Rate Analysis SSM

The document provides an analysis of labor rates for coursed rubble masonry work from a nature walk project budget dated March 8, 2012. It includes the labor costs for a foreman, mason, beldar, and water man to complete 4 cubic meters of work. The total labor cost is Rs. 4137.7 or Rs. 1034.425 per cubic meter. It then analyzes the labor rates derived from the nature walk budget from February 23, 2011 for 1 cubic meter and 1 cubic feet. Finally, it adjusts the labor rates using current market rates for materials.

Uploaded by

vinoth
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
1K views2 pages

Rate Analysis SSM

The document provides an analysis of labor rates for coursed rubble masonry work from a nature walk project budget dated March 8, 2012. It includes the labor costs for a foreman, mason, beldar, and water man to complete 4 cubic meters of work. The total labor cost is Rs. 4137.7 or Rs. 1034.425 per cubic meter. It then analyzes the labor rates derived from the nature walk budget from February 23, 2011 for 1 cubic meter and 1 cubic feet. Finally, it adjusts the labor rates using current market rates for materials.

Uploaded by

vinoth
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Nature Walk

Rate analysis for SSM Labor cost


Project: Nature Walk
Date: 03/08/2012

Ref: Analysis of rates Nabhi publications (Page no. 664, iem no 5.3.1.8)
Sl.No Description Units Quantity Rate Amount Remarks

1 Labour for Coursed rubble masonry- SSM (Assume 4 Cum)

a Foreman Nos 0.15 500 75


b Mason Nos 3.5 450 1575
c Beldar Nos 3.5 320 1120
d FC Nos 3.5 200 700
e water man Nos 0.4 320 128

Total 3598
Contractors profit @ 15% 539.7

Total Labor cost for 4 cum 4137.7 Rs.


Labor cost for 1 cum 1034.425 Rs.
Labor cost for 1 Cft 29.30 Rs.

Labor Rate derived from Nature walk budget for SSM which is inclusive of Labor + Material
Rate of SSM as per Budget dated: 23/02/2011
Material rates as per Basic price list in Budget
Sl.No Description Units Quantity Rate Amount Remarks

1 Labour for Coursed rubble masonry- SSM (Assume 1 Cum)

a Nature walk Budget Cum 1 2800 2800


Deductions
b Size stone Nos -96 8 -768
c Cement Bags -1.24 300 -372
d Sand Cft -9.3 45 -418.5
e Profit on b, c & d 15% -233.775

Labor cost for 1 cum 1007.725 Rs.


Labor cost for 1 Cft 28.54 Rs.

file:///conversion/tmp/scratch/481471415.xlsx 1 of 2
Nature Walk

Labor Rate derived from Nature walk budget for SSM which is inclusive of Labor + Material
Rate of SSM as per Budget dated: 23/02/2011
Material rates as per present market
Sl.No Description Units Quantity Rate Amount Remarks

1 Labour for Coursed rubble masonry- SSM (Assume 1 Cum)

a Nature walk Budget Cum 1 2800 2800


Deductions
b Size stone Nos -96 8.5 -816
c Cement Bags -1.24 310 -384.4
d Sand Cft -9.3 35 -325.5
e Profit on b, c & d 15% -228.885

Labor cost for 1 cum 1045.215 Rs.


Labor cost for 1 Cft 29.60 Rs.