0% found this document useful (0 votes)
139 views

Indoor Pool Application Examples - Load Calculation

Uploaded by

fireonice
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
139 views

Indoor Pool Application Examples - Load Calculation

Uploaded by

fireonice
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

HRV700i Application Example

Example #1 - Indoor Recreational Pool


Design Criteria - Case study

Commissioned: January 1990


Location: Toronto, Ontario
Room Size: 1500 ft2
Pool Size: 700 ft2 (nominal)

Design Conditions: - water 80°F [27°C]


- air 82°F [28°C], 55% relative humidity

Heating Load: 21 MBH (building fabric only)


Pool cover: Yes

Preamble
The formula found in ASHRAE for calculation of the minimum air quantity required to remove evaporated water can
be reduced to a single manageable digit if certain assumptions are made. This method may be used successfully as a
“rule of thumb” method. For a more detailed calculation, see the guide for calculation of ventilation requirements
based on moisture evaporation in this section.

The first assumption is that the design conditions for a pool equate to 0.04 lb [0.02 kg] of moisture evaporated from the
surface per square foot of pool surface.

The second assumption is that in a worst case scenario, the required ventilation equates to 25 cfm per lb of water
evaporated.
Therefore:
0.04 lb/ft2 x 25 cfm/lb = 1 cfm/ft2 (at 40° F [4°C] ambient temperature and 55% RH inside)

The rule of thumb is therefore:


Pool ventilation requires 1 cfm/ft2 of pool surface.

Minimum Ventilation Calculation


Pool size = 700 ft2
700 ft2 x 1 cfm/ft2 = 700 cfm

Thermodynamic Load Calculation for Ventilation


The calculation of thermodynamic load for ventilation in simple terms is as follows:

Q = Flow Rate (cfm) x Run Time (hr./day) x 1.08 x Degree Days (°F)
Btu (natural gas) x % Efficiency (heating device)

Where:
Flow Rate = 700 Btu = 35,335
Run Time = 24% Efficiency = 0.9
Degree Days = 6827

Therefore:
Q = 700 x 24 x 1.08 x 6827
35,335 x 0.9

Q = 3895 m3 (137 million Btu/year)


(heat load for ventilation only)
HRV700i Application Example
Cost Savings Analysis with HRV700i
With natural gas at $0.22 per cubic meter, the ventilation heat load without heat recovery represents an annual cost of:
Cost = 0.22 $/m3 x 3895 m3 = $857.00 (based on 24 hr. operation)

The HRV700i heat recovery ventilator operating under a level of consistent high humidity will have a regain efficiency
of 75%. Installation of this unit will reduce the annual cost to an amount equal to:
Cost = [3895 m3 - (3895 m3 x 75%)] x 0.22 $/m3 = $214.00 (based on 24 hr. operation)

Equipment Selection
1) Hydronic boiler, 150 MBH (nom.) capacity (pool water, space and post core heating).
2) HRV700i, fixed plate Heat Recovery Ventilator, polypropylene core.
3) Hydronic copper/aluminum finned coil (sized to suit total calculated heat loss, with protective coating).
4) Controls: Pool Plus wall control (includes dehumidistat control), low voltage thermostat.
5) Ducting system: Coated spiral round, or sealed rectangular duct sized to suit airflow, (installed as a closed loop
below the floor slab or above windows).
6) Air delivery: Linear slot diffusers, 15° inclined, aluminum (air to sweep glass surfaces).
7) Return air: Single grille, aluminum.
8) Defrost air: Via dedicated duct and grille (defrost air is not to be taken from any mechanical room).

Operation
General
This application uses the supply fan of the HRV700i as the source of energy for both recirculation of the space heating
and as a source of dilution ventilation for the purpose of moisture control. In the absence of either a heating or
dehumidification call, the entire system is idle, with minimal energy usage.

Control Strategy
The room thermostat closes on a call for heat, (class 2 wiring), which operates a hydronic zone valve which is
complete with end switch. The end switch initiates circulator pump action. The same room thermostat via a relay,
starts the supply fan (only) of the HRV, to provide space heating.
Upon a call for dehumidification, with or without a call for heating, the dehumidistat closure causes the HRV to go to
high speed ventilation with both fans on providing full flow dilution ventilation.

This example is for illustrative


purposes only, errors or
omissions excepted.
Application Example

Example #2 - Theoretical Indoor Assembly Area


A Theoretical Application in New Orleans, LA

Preamble

The following example is offered as an illustration of the need for the application of different technology to the task of
reducing cooling loads in a semi tropical location.
Indoor swimming pools are the exception rather than the norm in such climates, an indoor assembly area is used as
an example.

Concept

Regardless of the precise application, energy use reduction in geographical locations with high wet bulb
temperatures, using energy recovery ventilation equipment, does not reclaim energy, but diverts the unwanted
portion of same back to atmosphere, thereby reducing the installed load of the comfort cooling system.

Ventilation, per se, has been assumed to be mandatory, and to consist of two components, infiltration/exfiltration and
controlled mechanical. The incidence of improved building practices is steadily decreasing the presence of the
former, while increasing the presence of the latter. This evolving trend allows pre-planning for the use of the ERV to
reduce both the first cost of equipment and to more accurately predict the cost (fuel) operation of the equipment.

Calculations

1. Airflow Rates
Many attempts have been made to produce both estimated and mandated ventilation flow rates, intended for
application in the broad, and sometimes bureaucratic sense, however circumstances alter cases. A typical assembly
room can accommodate people pursuing a multitude of activities. There may be some who are smoking, some who
are moving energetically, others sedentary. For the purpose of this discussion the selection of 25 cfm (cubic feet per
minute) per person is illustrative, not definitive, as is an occupancy of 100 persons.
For the purpose of this example a flow rate of 2500 cfm is used.

2. Design Conditions (summer)


New Orleans, LA has a design dry bulb temperature of 92°F [33°C] and a design wet bulb of 78°F [25°C]. Or an
enthalpy of 41.7 Btu/lb of dry air and associated moisture.
Inside design conditions approximate: 75° F [24°C] dry bulb, and 55% R.H. Or an enthalpy of 29.5 Btu/lb of dry air and
associated moisture.
A difference of 12.5 Btu/lb etc.

3. Load at Design
The additional load upon the air conditioning of this building, attributable to controlled ventilation will be proportional
to:
4.5 x 12.5 x 2500 or 140,625 Btu/hr or approximately 12 tons.

Load Seasonal
This may best be estimated by using the recorded bin records for St. Charles AP, LA which provides time @
temperature in hours.
Five bins are relevant, 95 - 100° F, 90 - 95° F, 85 - 90° F, 80 - 85° F, 75 - 80° F.
35 - 38°C, 32 - 35°C, 29 - 32°C, 27 - 29°C, 24 - 27°C.
The co-incident wet bulb temperature for these dry bulb conditions provide an enthalpy difference for each bin which
may easily be tabulated into a seasonal total using the formula:

4.5 x cfm x De
Where: cfm = flow rate in cubic feet per minute
De = enthalpy difference in Btu/lb of introduced air
4.5 = mass flow rate of standard air per hour
Application Example
Using this formula:
The first bin equates to: 4.5 x 2500 x 12.5 x 2 = 281,250 Btu/season
The second bin equates to: 4.5 x 2500 x 12.5 x 246 = 34,593,750 Btu/season
The third bin equates to: 4.5 x 2500 x 8 x 664 = 59,760,000 Btu/season
The fourth bin equates to: 4.5 x 2500 x 6.3 x 819 = 58,046,625 Btu/season
The fifth bin equates to: 4.5 x 2500 x 2.5 x 1572 = 44,212,500 Btu/season

Using a Seasonal Energy Efficiency Ration (SEER) of 10 Btu/Watt the total energy usage equals
19,689,413 Watts or 19,689 kW.

4. Operating Cost
Using an arbitrarily set price per Kilowatt hour of $0.075, the energy used represents an operating cost of $1,476.68. The
building used for this example is assumed to operate during the hours of maximum enthalpy difference, no adjustment
is made for hours of occupancy.

Mitigation of Operating Cost


This can be achieved via the application of an ERV unit or units, utilizing coated rotary wheel technology. Such a unit
diverts ambient air borne moisture back to the atmosphere via the fan energy contained in the outgoing air stream of
the ventilation unit. Simultaneously, there is some sensible temperature reduction of the fresh air entering the building.
These units have been shown to provide combined latent/sensible diversion/regain levels of 70% on a seasonal basis.
Thus, the previously calculated operating cost may be reduced to:

[1,476.68 - (1,476.68 X 70%)] = $443.00 This is a savings of $1,033.68 per season.

Conclusions
Unequivocally, some form of an Energy Saving device MUST form an essential part of every contemporary mechanical
design package. The only question at issue is one of selection of the appropriate technology to suit the climatic
conditions. It is worthy to note that while two extremes have been examined, a location with both low winter
temperature and high summer dry bulb conditions may show an annual savings greater than either of those mentioned.

For more information, contact:

Venmar CES Inc.


Saskatoon, SK Canada
© Venmar CES Inc. 1996
PN 204276 04/99

You might also like