequisite
You have logged in to the BTS through the Site Maintenance Terminal.
Context
l The main control board of the base station is the GTMU.
l You need to load the software of the main control board prior to loading the software of
other boards. There are no strict requirements for the sequence of loading the software of
other boards.
Table 5-1 describes the parameters.
File Name File name of the software to be downloaded, Use the actual file
that is, the path in which the software is saved name. Note that the file
name is case sensitive.
Send Window Size of the data packet when the software is 1–49 (49 is
Size loaded recommended)
Procedure
Step 1 In the left pane of the Site Maintenance Terminal System window, click Site. In the right pane
of the window, double-click Forced Software Load.
The Software Download dialog box is displayed.
Step 2 Set File Name. In the Send Window Size spin box, specify a size. In the Version area, enter a
version number. In the File ID drop-down list box, select DTMU_MAIN , as shown in Figure
5-5.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 43/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
5 Running the BTS3900 Software Commissioning Guide
Step 3 Click Start.
You can view the loading progress in the Site Maintenance Terminal System. If the software is
loaded successfully, the Loading software successfully message is displayed on the status bar.
----End
Prerequisite
l You have logged in to the BTS through the Site Maintenance Terminal.
l The board software to be activated is loaded.
Context
l The main control board of the BTS is the GTMU.
l You need to activate the main control board software before activating the software of the
other boards. There are no specified sequence for activating the software of the other boards.
l The loading of software does not affect the services. The activation of software validates
the new version software on boards and affects the services. Therefore, Huawei
recommends you load the software in the day and activate it at night.
Table 5-2 lists the descriptions of the parameters.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 44/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 5 Running the BTS3900 Software
0-5.
If you do not enter a
board number, all the
boards of this type in
the BTS will be
activated.
Procedure
Step 1 In the left pane of the Site Maintenance Terminal System window, choose Site. In the right
pane of the window, double-click Software Activation.
The Software Activation dialog box is displayed.
Step 2 In the Version area, enter the version number of the main control board software. In the File
ID drop-down list, select the file ID, as shown in Figure 5-6.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 45/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
5 Running the BTS3900 Software Commissioning Guide
Step 3 Click OK .
The number of the board that is successfully activated is displayed in the The board list
activated successfully: area. The Software activation successfully message is displayed on
the status bar at the bottom of the dialog box.
Step 4 After that, activate the software of the other boards. In the Version area, enter the version number
of the software to be activated. In the Board No. area, enter the number of the board to be
activated.
Figure 5-7In
. the File ID drop-down list, select the board software to be activated, as shown in
Step 5 Click OK .
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 46/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 5 Running the BTS3900 Software
The number of the board that is successfully activated is displayed in the The board list
activated successfully: area. The Software activation successfully message is displayed on
the status bar at the bottom of the dialog box.
NOTE
During the activation of the DRFU board software, if the Site Maintenance Terminal prompts that the software
activation failed, check the communication between the BBU and the DRFU. If there is a communication
problem between the BBU and the DRFU, rectify the fault by referring to 6.1 Checking the Transmission
Between the BBU and the DRFU.
----End
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 47/97
7/16/2019 BTS3900 GSM Commissioning Guide
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 48/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 6 Checking the Transmission and Networking
6.1 Checking the Transmission Between the BBU and the DRFU
By checking the link status, you can rectify the fault caused by abnormal connection, thus
ensuring normal communication between the BBU and the DRFU.
6.2 Checking the Transmission Between the BBU and the BSC
This describes how to check the status of the LEDs on the GTMU panel, how to check the
connection of the E1 cable and E1 surge protection transfer cable, and how to rectify the fault
caused by improper connections.
6.3 Checking the Consistency Between Actual Networking and Data Configuration
The items to be checked consist of the BTS3900 network topologies, the configurations of the
boards and modules, RF cable connections of the DRFUs, and the data configuration of the RF
signal RX/TX mode.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 49/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
6 Checking the Transmission and Networking Commissioning Guide
Procedure
Step 1 Check the status of the CPRI0 LED on the GTMU panel and the status of the CPRI0 and
CPRI1 LEDs on the DRFU panel.
If... Then...
All the LEDs are in normal states (the The communication between the CPRI0 port on
green LEDs are on), the BBU and the DRFU is normal. Go to Step 4.
Some LEDs are not in normal states. The communication between the CPRI0 port on
The normal state is green LED on, the BBU and the DRFU is not normal. Go to Step
2.
NOTE
The status of the LED corresponding to the CPRI port that is not in use should be Off .
Step 3 Check the connection between the DRFU and the BBU.
1. Check that one end of the CPRI signal cable is securely connected to the CPRI0 port on
the DRFU, and the other end is securely connected to the CPRI port on the BBU.
2. Check the SFP male connectors at both ends of the CPRI signal cable. If any connector is
damaged, replace it.
Step 4 Repeat Step 1 through Step 3 to check the transmission between other CPRI ports on the GTMU
panel and other DRFUs.
----End
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 50/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 6 Checking the Transmission and Networking
Prerequisite
l The BBU is connected to the BSC through an E1/T1 cable.
l The BBU and the BSC are powered on.
Procedure
Step 1 Check the settings of the DIP switches on the GTMU. Ensure that the settings of DIP switches
are consistent with the on-site requirements.
Step 2 Check the operating status of the LIU0-LIU3 LEDs on the GTMU panel.
If... Then...
All the LEDs are Off, The communication between the BBU and the BSC
is normal. The checking is complete.
Some LEDs are ON or blink at 4 Hz, The corresponding E1/T1 links are not normal. Go to
Step 3.
NOTE
You need to check the status of only the LIU LED corresponding to the E1/T1 cable in use. The state of the
LIU LED corresponding to the unused E1/T1 cable is Off .
Step 3 Check the connection and connectors at both ends of the cable. If any connector is damaged or
does not work properly, replace it with a new connector.
If... Then...
The UELP is configured, l Check the connection between the E1/T1 cable and the
OUTSIDE port on the UELP.
l Check the connection between the E1 surge protection
transfer cable and the INSIDE port on the UELP.
l Check the connection between the E1 surge protection
transfer cable and the E1/T1 port on the GTMU.
The UELP is not configured, Check the connection between the E1/T1 cable and the E1/
T1 port on the GTMU.
Step 4 At the DDF on the BTS side, check the soldering conditions of the connectors for the E1/T1
cable where communication is not normal. Ensure that the E1/T1 connectors are in good
soldering conditions.
Step 5 Perform a physical loopback test of the E1/T1 line where the communication is not normal. On
the BTS side, check whether the communication of the E1/T1 line is normal.
1. On the BTS side, disconnect A from C, disconnect B from D, and then connect A to B on
the DDF, as shown in Figure 6-1. Thus, a physical loopback on the BTS side is formed.
The normal
between E1/T1
A and connection
C and between
connection theBBTS
between andand
D. the BSC consists of the connection
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 51/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
6 Checking the Transmission and Networking Commissioning Guide
A C
E1/T1 E1/T1
E1/T1 E1/T1
B D
BTS DDF BSC
2. Check the status of the LIU LED on the GTMU panel again.
If... Then...
The LED is OFF, The E1 link on the BTS side is normal. The
connection between the BTS and the BSC
is abnormal or the E1 link on the BSC side
is abnormal. End the testing task. Contact
Huawei BSC technical support engineers
to rectify the fault.
The LED is ON or blinks at 4 Hz, The E1 link on the BTS side is abnormal.
Rectify the fault on the BTS side.
3. Restore the normal E1/T1 connection at the DDF on the BTS side and ensure that the
connection is proper.
Step 6 Check the E1/T1 connection at the DDF. Ensure that the TX and RX ends of the E1/T1 cables
are connected properly.
NOTE
You can determine the TX or RX end of the E1 cable in the following manner:
Connect one pin of a common LED to the E1/T1 wire, and connect the other pin of the LED to the shielding
layer of the E1/T1 cable. If the LED is ON, the port is a TX port. If the LED is OFF, the port is an RX port.
----End
Prerequisite
l The Site Maintenance Terminal System is started.
l The board software is loaded and activated.
l
The transmission
and the between the BBU and the DRFU and the transmission between the BBU
BSC are normal.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 52/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 6 Checking the Transmission and Networking
Background Introduction
l The BTS supports the star, chain, tree, and ring topologies. The network topology between
the BBU and the DRFUs may be star, chain, or ring topology.
l In the data configuration, SFP numbers SFP0 – SFP5 in the Topology Management
window of the Site Maintenance Terminal System correspond to the CPRI0 – CPRI5 ports
on the BBU panel.
Procedure
Step 1 Check that the network topology of the DRFUs is consistent with the settings of the SFP numbers
and level numbers shown in the Topology Management window of the Site Maintenance
Terminal System. For details on network topologies, refer to Topology of DRFUs Connected
by CPRI Cables.
Step 2 Check that the boards and modules installed in the BTS3900 cabinet correspond to the boards
and modules configured in the Board Management window. As shown in Figure 6-2, the
Board Management window shows the slots for boards and modules in full configuration.
Table 6-1 lists the mapping between the names of the boards or modules shown in the window
and the actual names of the boards or modules.
Figure 6-2 Slots for boards or modules in the Board Management window
NOTE
l The PMU can be configured in any one of slots 2-5 in the CommonBox subrack.
l The FMU can be configured in any one of slots 8-15 in the CommonBox subrack.
l
The GTMU is fixedly configured in slot 6 and occupies slots 5 and 6 on the front panel. Therefore, the
GTMU is configured in slots 5 and 6 in the Board Management window.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 53/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
6 Checking the Transmission and Networking Commissioning Guide
Table 6-1 Mapping between the board/module name shown in the window and the actual board/
module name
PMU PMU
FMU FAN
GATM GATM
GTMU GTMU
BFU UBFA
EIU UEIU
PEU UPEU
Step 3 Check whether the RF cable connections of the DRFUs are consistent with the data configuration
of the RF signal RX/TX mode. For details on the RF cable connections of the DRFUs, refer to
RF Signal Cable Connections of the DRFU .
Step 4 Record the inconsistencies between data configuration and hardware installation in 12 Data
Sheet for Commissioning. Then, check whether the data configuration or the hardware
installation is incorrect by confirming it with Huawei BSC technical support engineers and BTS
technical support engineers.
If... Then...
The data configuration is incorrect, Modify the data configuration. For details, refer to
the BSC Initial Configuration Guide.
The hardware installation is incorrect, Reinstall the hardware. For details, refer to the
related hardware installation guide.
----End
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 54/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 6 Checking the Transmission and Networking
Figure 6-3 Star topology between the DRFUs and the BBU
Antenna
UELP
INSIDE OUTSIDE
Figure 6-4 shows the settings of the SFP numbers and level numbers in the Topology
Management window.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 55/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
6 Checking the Transmission and Networking Commissioning Guide
NOTE
In hardware installation, one CPRI port can support a maximum of three layers of cascading DRFUs.
Figure 6-4 As shown in Figure 6-4, each SFP number can be configured with a maximum of three
DRFUs in chain topology.
2. Check that the configurations of the boards or modules of the BBU in the Board
Management window shown in Figure 6-5 are correct.
3. Figure 6-3 shows the RF cable connections of S4. The receive mode is MAIN Diversity,
and the transmit mode is Independent/Combined Transmit. Check the RF RX/TX mode
displayed in the Parameter Management dialog box related to path A or path B of the
DRFUs, as shown in Figure 6-6.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 56/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 6 Checking the Transmission and Networking
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 57/97
7/16/2019 BTS3900 GSM Commissioning Guide
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 58/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 7 Commission the Antenna System
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 59/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
7 Commission the Antenna System Commissioning Guide
Prerequisite
The BTS is powered off.
NOTE
If you have checked the VSWR before powering on the BTS, you do not need to perform this task.
Procedure
Step 1 Measure the VSWR at the antenna port by using the Site Master.
If... Then...
The VSWR is less than or equal to 1.5, You can infer that the transmission of the antenna
system is normal. Record the measured value in the
Data Sheet for Commissioning.
The VSWR is greater than 1.5, You can infer that the transmission of the antenna
system is not normal. Go to Step 2.
Step 2 Locate the fault on the jumper or feeder where the VSWR is not normal by using the Site Master.
Check whether the jumper or feeder is securely connected and whether the connectors are in
good condition. If any connector is damaged, replace it.
NOTE
The fault often occurs on the connectors between the jumper and the feeder or the connectors between the
jumper and the antenna.
----End
This describes
the antenna how to check
connection the antenna
conditions connections
by checking by the
whether using a drive tester.
frequencies of theYou can determine
BCCH and BSIC
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 60/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 7 Commission the Antenna System
in the configuration data are consistent with the actual frequencies and whether the test level is
normal.
Prerequisite
l The BTS is powered on and is working normally.
l The antenna system is connected to the BTS cabinet.
l The test MS is registered with the HLR.
Procedure
Step 1 Power on the test MS and check the process of the MS in searching the GSM network.
If... Then...
The test MS fails to find the network, l Check whether the test MS has a SIM card. If the
test MS does not have a SIM card, insert the SIM
card in the MS.
l Check whether the SIM card supports
authentication and encryption. If the SIM card
does not support authentication and encryption,
replace the SIM card.
l Check whether the test MS is functional. If the test
MS is faulty, replace it.
Step 2 Lock the test MS to a frequency of a logical cell covered by the BTS.
Step 3 Perform the dialing test using the test MS. Then, check whether the antenna corresponding to
the frequency is connected properly according to the test results.
If... Then...
The dialing test succeeds, You can infer that the feeder corresponding to the frequency is
connected properly. Go to Step 4.
The dialing test fails, You can infer that the feeder corresponding to the frequency may
be connected improperly. Check the connections of the feeder and
make adjustment accordingly..
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 61/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
7 Commission the Antenna System Commissioning Guide
NOTE
l
Perform the dialing test for more than five times.
Step 4 Repeat Step 2 through Step 3 to check the antennas on all the frequencies of the BTS are
connected properly.
----End
Prerequisite
A drive tester and a test MS are available.
Procedure
Step 1 Record the longitude and latitude of the BTS in the drive test map.
Step 2 Start the drive test in the direction of the main lobe of the antenna in the target cell.
Step 3 Record the actual frequencies of the BCCH and BSIC in the cell. Compare the records with those
in configuration data of the BTS to ensure consistency.
Step 4 Check whether the test level is normal. The normal test level ranges from –48 dBm to –96 dBm.
CAUTION
After the drive test is complete, back up the BTS data configuration file.
----End
Procedure
Step 1 Measure the output power of the TRX on the ANT port of the DRFU by using a power meter.
Step 2 Check whether the output power of the TRX is within the normal range.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 62/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 7 Commission the Antenna System
NOTE
For example, in 900 MHz no combination mode, if the normal power is set to 45 W (46.5 dBm), the normal
range of the output power on the ANT port of the DRFU is 46.5 ± 1 dBm.
If... Then...
The output power is within the normal Record the value of the power in the Data Sheet
range, for Commissioning.
The output power is beyond the normal 1. Check whether the cable of the power meter is
range, connected securely.
2. Check whether the parameters of the power
meter are correctly set and whether the power
meter is calibrated.
3. Check whether the DRFU is correctly
configured and can transmit power.
4. Replace the DRFU in which the TRX does not
transmit power normally.
Step 3 Repeat Step 1 through Step 2 to check the output power of all the TRXs.
----End
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 63/97
7/16/2019 BTS3900 GSM Commissioning Guide
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 64/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 8 Checking the Operating Status of the BTS3900
To ensure the normal operation of the BTS3900, you need to check the status of the BTS3900
LEDs, check the alarm information displayed on the Site Maintenance Terminal System, and
perform loop back tests on the boards.
Prerequisite
l The transmission between the BBU and the DRFU and the transmission between the BBU
and the BSC are normal.
l The actual networking is consistent with the data configuration.
l The antenna system is commissioned, and each parameter is configured in accordance with
the actual requirements.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 65/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
8 Checking the Operating Status of the BTS3900 Commissioning Guide
Prerequisite
The output power of the TRXs is within the normal range, and the DRFU is running normally.
Context
l The PSU (AC/DC) is used to convert 220 V AC power into -48 V DC power. If the BTS3900
uses the external 220 V AC power input, the PSU (AC/DC) is configured.
l The PSU (DC/DC) is used to convert +24 V DC power into -48 V DC power. If the BTS3900
uses the external +24 V DC power input, the PSU (DC/DC) is configured.
Procedure
Step 1 Check whether the states of the LEDs on the boards and modules in the BBU are normal. Table
8-1 lists the normal states of the LEDs on the boards and modules.
Table 8-1 Normal states of the LEDs on the boards and modules in the BBU
ACT Green ON
CPRI0-CPRI5 Green ON
UBFA STATE Green Blinking (on for 1s and off for 1s)
Step 2 Check whether the status of the LEDs on the DRFU panel is normal. Table 8-2 lists the normal
states of the LEDs.
ALM - Off
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 66/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 8 Checking the Operating Status of the BTS3900
CPRI0 Green ON
CPRI1 Green ON
Step 3 Check whether the states of the LEDs on the GATM panel are normal. Table 8-3 lists the normal
states of the LEDs.
Step 4 Check whether the states of the LEDs on the Fan Unit panel are normal. Table 8-4 lists the
normal states of the LEDs.
Step 5 Check whether the states of the LEDs on the PMU panel are normal. Table 8-5 lists the normal
states of the LEDs.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 67/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
8 Checking the Operating Status of the BTS3900 Commissioning Guide
Step 6 Check whether the states of the LEDs on the PSU (AC/DC) or PSU (DC/DC) panel are normal.
Table 8-6 lists the normal states of the LEDs.
Step 7 Refer to 8.2 Checking the Alarm Information of the BTS3900 if the states of the LEDs on
the boards or modules are not normal. Then, check the alarm information on the Site Maintenance
Terminal System, and rectify the fault according to the suggestions displayed.
----End
Procedure
Step 1 Select Board in the left pane of the Site Maintenance Terminal System window, and then
double-click Board Management in the right pane of the window.
The Board Management window is displayed, as shown in Figure 8-1.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 68/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 8 Checking the Operating Status of the BTS3900
Step 2 Confirm the type of the board or module where the alarm information needs to be checked.
If... Then...
The board or module is DRFU, Go to Step 3, and check the alarm information.
The board or module is GTMU, UBFA, Go to Step 4, and check the alarm information.
UPEU, UEIU, GATM, or PMU,
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 69/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
8 Checking the Operating Status of the BTS3900 Commissioning Guide
Step 4 Right-click the target board or module, and then choose Board Alarm Information from the
shortcut menu.
The Board Alarm Information dialog box is displayed.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 70/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 8 Checking the Operating Status of the BTS3900
NOTE
Step 6 Perform operations according to the result displayed in the Board Alarm Information dialog
box.
If... Then...
No alarm is generated, Close the Board Alarm Information dialog box. Then, repeat Step
2 through Step 6 to check the alarm information of other boards or
modules.
----End
Context
Only the GTMU and DRFU support the loopback test. Table 8-7 describes the parameters shown
in the Loopback Test dialog box.
Table 8-7 Description of the parameters shown in the Loopback Test dialog box
Data length Length of the valid data of a single frame in the loopback 1-220
test command sent from the GTMU or DRFU to the
board.
Initial data Initial value of the valid data in the loopback test 0-255
Procedure
Step 1 Select Board in the left pane of the Site Maintenance Terminal System window, and then
double-click Board Management in the right pane of the window.
The Board Management window is displayed, as shown in Figure 8-4.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 71/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
8 Checking the Operating Status of the BTS3900 Commissioning Guide
Step 4 Click Start.
After the test is complete, the result is displayed on the status bar at the bottom of the dialog
box.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 72/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 8 Checking the Operating Status of the BTS3900
Step 9 Click Start.
After the test is complete, the result is displayed on the status bar at the bottom of the dialog
box.
Step 10 Repeat Step 5 through Step 9 to perform the loopback test of all the DRFUs.
----End
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 73/97
7/16/2019 BTS3900 GSM Commissioning Guide
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 74/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 9 Commissioning the BTS3900 Services
Prerequisite
The BTS3900 is running normally.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 75/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
9 Commissioning the BTS3900 Services Commissioning Guide
Background Introduction
l The BIU loopback test is performed to test the link transmission of the TRX timeslots on
the DBUS.
l The TRX self-test is performed to check whether the logical channel from the BBU to the
DSP in the RRU/DRFU is functional.
Procedure
Step 1 In the left pane of the Site Maintenance Terminal System window, select BT. In the right pane
of the window, double-click BT Loop Test.
The BT Loop Test dialog box is displayed, as shown in Figure 9-1.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 76/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 9 Commissioning the BTS3900 Services
The test time is related to the test option. Generally, a long-duration test produces a stable test result.
Step 3 Click Start.
The test result is displayed on the status bar at the bottom of the BT Loop Test dialog box.
NOTE
During the test, you can click Stop to stop the test. In this case, the Stopping test successfully. message
is displayed on the status bar at the bottom of the BT Loop Test dialog box.
Step 4 Repeat Step 1 through Step 3 to perform the baseband test on other BTs on site.
----End
Background Introduction
l The BIU loopback test is performed to test the timeslot transmission of the TRX traffic
channel on the BTS DBUS.
l The TRX RF self-loop test is performed to test the quality of the RX and TX channels.
Procedure
Step 1 In the left pane of the Site Maintenance Terminal System window, select Channel . In the right
pane of the window, double-click Channel Loop Test.
The Channel Loop Test dialog box is displayed, as shown in Figure 9-2.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 77/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
9 Commissioning the BTS3900 Services Commissioning Guide
Step 2 Specify the test option, test time, and power level.
NOTE
l The test time is related to the test option. Generally, the longer the duration of the test, the more stable
the test result.
l The value range of the power level is from 0 to 31. The power level is unavailable when you select the
BIU loopback test.
Step 3 Click Start.
The result is displayed on the status bar at the bottom of the Channel Loop Test dialog box.
NOTE
During the test, you can click Stop to stop the test. In addition, the Stopping test successfully. message
is displayed on the status bar of the Channel Loop Test dialog box.
Step 4 Repeat Step 1 through Step 3 to perform the baseband test on other Channels on site.
----End
Prerequisite
l Two test MSs, which support GSM and are registered with the HLR, are available.
l The logical cell to be tested is activated.
l The BSC is in normal operation.
l The signaling channel loopback test and traffic channel loopback test are conducted. The
test results are normal.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 78/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 9 Commissioning the BTS3900 Services
Procedure
Step 1 Power on the test MS and check the process of the MS in searching the GSM network.
If... Then...
The test MS fails to find the network, Check whether the test MS is faulty. For example,
the test MS does not have a SIM card, or the SIM
card does not support authentication and encryption.
After rectifying the faults, use the test MS to search
the network again.
Step 2 Lock the test MS to a frequency of a logical cell covered by the BTS.
Step 3 Make test calls.
1. Use one MS to call the other MS, and hold the call for a while.
2. Use one MS to originate a call to a PSTN user, and hold the call for a while.
3. Use a PSTN phone to originate a call to one MS, and hold the call for a while.
NOTE
To ensure the accuracy of test results, make each type of test call more than five times.
Step 4 Verify that all test calls are successful and the voice is clear.
If... Then...
Mobile-originated call fails, 1. Check the LED status of the BTS and the
alarm information, locate the faults occurring
on the BTS side, and rectify the faults.
2. Request BSC technical engineers to rectify
the BSC faults.
Mobile-originated call succeeds, and You can infer that the data configuration of the
mobile-terminated call fails, BSC is improper. Request BSC technical
engineers to rectify the fault.
Step 5 Repeat Step 2 through Step 4 to test CS services in the other logical cells covered by the BTS.
----End
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 79/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
9 Commissioning the BTS3900 Services Commissioning Guide
Prerequisite
l One test MS, which supports GSM and is registered with the HLR, is available. This MS
is GPRS-capable.
l The BTS is configured with the GPRS or EGPRS services.
l The logical cell to be tested is activated.
l The computer and BSC are operating normally.
l The signaling channel loopback test and traffic channel loopback test are conducted. The
test results are normal.
Procedure
Step 1 Connect the MS to the USB port of the computer using a USB cable.
Step 2 Activate the GPRS or EGPRS data services using the MS. Then, test PS services through multi-
service testing, such as multimedia message sending, website browsing, and file downloading.
Step 3 Check whether the multimedia message sending, website browsing, and file downloading are
successful.
If... Then...
The testing of one type of PS services is You can infer that the BTS hardware meets the
successful, requirements of PS services.
The testing of three types of PS services Check whether the test MS is faulty. For
fails, example, the test MS does not have a SIM card,
or the SIM card does not support authentication
and encryption.
Step 4 Repeat Step 1 through Step 3 to commission PS services in all the other logical cells covered
by the BTS.
----End
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 80/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 10 Checking the BTS3900 Environment
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 81/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
10 Checking the BTS3900 Environment Commissioning Guide
NOTE
l Critical alarm: devices or resources may be unusable, and restoration should be performed at once.
l Major alarm: The QoS of devices or resources severely deteriorates, and measures should be taken as
soon as possible.
l The thresholds of temperature alarm and humidity alarm are subject to the local climate and terrain
conditions and should be specified on the basis of the field requirements.
Fire Alarm
The fire alarm is the environment alarm generated when the equipment room is on fire. This is
a critical alarm.
Smoke Alarm
The smoke alarm is an environment alarm generated when the smoke density in the equipment
room reaches a predefined threshold. This is a critical alarm.
Infrared Alarm
The infrared alarm is an environment alarm generated when an infrared facility is taken into the
equipment room or is in the infrared detection range of the cabinet. This is a major alarm.
Water Alarm
The water alarm is an environment alarm generated when water immersion occurs in the
equipment room.
Temperature Alarm
The temperature alarm consists of the overtemperature alarm and the undertemperature alarm.
This is a major alarm.
l The overtemperature alarm is generated when the ambient temperature is higher than the
predefined upper threshold of the temperature.
l The undertemperature alarm is generated when the ambient temperature is lower than the
predefined lower threshold of the temperature.
Humidity Alarm
The humidity alarm consists of the high humidity alarm and the low humidity alarm. This is a
major alarm.
l
The high humidity
predefined alarm is of
upper threshold generated when the environment humidity is higher than the
the humidity.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 82/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 10 Checking the BTS3900 Environment
l The low humidity alarm is generated when the environment humidity is lower than the
predefined lower threshold of the humidity.
Air-Conditioner Alarm
The air-conditioner alarm is generated when the air-conditioner is not running properly or the
AC power supply is not normal. This is a major alarm.
Burglar Alarm
The burglar alarm is generated when the infrared alarm or door status alarm occurs. This is a
critical alarm.
Prerequisite
You have logged in to the BTS through the Site Maintenance Terminal.
Context
Table 10-1 describes the parameters.
Clear Robbery Clearing the infrared alarm and the door status alarm -
Alarm
Set Temperature Set the upper and lower thresholds of temperature and -
and Humidity humidity. Based on the thresholds, the alarm box reports
Threshold a temperature alarm and a humidity alarm.
Relay Operation Control the relay status. The relay is used to start or close -
the refrigeration device, heating device, dehumidifier,
humidifier, fire extinguisher, and anti-burglar device.
The default state is Close.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 83/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
10 Checking the BTS3900 Environment Commissioning Guide
Disable the EAC Disable the reporting of alarms in a short time. In the -
Alarm maintenance of equipment, the related personnel can
select the option to disable the reporting of alarms for
ten minutes. After ten minutes, the alarms can be
reported. If the equipment is maintained for more than
10 minutes, restart the alarm shield.
Get Current View the temperature and humidity associated with the -
Temperature and base station in operation. This parameter can be used for
Humidity querying the status of the environment alarm.
Procedure
Step 1 In the left pane of the Site Maintenance Terminal System window, click Site . In the right
pane of the window, double-click Environment Monitor.
The Environment Monitor dialog box is displayed, as shown in Figure 10-1.
Step 2 Perform the following operations in the Select Operation Type area:
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 84/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 10 Checking the BTS3900 Environment
Select... Then...
Step 3 Click OK .
----End
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 85/97
7/16/2019 BTS3900 GSM Commissioning Guide
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 86/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 11 FAQs for BTS Commissioning
11.1 Failed Communication Between the Site Maintenance Terminal and the BTS
This describes the fault symptom and analyzes the cause of the failed communication between
the Site Maintenance Terminal and the BTS. It also provides the fault handling suggestions.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 87/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
11 FAQs for BTS Commissioning Commissioning Guide
Fault Symptom
You fail to log in to the BTS on the Site Maintenance Terminal System. The result of running
the ping commands shows that the connection between the Site Maintenance Terminal PC and
the BTS cannot be established.
Table 11-1 Possible causes and handling suggestions for failed communication between the Site
Maintenance Terminal and the BTS
The crossover cable is faulty. Check the connection of the crossover cable.
Check whether the RJ45 connectors on both
ends are functional. If the RJ45 connector is
faulty, replace it with a new one.
The IP address of the Site Maintenance Check whether the IP address of the Site
Terminal PC is incorrect. Maintenance Terminal PC is on the same
network segment as that of the board by
referring to Checking Whether the IP
Address of the Site Maintenance Terminal
PC is on the Same Network Segment as
That of the Board.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 88/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 11 FAQs for BTS Commissioning
6. Run the hostShow command on the displayed HyperTerminal window to check the IP
address of the board. The IP address of the board is 12.12.12.100, as shown in Figure
11-1.
CAUTION
The IP address shown in Figure 11-1 is only for reference and is subject to the actual
configurations on site.
7. Check whether the IP address of the Site Maintenance Terminal PC is on the same network
segment as 12.12.12.100. If the IP addresses are not on the same network segment, change
the IP address of the Site Maintenance Terminal PC by referring to 4.1 Setting the IP
Address of the Site Maintenance Terminal PC .
Fault Symptom
When logical cells and all the links of upper layers are available, the E1 link on the BTS side is
abnormal.
Cause Analysis
The possible causes of the faulty E1 link are as follows:
Handling Suggestion
1. Check
Ensureall
thatthe
theconnections
connectionsonare
thereliable
E1 linkand
andthe
theconnectors
connectorsare
at functional.
both ends of each cable.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 89/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
11 FAQs for BTS Commissioning Commissioning Guide
2. Check whether the E1 link on the BTS side is normal through the physical loopback test.
3. Check the transmission channels. Ensure that all transmission channels are available.
For example, the physical loopback test is performed to troubleshoot the UELP failure, which
(1) On the BTS side, disconnect A from C, disconnect B from D, and then connect A to
B on the DDF, as shown in Figure 11-2. Thus, a physical loopback on the BTS side
is formed. The normal E1/T1 connection between the BTS and the BSC consists of
the connection between A and C and connection between B and D.
Figure 11-2 Physical loopback of the E1/T1 cable on the BTS side
A C
E1/T1 E1/T1
E1/T1 E1/T1
B D
BTS DDF BSC
(2) Check the status of the LIU LED corresponding to the E1/T1 cable in loopback mode.
Table 11-2 describes the meaning of the states of the LED.
Table 11-2 Meaning of the states of the LIU LED (UELP used)
If... Then...
The LED is ON or blinks at 4 Hz, The E1/T1 link on the BTS side is not
normal. Continue to troubleshoot the
fault in the UELP.
(3) Disconnect the E1 transfer cable and the E1/T1 cable. Then, directly connect the E1/
T1 cable to the E1/T1 port on the GTMU.
(4) When the UELP is not used, determine whether the E1/T1 link is normal based on the
status of the LIU LED on the GTMU panel, as listed in Table 11-3.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 90/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 11 FAQs for BTS Commissioning
Table 11-3 Meanings of the states of the LIU LED (UELP not used)
If... Then...
The LED is ON or blinks at 4 Hz, The E1 link on the BTS side is not
normal, but the UELP is functional.
(5) Reconnect the E1/T1 cable to the OUTSIDE port on the UELP and ensure that the
connection is proper.
(6) Reconnect the INSIDE port on the UELP and the E1/T1 port on the GTMU with the
E1 transfer cable and ensure that the connection is proper.
CAUTION
After the physical loopback test is complete, you should restore the normal E1/T1 connection
at the DDF on the BTS side and ensure that the connection is proper.
Fault Symptom
An MS fails to find the network.
Cause Analysis
The possible causes are as follows:
l The downlink signals are weak. Therefore, the MS is unable to locate the cell.
l The downlink interference is strong. The MS is unable to locate the cell or receive the
correct downlink system information.
l The cell radius is small.
NOTE
When the MS fails to find the network, pay attention to the output power of the local cell and the radio
network coverage.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 91/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
11 FAQs for BTS Commissioning Commissioning Guide
Fault Symptom
Service dialing failure may occur in either of the following cases:
Table 11-4 Possible causes and handling suggestions for service dialing failure
The CS domain or the PS domain on the CN side is not Keep the CS domain and the PS
ready. domain ready.
Fault Symptom
During the service test, the following problems may occur: low GPRS data rate in the PS domain
of the newly added BTS, or a high BER on the Abis interface.
Cause Analysis
The possible causes are as follows:
l The E1 cable is not properly grounded. You can enable the grounding status of the E1 cable
by setting the DIP switch SW2 on the GTMU. Table 11-5 describes the DIP switch
SW2.
1 2 3 4
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 92/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 11 FAQs for BTS Commissioning
1 2 3 4
If... Then...
Only one end of the E1 cable is grounded, The E1 cable is grounded properly.
Both ends of the E1 cable are grounded, The E1 cable is not grounded properly.
l The data configuration negotiated between the BSC and the BTS is not consistent.
l
The cell signals are weak.
l The MS capability is limited.
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 93/97
7/16/2019 BTS3900 GSM Commissioning Guide
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 94/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 12 Data Sheet for Commissioning
The commissioning data sheet is used to record the process and result of the commissioning.
Site Name
BTS Model
Commissioning
Engineers
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 95/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
12 Data Sheet for Commissioning Commissioning Guide
Transmission normal?
VSWR normal?
Service test
Site environment
Commissioning
Result
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 96/97
7/16/2019 BTS3900 GSM Commissioning Guide
BTS3900 GSM
Commissioning Guide 12 Data Sheet for Commissioning
Unsolved
problems during
commissioning
http://slidepdf.com/reader/full/bts3900-gsm-commissioning-guide 97/97