0% found this document useful (0 votes)
74 views

Process Selection and Facility Layout: Learning Objectives

Here are the steps to solve this line balancing problem: 1. Draw the task relationship diagram with bubbles and arrows 2. Calculate cycle time: - Output = 275 units per day - Available time = 440 minutes - Cycle time = 440/275 = 1.6 minutes 3. Calculate minimum number of workstations: - Sum of task times = 0.3 + 0.6 + 0.4 + 1.2 + 0.2 + 0.6 + 0.1 + 0.5 + 0.3 = 4.2 minutes - Number of workstations = Sum of task times / Cycle time = 4.2/1.6 = 3 workstations 4. Assign tasks to work

Uploaded by

Winter Nai
Copyright
© Attribution Non-Commercial ShareAlike (BY-NC-SA)
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
74 views

Process Selection and Facility Layout: Learning Objectives

Here are the steps to solve this line balancing problem: 1. Draw the task relationship diagram with bubbles and arrows 2. Calculate cycle time: - Output = 275 units per day - Available time = 440 minutes - Cycle time = 440/275 = 1.6 minutes 3. Calculate minimum number of workstations: - Sum of task times = 0.3 + 0.6 + 0.4 + 1.2 + 0.2 + 0.6 + 0.1 + 0.5 + 0.3 = 4.2 minutes - Number of workstations = Sum of task times / Cycle time = 4.2/1.6 = 3 workstations 4. Assign tasks to work

Uploaded by

Winter Nai
Copyright
© Attribution Non-Commercial ShareAlike (BY-NC-SA)
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 25

17/2/2020

Process Selection and Facility


Layout

Learning Objectives

When you complete this supplement you


should be able to:

 be able to determine some of the main


reasons for redesign layout
 be able to discuss the major factors that
need to be considered
 be able to describe basic types of layout
 be able to apply line balancing

1
17/2/2020

REASONS FOR REDESIGNING LAYOUT

•Inefficient operations – bottlenecks


•Accident or safety hazards
•Introduction of new product or change of
current product design
•Change in volumes, mix outputs
•Change in process, method or equipment
•Change in environmental or legal requirements

FACTORS NEED TO BE CONSIDERED


•Capacity and space requirements – machines,
personnel, equipment allowance
•Selection of material handling equipment –
conveyor belt, AGV
•Environment and aesthetics – Lighting,
Temperature
•Flow of information - arrangement
•Cost of moving between work areas
•Safety aspects – hazard areas

2
17/2/2020

BASIC TYPES OF LAYOUT

1. Process Layout or Functional Layout


or Process-Oriented Layout
2. Product Layout or Product-Oriented
Layout
3. Fixed Position Layout

1. PROCESS LAYOUT
•All operations of similar nature are grouped
together in the same department or part of the
factory
•Variety High, Volume Low – job shop, small
batch production
•Permits flexibility in production, involved skill
workers
•Disadvantages – operate with high level of work
in progress, throughput time is high, cost of
material handling is high

3
17/2/2020

EXAMPLE OF PROCESS LAYOUT

Lathe Milling Drill

Assembly Grinding

Raw Material Finished Goods


Inspection
Storage Storage

2. PRODUCT LAYOUT
•Arrange activities in a line according to the
sequence of operations of a particular
product
•Each product has own line specifically design
to meet requirements
•Flow orderly and efficient, more automated
•Suitable for mass production or repetitive,
stable demand
•Variety Low, Volume High

4
17/2/2020

EXAMPLE OF PRODUCT LAYOUT

Workers

Components Move to
feed into inspection
conveyor
Machines

3. FIXED LAYOUT
•Product remains stationary for entire
production cycle
•Product produces too fragile, bulky or heavy
to move e.g. ship, house, aircraft
•Equipment, workers, materials and other
resources are brought to the production site
•Highly skilled workers, low equipment
utilization

10

5
17/2/2020

EXAMPLE OF FIXED LAYOUT

Workers Raw Materials

SHIP

Equipment Tools

11

LINE BALANCING
•To allocate a group of tasks to a workstation
and to determine an optimal set up of
workstations
•Cycle time is the time any two successive
units coming off the end of the line.
•Each workstation may consists of a number
of tasks
•Large number of combinations may be
possible but need to choose the optimum
solution

12

6
17/2/2020

Steps in Line Balancing


1. Draw up a diagram of the relationships among the
tasks; circle for tasks and arrow for relationship
2. Determine the required Cycle Time.
Cycle time
•The maximum time allowed at each workstation
to complete its set of tasks on a unit
•Cycle time also establishes the output rate of a
line

CT = Production Time per day (in min or sec)


Output per day (in units)

13

3. Derive the Min Number of Workstation


N = Sum of times for all tasks
CT
4. Assign tasks into workstation based on the rule
Add the task if total station time is less than the
cycle time and the predecessors of the task are
already done
Tasks should be assigned in the N workstations

5. Calculate the Efficiency of the Line

Efficiency = Sum of times for all tasks x 100%


N x CT

14

7
17/2/2020

Cycle Time is the time that 1 unit is produced.


100
chairs
Same as
per day Standard
Calculate the Output Rate Time (ST)
Output Rate = Operating time per day
CT

Bottleneck : the longest task act as a constraints

Minimum cycle time = the longest task (bottleneck)

Maximum cycle time = the sum of the task time

15

Assume 8 hours per day


0.1 min. 0.7 min. 1.0 min. 0.5 min. 0.2 min.

Min cycle time = the longest task (bottleneck)

Max cycle time = the sum of the task time (Σ)

Max Output

Min Output

16

8
17/2/2020

Bottleneck Workstation
30/hr. 30/hr. 30/hr. 30/hr.
1 min. 1 min. 2 min. 1 min.

Bottleneck

Parallel Workstations
30/hr. 2 min. 30/hr.

60/hr. 60/hr.
1 min. 1 min. 1 min.
30/hr.
2 min. 30/hr.
Parallel Workstations
6-17

17

Line Balancing Rules (2)


Some Heuristic (intuitive) Rules:
1. Assign tasks in order of most following tasks or
most followers. (ekor)
• Count the number of tasks that follow
2. Assign tasks in order of greatest positional
weight or longest processing time (kepala)
• Positional weight is the sum of each task’s
time and the times of all following tasks.

18

9
17/2/2020

The tasks shown in the table are to be assigned to


workstations. Management has designed an output rate of
275 units per day. Assume 440 minutes are available per
day.
Task Immediate Task Time
a. Calculate Cycle Time Follower (min)
b. Calculate the number A C 0.3
of workstation and
B D 0.6
efficiency.
C E 0.4
c. Assign all the tasks
D F 1.2
into workstations.
E G 0.2
F H 0.6
G H 0.1
H I 0.5
I End 0.3
19

Output=275 units per day. Assume 440 minutes per day.

Cycle Time = Production Time per day (in min)


Output per day (in units)

No. of Workstation = Sum of times for all tasks


Cycle Time

Efficiency = Sum of times for all tasks x 100 %


N x CT

20

10
17/2/2020

Draw Bubbles (tasks) & arrows

Task Immedia Task


te Time
Follower (min)
A C 0.3
B D 0.6
C E 0.4
D F 1.2
E G 0.2
F H 0.6
G H 0.1
Use rule: greatest positional weight or longest H I 0.5

processing time (kepala) I End 0.3

21

Time Task Idle


Assign
Workstation Remain Eligible Time Time
Task
(min) (min) (min)

22

11
17/2/2020

Result of Line Balancing

A C E G H I

B D F

23

Tutorial 1

Mac 2017

24

12
17/2/2020

25

a) Draw Precedence Diagram

26

13
17/2/2020

b) Calculate the output per hour

Cycle Time = Production Time per hour (in min)


Output per hour (in units)

Output = Production Time per hour =


CT

c) Calculate its efficiency


Efficiency = Sum of times for all tasks x 100 %
N x CT

27

Activity Preceding Time (min)


60% reduced
A - 0.5 from 1.0 min
B - 0.8
C - 0.7
D B 0.4
G A,D 0.72 40% reduced
from 1.2 min
H B,C 0.6
I G,H 0.64 20% reduced
from 0.8 min
J I 1.3
Σ=5.66
E & F eliminate

28

14
17/2/2020

Cycle Time = Production Time per hour (in min)


Output per hour (in units)

No. of Workstation = Sum of times for all tasks


CT
=

Efficiency = Sum of times for all tasks x 100 %


N x CT
=

29

G
A

0.5 0.72
D I J
B
0.4 0.64 1.3
0.8

H
C
Activity Preceding Time (min)
0.6
0.7 A - 0.5
B - 0.8
C - 0.7

Rule: most follower D


G
B
A,D
0.4
0.72
(ekor) H B,C 0.6
I G,H 0.64
J I 1.3

30

15
17/2/2020

WS CT (min) Eligible Assign Time (min) Idle (min)

Total Idle time


31

Assignment
Oct 2016

32

16
17/2/2020

33.3 kg outputs per hour


Cycle Time = Production Time per hour (in min)
Output per hour (in kg)

No. of Workstation = Sum of times for all tasks


CT

Efficiency = Sum of times for all tasks x 100 %


N x CT

33

C
a b f
0.6
1.4 0.5
0.5
h
d 0.5

0.7
g
1.0
e
0.8

34

17
17/2/2020

WS CT (min) Eligible Assign Time (min) Idle (min)

Total Idle time =


35

36

18
17/2/2020

Mac 2015

37

i) Draw Precedence Diagram

ii)Which task is bottleneck?

38

19
17/2/2020

39

40

20
17/2/2020

vi) Assign into workstation

41

WS CT (min) Eligible Assign Time (min) Idle (min)

Total Idle time =


42

21
17/2/2020

Jan 2018

43

44

22
17/2/2020

45

46

23
17/2/2020

WS CT (min) Eligible Assign Time (min) Idle (min)

Total Idle time =


47

48

24
17/2/2020

24 output per hour

Cycle Time =

No. of Workstation =

Efficiency =

49

WS CT (min) Eligible Assign Time (min) Idle (min)

Total Idle time =


50

25

You might also like