5-DPWH Proc Manual, Infra, App 2.1 DPWH Guide To VE PDF
5-DPWH Proc Manual, Infra, App 2.1 DPWH Guide To VE PDF
Contents
ABBREVIATIONS .......................................................................................................................................... IV
GLOSSARY ...................................................................................................................................................... V
1 INTRODUCTION ................................................................................................................................. 1-1
1.1 THE PURPOSE OF VALUE ENGINEERING ........................................................................................................ 1-1
1.2 DEFINITION OF VALUE ENGINEERING AND METHODOLOGY ............................................................................ 1-2
2 FUNDAMENTALS OF VALUE ENGINEERING .................................................................................... 2-1
2.1 HISTORY OF DEVELOPMENT ........................................................................................................................ 2-1
Value Methodology Policy in the Philippines .................................................................................. 2-2
2.2 BENEFITS OF VALUE METHODOLOGY TO AN ORGANIZATION ........................................................................... 2-3
2.3 TECHNIQUES .............................................................................................................................................. 2-4
General ............................................................................................................................................. 2-4
The Job Plan ...................................................................................................................................... 2-5
Functional Analysis .......................................................................................................................... 2-5
Weighted Evaluation Technique...................................................................................................... 2-8
Whole Life Costing .......................................................................................................................... 2-12
2.4 THE VALUE STUDY ................................................................................................................................... 2-14
General ........................................................................................................................................... 2-14
The Facilitator ................................................................................................................................ 2-14
Team Selection ............................................................................................................................... 2-16
Workshop Organization ................................................................................................................. 2-17
The Job Plan .................................................................................................................................... 2-19
3 PROJECT PHASE APPROACH ............................................................................................................ 3-1
4 PROJECT SELECTION ......................................................................................................................... 4-1
5 THE HIRING AND MANAGING OF VALUE ENGINEERING CONSULTANTS ..................................... 5-1
5.1 REQUIREMENTS ......................................................................................................................................... 5-1
5.2 SELECTION OF CONSULTANTS ...................................................................................................................... 5-1
6 REFERENCES ...................................................................................................................................... 6-1
i
Guide to Value Engineering
Volumes
Volume 1 Introduction and Overview
Volume 2A GeoHazard Assessment
Volume 2B Engineering Surveys
Volume 2C Geological and Geotechnical Investigations
Volume 3 Water Engineering Projects
Volume 4 Highway Design
Volume 5 Bridge Design
Volume 6 Public Buildings and Other Related Structures
Annexes
A Examples of Value Engineering
B Examples of Functions and Modifiers
C Examples of FAST Diagrams
D Discounted Cash Flows and Recurring Cost
E Checklist
F Creative Blocks
G Reason for Unsatisfactory Result
H Terms of Reference for Hiring Value Engineering Consultants
ii
Guide to Value Engineering
iii
Guide to Value Engineering
Abbreviations
Abbreviation Definition
iv
Guide to Value Engineering
Glossary
Acronym Definition
Function Analysis System A method for analyzing, organizing, and graphically displaying the interrelation of the basic and
Technique (FAST) secondary functions of a system, product, design, process, procedure, or facility.
Life-Cycle Cost Total cost of an item's ownership. This includes initial acquisition costs (right-of-way, planning,
design, and construction), operation, maintenance, modification, replacement, demolition,
financing, taxes and disposal as applicable.
Value Engineering The application of a value methodology to a planned or conceptual project or service to achieve
value improvement.
Value Management Recognizes that value principles are management tools applicable to a variety of problems only
one of which is cost. Internationally, the term has been adopted in preference to Value
Analysis or Value Engineering to differentiate the activity from the engineering functions in an
organization.
Value Methodology A systematic process used by a multidisciplinary team to improve the value of a product or
project through the engineering of its functions.
Worth of Basic Function An estimate of the least expensive way of performing a function, neglecting the actual
application of that function.
v
Guide to Value Engineering
1 Introduction
1.1 The Purpose of Value Engineering
This Guide draws on the content of the NEDA Value Engineering Handbook (NEDA,
2009) and maintains consistency with the requirements of that handbook, whilst
focusing on activities relevant to DPWH and other agencies involved in
infrastructure and building works. The GOAL Value Methodology Pocket Book
(GOAL, 2008) has also been drawn on in drafting this Guide.
VE is the most effective technique known to improve value, and eliminate
unnecessary costs in product design, testing, manufacturing, construction,
operations, maintenance, data, and processes and practices. While its application
to processes and practices is less well known, effectiveness in this area has been
highly successful.
Saving money and, at the same time, providing better value is a concept that
everyone can support. The benefits of optimizing infrastructure expenditures,
constructing more with less money, increasing efficiency and reducing the amount
of resource use must be recognized today and pursued in the future.
In the constant battle to find a better way to fight inflation, validate cost estimates,
and assure all stakeholders that the solutions being proposed are cost effective,
the application of VE comes to the forefront, for both government and private
decision-makers. VE is a proven technique used to combat runaway costs and is a
process proven by countless owners, manufacturers and government entities.
More specifically, VE is defined by an international certification body (SAVE
International) as: "the systematic application of recognized techniques by multi-
disciplinary team(s) that identifies the function of a product or service; establishes
a worth for that function; generates alternatives through the use of creative
thinking; and provides the needed functions, reliably, at the lowest overall cost".
Section 1 of this Guide provides an introduction to VE and Section 2 provides a
discussion on fundamentals of VE including history, benefits, techniques, and a
complete procedure for conducting a Value Study. Section 3 describes the phases
of a project and how VE can be applied in each phase. Section 4 deals with the
selection of projects for VE. Section 5 provides a procedure for hiring and
managing of VE Consultants.
The Guide provides specific guidance for analyzing VE studies to assure that the
studies have been accomplished in accordance with internationally accepted
standards and practices. Most importantly, the information included in these
chapters provides basic guidance in certifying that the study was accomplished
under the direction of a qualified expert, was accomplished by a multi-disciplinary
and certified team of bona fide experts, and was performed following the Job Plan.
The Job Plan is an internationally defined and accepted analytical process for VE.
1-1
Guide to Value Engineering
1-2
Guide to Value Engineering
1-3
Guide to Value Engineering
with developing the alternative ideas and costing them. Whole Life Costing
approach is incorporated into the VE system.
The details of the workshop, the involvement and background of the facilitator, the
scope of the VE and other detail varies both by country and by individual project.
However the fundamental requirement is a facilitated structured engineering by
an appropriate knowledge group, adequately briefed on the project, with clear
goals and identified outcomes.
In order to deliver VE successfully there needs to be a culture within the
organization and its consultants of “no blame”. It must be understood before the
VE process starts that the benefits of VE outputs come from the combined efforts
of the whole team, and that the original concept or detailed designs will change
during the VM process. If the original designer is considered blameworthy for
failing to identify the potential improvements, then the system will be resisted and
its success will be compromised.
Where external consultants are involved in the design process, they must under
their contract:
Be required to take part in value workshops.
Be required to undertake assessments, redesigns and costing of the
alternatives identified during the VM process.
Accept responsibility for the revised design.
Be recompensed for the additional work they undertake.
If the outcome of the VE process identifies that the original design was below a
reasonable standard then that issue should be dealt with completely separately
and subsequently, so as not to damage the positive approach required in the VE
process.
1-4
Guide to Value Engineering
Country Year
Canada 1950’s
Japan 1957
India 1977
Australia 1991
Malaysia 2000
Singapore 2008
2-1
Guide to Value Engineering
1
www.valuefoundation.org
2-2
Guide to Value Engineering
2
http://www.fhwa.dot.gov/ve/vereport.cfm
2-3
Guide to Value Engineering
NEDA (2009) provide examples of cost savings achieved worldwide. Case studies
in other countries have shown savings of 30% or more and benefit/cost ratios of
VE of over 30.
A 2008 report3 identified the Ho-Nam High Speed Railway project in Korea as
having reduced cost by 3.8% but also increased performance by 6.1% to achieve
an overall value improvement of over 10%. This assessment was undertaken using
an extension of the Caltrans VE approach.
2.3 Techniques
General
Among many techniques used to solve problems, only the VE approach calls for
function engineering followed by the application of creative thinking techniques.
Each step of the VE job plan (called phases) includes several tasks. To apply the VE
job plan, two important factors must be recognized:
An effective VE effort must include all phases of the job plan, as described
below. Omission of any phase will hamper the accomplishment of the
objectives. The amount of attention given to each phase, however, may differ
from one project to another.
A successful VE study requires a team effort. The cooperation and active
participation of several people produces synergy. This group dynamic plays a
key role in developing new ideas, and illustrates that the results of a team of
experts is greater than the sum of the effort of a number of individuals.
3
http://www.value-eng.org/2008conference/Park_HM-Multi-Level_Performance_Measurement.pdf
2-4
Guide to Value Engineering
Functional Analysis
The functional analysis requires the identification of function, modification to
achieve clarity, and the development of the functional analysis diagram, as
described in the following sections.
2-5
Guide to Value Engineering
2-6
Guide to Value Engineering
2-7
Guide to Value Engineering
Annex C shows typical FAST diagrams, and also the FAST listing for a remedial
work in landslide areas in the Philippines.
The latter listing does not provide the full power of diagramming, as the functions
linkages are not identified; however, for complex projects it provides a means of
displaying the resulting data from a FAST workshop activity.
The attributes, features, or criteria you pick normally relate to the subject of
the study. For example, a manufactured product may be judged on its
reliability, durability, ease to manufacture, development effort, customer
acceptance, and so on - A car might be judged on its handling, style,
acceleration, operating cost, and so on.
Each criterion used should meet minimum user owner needs. That is, if safety
is being compared to cost, the comparison is not between unsafe conditions
2-8
Guide to Value Engineering
versus lower costs, but increased safety over the minimum required safety
versus cost.
Cost may be a criterion, but it is not recommended since all proposals must
also pass a business case evaluation.
2. Define the criteria so all team members understand them.
The more elements of criteria that are compared to each other, the better. This
reduces the chance that one or two elements will receive such weight that they
swing or govern the decision regardless of how the other elements score.
3. List all the criteria on the evaluation form, assigning each a letter of the
alphabet as shown in the Table 2-3.
4. Use a paired comparison to determine the weight to be used for each criterion.
Paired comparison is a technique based on the understanding that any person
or group of people can select between any two items or, if they cannot choose,
can call them equal in importance.
Compare each criterion to another in turn. First, ask which is more important,
A or B. In the example of initial cost versus maintenance, the answer is A.
Next, ask how much more important that answer is, rating it major, medium,
or minor - that is, giving it three, two, or one points. Again, in the example,
initial cost A is medium in being more important than maintenance and is thus
recorded in the scoring matrix as A-2.
Continue to compare A with C, then A with D, and so on, until all criteria are
compared with each other and recorded in terms of their importance. Note
that, in the example, when B is compared with C, a choice cannot be made
between them, so the selection is recorded in the scoring matrix as B/C.
All judgments of the relative importance of criteria are between minimum and
maximum performance levels, or between needs and desires, with the intent
to determine the relative importance of each in order to optimize them later or
make tradeoffs.
5. Add the total number of each letter of the alphabet recorded in the scoring
matrix. This is the raw score of the weight for each of the criteria selected. For
example, on the first row of scoring matrix, criteria A have scored 2, 1, 2 and 3
giving a total of 8. So the number 8 is transferred to the Weighting Evaluation
Table under column ‘Raw Score’ against the row ‘A Initial Cost’.
If one criterion receives a zero score, it means that the attribute is not
important to the team in evaluating the idea, and it can be dropped from
further consideration. If, however, the team disagrees with this automatic
conclusion, giving it a raw score of one can save the evaluation criteria. This is
demonstrated in Table 2-3. Notice the Raw Score for criterion D “Aesthetics”
has a value of “1” even though “D” does not appear in the scoring matrix.
6. Reviewing the raw score, determine the weight of importance of each of the
criteria on a scale of one to ten, with ten being the highest and one being the
lowest. Remember that not all criteria are created equal.
Prepare a scoring matrix as shown on Table 2-3.
2-9
Guide to Value Engineering
SCORING MATRIX
B C D E F G H
C C-3 C/E
D E-3
DETERMINATION OF WEIGHTS
Phase Date
Design Development Phase
2-10
Guide to Value Engineering
Energy Reliability
Initial Cost Maintenance Aesthetics
Usage Performance
WT ASSIGNED
10 VALUE 6 8 1 6 TOTAL
PRESENT WAY
5 E E E E E RANK
2 F F √ F √
1 √ P P P P
Subtotal 10 18 16 3 12 59
IDEA 1 5 √ E E E E
4 VG VG VG VG VG
One thru-wall unit 3 G G G √ √ 1
One rooftop Unit 2 F √ √ F F
1 P P P P P
Subtotal 50 12 16 3 18 99
IDEA 2 5 E E E E E
4 VG VG VG VG VG
3 √ G G G √ 4
2 F F √ √ F
1 P √ P P P
Subtotal 30 6 16 2 18 72
IDEA 3 5 E E E E E
4 VG VG VG VG VG
3 G √ √ √ √ 3
2 √ F F F F
1 P P P P P
Subtotal 20 18 24 3 18 83
IDEA 4 5 E E E E E
4 √ VG VG √ VG
3 G √ G G G 2
2 F F √ F √
1 P P P P P
Subtotal 40 18 16 4 12 90
2-11
Guide to Value Engineering
7. List the criteria and the weights you have just established across the top of the
form.
8. Take one criterion at a time and score all ideas against it.
2-12
Guide to Value Engineering
Operation and Maintenance (O&M) costs are the costs associated with owning,
maintaining, operating, and using an item, or system. There are two types of O&M
costs, recurring and non-recurring. Recurring O&M costs are ordinary, routine,
repetitive maintenance expenses. On a highway, they include grass-cutting,
replacing traffic markings, and the cost of electricity for lights, drainage
maintenance, and guardrail maintenance. Consider these costs as a lump sum,
annual payment. Non-recurring O&M costs include replacement or irregular
activities, such as resurfacing a highway, re-decking a bridge, and crack and joint
sealing. Consider these costs individually.
Salvage Value is the value of selling or re-using items and material at the end of the
life cycle. For example, some items with salvage value are guardrail, recycled
pavement, bridge beams, rails, etc.
Another type of salvage value occurs when a highway’s life cycle is completed, and
a major reconstruction is undertaken. The salvage value of the old road would be
the right of way, grading, sub-base, etc., that will not have to be purchased or
performed for the reconstruction.
Perhaps the most difficult part of life cycle cost engineering to understand is the
time value of money. Put simply, money in the future is not as valuable as money
today. This has nothing to do with inflation, but with the flexibility of having the
money now, and the opportunity costs of not having the money now. The adopted
discount rates vary considerably from country to country; NEDA uses 15%. That
means that the value of a peso decreases by 15% for every year in the future. For
example, one peso in one year is worth PHP0.85 today.
Over the life cycle of different items or systems, costs are incurred at different
times. Because of the time value of money, it is not fair or consistent to compare
these costs at face value. For a fair comparison, refigure costs to today's pesos, by
applying a discount rate to bring future costs back to their value today.
To find the Life Cycle Cost of an item or system, the following steps are generally
followed:
Identify the expected life of the project element. This can be based on
background information, experience, policy, or by arbitrarily selecting an
expected life.
Identify construction costs of all alternatives. In most cases, this information
will be provided. If not, find it during the investigation phase of the VE study.
Identify recurring maintenance costs by year. This information is available
from maintenance staff, repair records, material usage, or accounting records.
Identify non-recurring maintenance costs by year. This information is also
available from maintenance staff, repair records, material usage, or accounting
records.
Identify salvage values, if any. For items such as right of way, grading, etc., the
initial cost can be used for the salvage value. Other items may require an
estimate on the part of the VE study team.
Using the discount rate chart, multiply recurring costs by the Uniform Series
present worth factor for the appropriate final year. For an item with a 20-year
life span, multiply the total annual recurring cost by the Uniform Series present
2-13
Guide to Value Engineering
worth factor for 20 years. This gives the total of all annual recurring costs for
the 20-year period.
Using a discount rate chart, multiply non-recurring costs by the Single
Payment present worth factor for the appropriate year. Multiply a cost
occurring during the 5th year by the Single Payment present worth factor for
year 5. This gives the present value of that payment in year 5 only. Multiply
other non- recurring costs by the appropriate factor individually.
Using the discount rate chart, multiply the total salvage value by the Single
Payment present worth factor for the appropriate (last) year. Find the salvage
value of an item in the last year of the life span, which is a single event. The
present value of the salvage is a NEGATIVE cost, since it returns money to the
owner. Subtract the salvage value from the total Life Cycle Cost of ownership
when finding the total cost.
The result of totaling the values from the computations gives the present worth
of the life cycle cost of the project.
As an alternative to the use of discount rate charts, use spreadsheet functions such
as the Excel NPV Net Present Value function. An example of a discount rate chart
is given in Annex D.
General
A Facilitator and the requirements for this position lead the value study, and the
stages of the study, are described in the following sections.
The Facilitator4
A facilitator is an individual who contributes structure and promotes participation.
He or she is a “content neutral” party who will help by supporting the team
member’s work more effectively, by doing their best thinking that enables the team
to achieve effective solutions. An example is a team leader offering team members
a method with which they can develop their own strategies to resolve a problem.
Although the leader is not giving answers, he or she has not abandoned the
members either. He or she attends the meeting to guide the members to their own
solution step-by-step.
A meeting chairperson can use the facilitation role to run those portions of a
meeting when they want the participants to offer their ideas and generate actions
they will implement. A leader can use facilitation whenever he or she wants
members to work a problem or activity themselves.
Instead of being a player, facilitators act more like a referee. They watch the action
more than participate in it. They control the pace and which activities happen and
when. They keep their finger on the pulse and know when to move on or bring
closure. Most important, facilitators help members define and reach his/her goals.
4
Facilitating with Ease! Core Skills for Facilitators, Team Leaders and Members, Managers, Consultants, and Trainers,3rd
Edition. Copyright © 2012 by John Wiley and Sons, Inc. Reproduced by permission of Jossey-Bass, an Imprint of Wiley.
www.josseybass.com
2-14
Guide to Value Engineering
When someone takes up the challenge of facilitating, they’re stepping into a very
clearly defined set of roles and responsibilities. These roles are:
To help the group define its overall goal, as well as its specific objectives.
To help members assess needs and create plans to meet them.
To provide processes that help members use their time efficiently to make high
quality decisions.
To guide group discussion to keep it on track.
To make accurate notes that reflect the ideas of members.
To help the group understand its own processes in order to work more
effectively.
To make sure that assumptions are surfaced and tested.
To support members in assessing their current skills as well as build new skills.
Using consensus to help a group make decisions that take all members’
opinions into account.
To support members in managing their own interpersonal dynamics.
To provide feedback to the group so that they can assess their progress and
make adjustments.
To manage conflict using a collaborative approach.
To help the group communicate effectively.
To help the group access resources from inside and outside the group.
To create an environment where members enjoy a positive, growing
experience while they work to attain group goals.
To foster leadership in others by sharing the responsibility for leading the
group.
To teach and empower others to facilitate: working oneself out of a job.
The main theory underpinning facilitation concerns the difference between
process and content. This theory states that in any interaction between people,
there are always two dimensions, the content and the process.
The content of any meeting is what is being discussed. It’s the task at hand, the
subjects being dealt with, and the problems being solved. The content is expressed
in the agenda. The content is the verbal portion of the meeting. It is obvious and
typically consumes the attention of the members.
The other element of any interaction is the process.
The process is how things are run. It refers to the methods, the procedures, the
format and the tools used. The process also includes the style of the interaction,
the group dynamics and the climate that is established. The process is silent and
harder to discern. It is the aspect of most meetings that’s largely unseen and often
ignored, since people are largely focused on discussing the content.
2-15
Guide to Value Engineering
When a meeting leader offers their opinion with the intent of influencing the
outcome of discussions, he or she is acting as the content leader.
When a meeting leader becomes neutral and non-directive in relation to the
content, he or she becomes the process leader or facilitator.
Team Selection
Depending on the scope of the project and time constraints for completion, VE
studies can vary from a small to large team effort, and may also have several people
assigned to support the team if and when their particular skills are needed.
Although there is no set size for an efficient VE team, five persons, supported on a
part-time basis by other elements of the organization (e.g. the proponent agency),
is usually a sufficient number. Selection of members to perform the study should
be based on the following criteria:
Use only staff/employees who have had VE training to support the VE team.
Team members should have attended an appropriate VE workshop-training
seminar, and should have familiarity with the VE process. If such experience is
unavailable, include a suitable orientation during the conduct of the study.
Identify work experience or background of the team members related to the
project under study. A mix of talent is desired to achieve different points of
view. Typical team members might include :
- Geotechnical engineer
- Right-of-way specialist
- Materials specialist
- Environmental specialist
- Structural engineer
- Design engineer
- Landscape architect
- Traffic operations specialist
- Maintenance engineer
- Resident engineer
- Cost estimator
- External stakeholders
The selection of individual team members is of paramount importance. As a
minimum, the team should be staffed with a higher level of experience and
expertise than the team performing the project or technical design. Team members
must have excellent communication skills and work easily within a team
environment. It is very important that the team be interdisciplinary. The particular
makeup of team members will vary depending on what point of project design or
implementation the VE study is occurring. At the preliminary planning or Concept
Development point more emphasis would be on staffing the team with planning
expertise rather than heavy with technical expertise. When VE is done at the
project Design Development Phase, Detailed Design or implementation stages, the
criteria for selecting the VE team members shift towards the technical
qualifications and construction expertise.
2-16
Guide to Value Engineering
Workshop Organization
2-17
Guide to Value Engineering
degree angle to the front of the room are useful because the team members can
easily see information projected on a screen or wall and face each other. In all
cases, it is useful to have natural lighting/ windows, computer Internet access, and
temperature control. It is the facilitator's responsibility to arrange the room prior
to the workshop to accommodate the group and visitors.
2-18
Guide to Value Engineering
2-19
Guide to Value Engineering
The basic function of a design element satisfies the user's need for having an action
performed. The secondary function may or may not support the basic function. An
aesthetic or esteem function fulfills a desire to form something more than what is
needed.
These functions are not mutually exclusive and are frequently present in designs.
Good value occurs when the user is provided with the essential functions, and the
unessential ones he desires, at a reasonable cost.
An outline of the Information Phase is given in Checklist 1 and further checklists
on information gathering, general information, engineering and design, methods
and processes, material and procurement and function and worth are given in
Checklist 2 to 8 in Annex E.
2-20
Guide to Value Engineering
Functional Cost
Functional cost is the method chosen to perform the function under consideration.
Where an item serves one function, the cost of the item is the cost of the function.
However, where an item serves more than one function, the cost of the item should
be pro-rated to match each function.
Functional Worth
Worth is the most inexpensive way to perform a function. Once all functions are
identified as basic or secondary and unnecessary functions discarded, the team
establishes the worth of a function, without considering where or how the function
is used. Functional worth determination is perhaps the most difficult step in VE,
but it is an indispensable step.
It is a highly creative endeavor because worth is a subjective rather than absolute
or objective measure. Skill, knowledge, and judgment play a major role in
determining the quantitative aspect of worth, in terms of pesos.
2-21
Guide to Value Engineering
value. Value engineers look beyond initial cost. The costs of operation,
maintenance, and disposal or replacement must also be considered.
A complete life cycle cost model should include an engineering of the following
items calculated in terms of present value:
Capital cost - initial cost of construction, design, land, legal fees, other related
costs.
Maintenance cost - the cost of regular maintenance patrol, repair, salaries of
maintenance personnel, and maintenance contracts.
Rehabilitation / replacement cost - the cost of replacing materials, equipment
or other elements during the life cycle of the entire facility.
Refer to Checklist 8, Annex E for detailed requirements of the Information on
Function and Worth.
2-22
Guide to Value Engineering
2-23
Guide to Value Engineering
2-24
Guide to Value Engineering
further. Use the same method on all 4-point ideas, and, if necessary, on the 3-
point ideas.
Probabilities Technique. In this technique, assign subjective probabilities of
success to the implementation of acceptable ideas. A probability close to one
means that the idea has a good chance of being implemented. A probability
close to zero means the idea has little, if any, chance of being adopted.
Estimating Alternatives. Rank the remaining alternatives according to an
estimate of their relative cost-avoidance potential. Base the ranking on relative
estimates comparing each of the alternatives against the original design
method for providing the function. Develop the surviving alternative further to
obtain more detailed cost estimates. Proceed to more detailed cost estimates
only if the preceding step indicates that the alternative is still a good candidate.
2-25
Guide to Value Engineering
records them on the matrix sheet. For this example the criteria are: cost,
appearance, comfort, performance, and safety.
Next, the individual weighs each criterion against the other. In this example the
decision is that cost is better than appearance by a factor of "2" same for cost
versus comfort; and cost is better than performance by a number of "1". This
process is continued until each criterion is compared to all other criteria.
Next, each of the Letter scores is added and the sum recorded below as a "Raw
Score" and then weighted as described above. Finally it is shown that Automobile
A is favored by a score of 86 over B (80) and C (77).
The example of a Weighing Matrix uses information to illustrate the method. The
actual information for a project should be used in the Weighting Matrix.
2-26
Guide to Value Engineering
Contractor 1
Contractor 2
Contractor 3
Contractor 4
Contractor 5
Contractor 6
Contractor 7
Contractor 8
Contractor 1
Contractor 2
Contractor 4
Contractor 5
Contractor 6
Contractor 7
Contractor 8
Weighting
Generic
Quality 5 10 10 10 10 10 10 10 10 10 10 5 10 5 10 5 15
Risk (10)
Cost risk 6 12 12 12 12 12 12 12 12 6 12 12 12 6 6 6 6
Time Risk 4 8 8 8 0 8 8 8 0 8 8 0 8 0 4 0 4
Environmental Impact 10 20 20 20 20 20 20 20 20 20 20 30 30 20 20 20 20
Time (10)
Start 5 10 10 10 10 10 0 10 10 0 10 10 10 10 10 10 10
La
La
ck
ck
of
of
D
Da
House at
ta
Delivery 2 2 2 2 2 2 2 2 2 2 0 4 0 4 0 a
Overall 3 3 3 0 3 3 0 3 0 0 3 3 3 3 3 6 6
Not Not Not
Mar Mark Mar
Cost 9 9 18 18 0 27 0 18 0 0 18 ked 36 ed 9 ked 0
Community/Beneficiary
Acceptance 9 36 36 36 36 36 36 36 36 36 36 0 27 36 36 0 36
11 11 11 12 11 11 13 10
Total 0 9 6 93 8 88 9 90 80 7 60 4 86 2 47 97
Unacceptable
2-27
Guide to Value Engineering
2-28
Guide to Value Engineering
2.4.5.7.2 Procedure
General. Subject each alternative to: (a) careful engineering to insure that the
user's needs are satisfied; (b) a determination of technical adequacy; (c) the
preparation of estimates of construction and life-cycle costs; and (d) a full
consideration of the costs of implementation, including redesign and schedule
changes.
Develop Specific Alternatives. Follow those alternatives that stand up under
close technical scrutiny to the development of specific designs and
recommendations. Prepare sketches of alternatives to facilitate identifying
problem areas remaining in the design. Perform a detailed cost engineering for
proposed alternatives to be included in the final proposal.
Testing. Perform any tests required to demonstrate technical feasibility before
the alternative is recommended for implementation. Often the desired tests
have already been conducted by another agency. Ask for a report on those
tests. If not available, the VE team may arrange for the necessary testing and
evaluation. Required testing should not delay approval of a proposal when: (a)
Risk is low; (b) Consequences of less success would involve nothing more
serious than less cost avoidance; (c) The element being tested involves an
intangible or subjective factor; and (d) The test is normal confirmation
procedure after an action is taken.
2-29
Guide to Value Engineering
2-30
Guide to Value Engineering
2-31
Guide to Value Engineering
2-32
Guide to Value Engineering
2-33
Guide to Value Engineering
2-34
Guide to Value Engineering
3-1
Guide to Value Engineering
3-2
Guide to Value Engineering
4 Project Selection
The key to project selection is to identify candidate projects for a VE study. The
projects should have the potential to achieve maximum cost avoidance, energy
savings, or other benefits, such as a shorter construction schedule through a
complete VE. It is also important that the right team members are chosen for the
study.
Proper selection is vital to the success of the entire VE program. As VE resources
are limited, a major criterion in project selection should be the potential benefit
from the resources invested.
There are certain qualities or aspects of a proposal that serves as indicator for
possible VE. The following areas of high cost or causes of high cost, which may
indicate poor value, should receive the majority of the VE effort.
Projects appropriate for undertaking VE are those that are of sufficient size to
justify the costs of the VE study, sufficiently complex that they require the analysis
and will provide benefits from the study, and where the stakeholders will support
the undertaking of the study, which might result in some time delay in completion
of the stage under study to provide benefits in the overall delivery.
Project selection in DPWH requires a short-term and a long-term strategy. Starting
with the larger and more complex whilst resources are limited and moving
towards a more comprehensive approach in the longer term when resources are
more plentiful would be the recommended way forward. A final target of all
projects over PHP100m has been recommended; this can be reviewed as the VE
Unit develops; however it will always be the case that very small projects will not
provide value for money from the VE activity, and should be improved by trickle-
down from lessons learned from larger projects.
The Champion in consultation with the VE Unit Head and with relevant
stakeholders should select projects.
Since the value of a project has been used as the guide to selection for VE the status
of packaged and split projects needs to be addressed. Packaged projects are those
where small projects are grouped together for procurement purposes. Unless
there is a common thread in the package, which would be worth examining using
VE, these projects would be classed for selection according to the value of the
individual package.
Split projects are those where one major project is divided into parts to provide
resources, or for procurement purposes. This division is not relevant to the
consideration of VE process and the total project value should be considered in
selection.
Notwithstanding the comments above regarding packaged and split projects, the
decision on selection of projects should finally be taken taking account of all
factors, not just the value of a project
4-1
Guide to Value Engineering
5-1
Guide to Value Engineering
6 References
Barry A J, Understanding your Client using Value Drivers, Value Magazine, October
2009.
Barton R, Back to Basics – an Overview of Value Management, HKIVM International
Conference, November 2000.
Barton R, Entities, Attributes and Value: Unpacking the Australian Standard
Definition of Value, Value Times, June 2007.
Barton R, More on the New VM Standard - Defining Value Management Studies,
Value Times, 2008.
Barton R, Value, Values and Value for Money, CPG Learning Seminar, 2009
Best Management Practice: Management of Value (MOV) Toolbox, UK Government
2011.
Bohon J D et al, Value Methodology: A Pocket Guide to Reduce Cost and Improve
Value Through Function Engineering, GOAL/QPC, 2008.
Certification Examination Study Guide, SAVE International, September 2011.
Dallas M, Innovations in the Management of Value, APM Group Ltd.
Department of Defense Instruction Number 4245.14: DoD Value Engineering (VE)
Program, October 26, 2012.
FHWA Value Engineering Policy, Order 1311.1A, 11pp, May 25, 2010.
Fisk E R and Reynolds W D, Construction Project Administration: Chapter 16 Value
Engineering, 9th Edition, Jul 24, 2009
Government Circular on Value Management.
Guidebook for VE Activities – A Basic VE Manual, (VE Katsudo No Tebiki, Society of
Japanese Value Engineering, August 1971) English translation 1981.
Guidelines for Value Engineering, AASHTO, March 2010.
Handbook for Logical Framework Engineering, Economic Planning Unit, Prime
Minister’s Department, Malaysia, 2010.
http://www.neda.gov.ph/progs_prj/Handbook/Value%20Engineering%20Hand
book%20-%20June%202009.pdf.
Implementing Lean in Construction: Overview of CIRIA’s Guides and a Brief
Introduction to Lean, RP978, and CIRIA London, 2013.
Invitation to first Philippine Association of Value Engineers Conference.
Life-cycle Cost Engineering Procedures Manual, California Department of
Transportation, 150pp, November 2007 (updated August 2010).
Male S, Kelly J, Gronqvist M and Graham D, Reappraising Value Methodologies In
Construction For Achieving Best Value, Value Solutions, 2005.
Male S, Kelly J, Gronqvist M and Graham D, Managing Value as a Management Style
for Projects, Value Solutions, 2006.
6-1
Guide to Value Engineering
6-2
Guide to Value Engineering
6-3
Annex A Examples of Value Engineering
Guide to Value Engineering
A. ORIGINAL DESIGN:
Rent, operate, and maintain two service and four utility vehicles.
B. ALTERNATIVE DESIGN:
Buy six used vehicles (less than 3 year old models) to be operated and maintained during the
execution of the project. Immediately following completion the vehicles will be turned over to
the government to be bid out with a minimum asking price of 50% of the purchasing price.
D. ADVANTAGE:
E. DISADVANTAGE:
G. TECHNICAL JUSTIFICATION:
Since the vehicles are to be sold at the end of the project, there will be no future maintenance
costs for the government as required by the Department of Budget and Management.
The vehicles could be purchased in urban environments to guarantee a less harsh treatment
and better condition of the unit.
A-1
Guide to Value Engineering
CALCULATIONS
ITEM A(5)a - Provide, operate and maintain 2 units (rental basis) PHP 7,036,444.80
at PHP 97,728.40/per month for 72 months
ITEM A(5)b - Provide, operate and maintain 4 units utility vehicles PHP 14,230,149.21
at PHP 98,820.48/per month for 144 months
________________
Total Cost of Original Plan - PHP 21,266,594.00
ITEM A(5)a - Purchase 6 slightly used Frontier 4x2 used PHP 2,700,000.00
(3 year old) Double cab pick-up (Year model Direct
2003) at PHP 450,000.00/per vehicle Cost
ITEM A(5)b - Operate and maintain 6 slightly used frontier 4x2 PHP 6,480,000.00
Direct Double Cab pick-up (year model 2003) at
Cost PHP 30,000.00/month for 216 months
COST SHEET
ITEM REFERENCE
1. Original Design
A-2
Guide to Value Engineering
2. VA Alternative
A-3
Guide to Value Engineering
Construct, operate and maintain two separate buildings, one building for office and laboratory
and one building for quarters inside a lot to be purchased and secured.
B. ALTERNATIVE DESIGN:
Construct, operate and maintain one single building, longer than the original, to serve as office,
laboratory and quarters inside the nearest Public School.
D. ADVANTAGES:
E. DISADVANTAGES:
G. TECHNICAL JUSTIFICATION:
The idea proposed here has been and is being adapted in other projects in the Philippines. The
combination of the structures allows for a net reduction of 24 m2 area of building.
The idea to use land provided by a school for their future use, or as in other projects, land from
the local town to provide the structure for a future clinic is a win-win situation both for the
local government and DPWH. DPWH has plenty of office space and does not need to
accumulate any more, while the local governments may be in need of new structures such as
schools for the growing population.
A-4
Guide to Value Engineering
Mutual cooperation and understanding between DPWH and the Department of Education
through a Memorandum of Agreement could be a much welcome idea and beneficial for both
entities. Construction of the building inside a Public School will give the necessary land
providing for the Engineer’s compound. It will only require minimum expenses to secure the
structure with fencing. The original design is shown below.
A-5
Guide to Value Engineering
ORIGINAL DESIGN
Engineer’s Living Quarters
a. Const. Cost PHP 2,277,225.15
b. Operation and Maintenance Cost PHP 2, 356,200.00
Total PHP 4,633,425.00
Say: 4.6 millions
Field Office and Laboratory
a. Cost of Const. PHP 2,300,700.00
b. Operation and Maintenance Cost PHP 6,811,200.00
Total PHP 9,111,900.24
Say: PHP 9M
Office/Facilities Compound
a. Acquire/Site Dev PHP 418,000,00
b. Operation and Maintenance Costs PHP 2,222,550.00
Total PHP 2,640,550.00
A-6
Guide to Value Engineering
A-7
Guide to Value Engineering
Note:
Original Estimated Cost PHP 16,385,875.39
After application of VE PHP 7,094,400.00
Savings PHP 9.29M
CALCULATIONS
ORIGINAL PLAN
Technical Description
1. Quarter Bldg. is 168 square meter (7x24)
2. Office Building is 168 square meter (7x24)
3. Office Compound 40m width and 45 length (1,800 square meter)
Item Acquire/Construction Cost Operation and Maintenance Total of A and B
Living Quarter PHP 2,277,225.15 PHP 2,356,200.00 PHP 4,633,425.15
Field Office PHP 2,300,700.24 PHP 6,811,200.00 PHP 9,111,900.24
Office Compound PHP 418,000.00 PHP 2,222,550.00 PHP 2,640,550.00
TOTAL PHP 4,995,925.39 PHP 11,389,950.00 PHP 16,385,875.39
Say 5.0 Millions Say 11.39 Millions Say 16.39 Millions
PHP 4,960,000.00
Material Engineer 1 9,000.00 36 mo. 324,000.00
Lab Technician 2 6,000.00 36 mo. 432,000.00
Lab Aide 2 5,000.00 36 mo. 360,000.00
Typist 1 6,000.00 36 mo. 216,000.00
Utility 1 4,000.00 36 mo. 144,000.00
Miscellaneous Electricity,
Maintenance, Bldg,
Site/Etc
25,000.00 36 mo. 900,000.00
Allowances for overtime
and SSS 800,000.00
Consumables 500,000.00
PHP 4,000,000.00
A-8
Guide to Value Engineering
COST SHEET
ITEM REFERENCE
1. Original Design
2. VA Alternative
A-9
Annex B Examples of Functions and Modifiers
Guide to Value Engineering
Verbs Nouns
Allocate identify alternative material
Allow improve awareness option
analyze increase concept order
Audit Inform control part
authorize maintain coordination performance
certify measure criteria personnel
compile monitor data plan
confirm obtain decision priority
copy organize design process
create procure deviation record
decrease protect direction regulation
develop provide documentation request
distribute receive facility resource
enter reconcile funds schedule
establish record goal shipment
evaluate report history source
facilitate set information staff
forecast specify instruction standard
generate test inventory status
guide transmit limit trend
Projects
Verbs Nouns
absorb heat air material
alter illuminate appearance objects
amplify impede balance oxidation
change improve beauty parking
circulate increase color people
collect induce communication power
condition insulate compression preparation
conduct interrupt convenience prestige
connect modulate current protection
contain prevent ego radiation
control protect enclosure sheer
convey provide energy sound
cool rectify environment space
create reduce features structure
distribute reflect feeling style
emit repel fire symmetry
enclose resist flow temperature
enjoy separate fluids tension
establish shield force texture
exclude smell form one
extinguish support heat torque
feel taste image utilities
filter think landscape view
finish transmit light voltage
generate ventilate load weight
B-1
Annex C Examples of FAST Diagrams
Guide to Value Engineering
C-1
Guide to Value Engineering
C-2
Guide to Value Engineering
FUNCTION ANALYSIS
BASIC FUNCTION: PROVIDE SHELTER
No COMPONENT VERB+NOUN TYPE
COST
A Facilities for the Engineer Provide Shelter B 28.43
A2 Laboratory Building Store Equipment S 9.05
A5 Service Vehicles Transport Personnel S 7.09
Ab Survey Instrument Collect Data S 6.02
A3 Engineer’s Quarters Provide Shelter S 4.09
A1 Field Office Compound Secure Area S 1.53
A4 Engineer’s Communication Communicate Instructions S 0.50
A7 Progress Photographs Support Documents S 0.16
TOTAL 56.87
BASIC FUNCTION: IMPROVE COMMUNICATIONS
No COMPONENT VERB+NOUN TYPE
COST
B Other General Requirements Provide Safety S 9.60
B11 Working Platform Provide Safety S 2.52
B3 Mobilization and Demobilization Provide/remove Safety S 2.42
B5 Traffic Control Devices Provide Safety S 1.98
Guide Motorist S
B12 Boring, Standard Penetration and Materials S 1.56
Determine Laboratory Test
Study Characteristics B
B2 Protect Personnel S 1.12
TOTAL 19.20
BASIC FUNCTION: CLEARING GROUND
No COMPONENT VERB+NOUN TYPE
COST
C Earthwork Remove Materials S 12.95
Establish Foundation S
C2 Surplus Common Excavation Remove Materials B 5.80
C4 Embankment Add/Support Materials B 2.50
C3 Bridge Exec., Found and Material Support Foundation B 2.28
C1 Removal of Existing Remove Structure S 1.43
C0 Clearing and Grubbing Clear Area S 0.47
TOTAL 25.43
BASIC FUNCTION: TRANSPORT GOODS
No COMPONENT VERB+NOUN TYPE
COST
D Sub-base and Base Course Support Pavement S 4.74
D0 Aggregate Sub-base Course Support Base Course S 5.98
D1 Aggregate Base Course Support Pavement S 3.53
D2 Crushed Aggregate Strengthen Base Material S 0.24
TOTAL 14.49
BASIC FUNCTION: SPAN OPENING
No COMPONENT VERB+NOUN TYPE
COST
F Bridge Construction Provide River Crossing B 25.90
Connect Highways B
Crossing Vehicles B
F0 Concrete Piles Support Structure S 12.78
F4 Reinforcing Steel Reinforce Concrete S 8.47
Strengthen Concrete S
F5 Concrete (Str. Seal, Lean) Strengthen Structure S 4.65
TOTAL 51.80
C-3
Guide to Value Engineering
TOTAL 27.00
BASIC FUNCTION: DRAIN WATER
No COMPONENT VERB+NOUN TYPE
COST
G Drainage and Slope Protection Protect Highway S 164.50
G8 Concrete Crib Protect Slope S 86.52
G10 Concrete Lined Canal Drain Water S 31.75
G13 Anchor, Mortar Spray, Geo-Grid Protect Slope S 26.40
G11 Concrete Chute Canal Collect Water S 11.60
G5 Stone Masonry Protect Slope S 2.40
G9 Gabions Protect Slope S 2.30
G4 Grouted Riprap Protect Slope S 1.13
G2 Concrete Catch Basin Collect Water S 0.86
G1 Under-drain Collect Water S 0.78
G6 Hand Laid Boulder/Apron Protect Slope S 0.35
G3 Cleaning of Existing Pipe/Line Restore Structure S 0.24
G0 Reinforced Concrete Pipe Culvert Drain Water S 0.16
TOTAL 328.83
BASIC FUNCTION: PROVIDE SAFETY
No COMPONENT VERB+NOUN TYPE
COST
H Miscellaneous Structures Prevent Accident S 7.28
H3 Metal Beam Guardrail Provide Safety S 2.06
H9 Grass and Wicker Work Protect Slope S 1.75
Control Erosion S
H12 Reflectorized Thermoplastic Guide Motorist S 1.30
Pavement
H10 Sodding Stabilized Slope S 1.12
H0 Concrete Curb and Gutter Collect Water S 0.79
H5 Road Signs Provide Safety S 0.18
H13 Concrete Informatory Signs Provide Information S 0.076
TOTAL 14.56
B = Basic Function
S = Secondary Function
C-4
Annex D Discounted Cash Flows and Recurring
Cost (Example)
Guide to Value Engineering
D-1
Annex E Checklists
Guide to Value Engineering
Checklists
Checklist 1. Information Phase Outline ............................................................................................ 1
E-i
Guide to Value Engineering
Project Project ID
Checklist 1 Information Phase Outline
E-1
Guide to Value Engineering
Quantity Data
volume or repetition
Prepared By: Date:
E-2
Guide to Value Engineering
E-3
Guide to Value Engineering
E-4
Guide to Value Engineering
E-5
Guide to Value Engineering
E-6
Guide to Value Engineering
E-7
Guide to Value Engineering
E-8
Guide to Value Engineering
E-9
Guide to Value Engineering
E-10
Guide to Value Engineering
E-11
Guide to Value Engineering
E-12
Guide to Value Engineering
Project Project ID
Checklist 13 Selection Phase
• Great complexity in the design - Generally, the more complex the design, the
more opportunity for improving value and performance.
• Advancement in the state-of-the-art- Those aspects of design that go beyond
the state-of-the-art usually offer potential value engineering savings.
• High degree of time compression in the design cycle- A project having an
accelerated design program usually contains elements of over design.
• A component or material that is critical, exotic, hard -to-get, or expensive
• Intricate shapes, deep excavations, high embankments, steep slopes, etc.
• Components that appear to be difficult to construct
• Overly long material haul- excessive borrow; excessive waste
• Expensive construction
• Long foundation piles
• Excessive reinforcement
• Cofferdam dewatering
• Architectural embellishment
• Record seeking designs (Longest span, highest piers, deepest cut, etc.)
• Large safety factors
• Curb, gutter, and sidewalk (rural)
• Specially designed components that appear to be similar to low-cost off-the-
shelf items
• Components that include non-standard fasteners, bearings, grades, and sizes
• Sole-source materials or equipment
• Processes or components that require highly skilled or time-consuming labor
• Items with poor service or cost history
• Items that have maintenance and field operation problems
• Project costs that exceed the amount budgeted
• Standard plans that are in use for more than three or four years
Prepared By: Date:
E-13
Annex F Creative Blocks
Guide to Value Engineering
Creative Blocks
1. Habitual Blocks
F-1
Annex G Reason for Unsatisfactory Result
Guide to Value Engineering
G-1
Guide to Value Engineering
G-2
Annex H Terms of Reference for Hiring Value
Engineering Consultants
Guide to Value Engineering
Pro Forma
Terms of Reference
for
Hiring Value Engineering Consultants
H-i
Guide to Value Engineering
Contents
1.0 INTRODUCTION........................................................................................................................................... 1
List of Exhibits
H-ii
Guide to Value Engineering
1. INTRODUCTION
Insert Name of Client (“the Client”) is seeking a qualified value engineering
consultant to provide value analysis, value engineering, value enhancement, value
management (SELECT ONE) services related to Insert name of project, product,
system or study object.
Describe project, product, system or study object. The objectives of the value
engineering consulting assignment are:
1. To identify potential changes to the project, product, system or study object
design that would satisfy the essential functions of the project, product,
system or study object at a lower (capital or life cycle) cost.
2. SCOPE OF WORK
It is intended that the selected value engineering consultant will conduct Insert
Number value workshop(s) to be conducted in Insert Location over a period of Insert
Number month(s).
The work will consist of the following individual tasks: (or as detailed in Exhibit “A”
Scope of Work:)
H-1
Guide to Value Engineering
iii. Using information provided by the Client and by the design team,
prepare cost, energy, life-cycle cost, space and/or other models as
appropriate.
iv. Conduct a validation of the estimated project, product, system or study
object costs.
4. Workshop(s) is/ are to be conducted using a job plan consistent with SAVE
International guidelines for value studies. The workshop(s) will be
conducted in the location identified in this Request for Proposal. The facility
in which the workshop(s) will be conducted will be provided and paid for by
the Client or Consultant (INSERT ONE). Each value engineering workshop
will consist of the following six phases conducted over a period of Insert
Number consecutive days:
i. Information Phase
ii. Function Analysis Phase
iii. Creativity Phase
iv. Evaluation Phase
v. Design Development Phase
vi. Presentation Phase
H-2
Guide to Value Engineering
3. REQUIRED QUALIFICATIONS
The value engineering consultant shall provide the following team members:
1. A value team leader who is certified by SAVE International as a Certified
Value Specialist (CVS).
2. An assistant team leader who, at minimum, is certified by SAVE International
as an Associate Value Specialist (AVS).
3. Technical specialists with appropriate qualifications (List Required
Specialists including quantity surveyors if required).
4. Supporting clerical and administrative staff to participate in the workshops
and assist with the study documentation.
The value engineering consultant shall demonstrate corporate experience pertinent
to the subject matter of the value engineering study.
4. SPECIAL REQUIREMENTS
The selected value engineering consultant will be invited to enter into a contract in
the standard SAVE International Form of Contract for Value Consulting Services and
to begin work within fourteen (14) days of notification to proceed.
Insert special conditions of contract, if any, including expectations of the Value
Engineering Consultant related to venue, equipment and related matters.
5. PROPOSAL FORMAT
Proposals are requested in the following format:
1. Cover Letter
2. Table of Contents
3. Introduction/Understanding of Scope of Work
4. Proposed Methodology and Delivery Schedule
5. Corporate Qualifications and Experience (including client references) Brief
Biographies of Key Personnel
6. Fee Proposal (include under separate cover) Other Considerations
6. SELECTION PROCESS
Submission Deadline
Proposals are due by Insert Date and Time at the following address:
Address Line 1
H-3
Guide to Value Engineering
Address Line 2
Any City, Any Country
Electronic copies may be transmitted by e-Mail to: Insert e-Mail Address
Proposals received after the date and time specified will not be considered.
Criterion Weighting
Understanding and Approach 25%
VE Team Leader Qualifications 25%
VE Team Member Qualifications 25%
Previous Experience and Performance 15%
Availability and Schedule 10%
Depending on the results of the evaluation of proposals, interviews may be conducted
with a short list of the proposers to make the final selection of the firm to conduct
this work. If interviews are required, the shortlisted proposers will be advised of the
date and time for their interview. Each firm will have one hour for their interview
process. The first 30 minutes will be spent in a formal presentation by the firm
expanding on the information provided in their proposal. The second 30 minutes
will be spent responding to questions from the interview panel. The final selection
will be based on the same criteria listed above, and will use the same weights as
indicated for the proposal evaluation.
Once the highest rated firm has been selected, Insert Name of Client will endeavor to
negotiate a contract with that firm. Should the two parties not be able to successfully
negotiate a contract for the services, negotiations with the highest rated firm will be
terminated and negotiations will be opened with the second highest rated firm and
so on.
Insert Name of Client reserves the right to reject any and or all proposals.
H-4
Guide to Value Engineering
EXHIBIT
“A”
The Value Engineering Consultant will provide the study team members identified
below:
__________/Cost Estimator
The Client will provide all other team members, at no cost to the Value E n gi ne eri ng
Consultant. The Value Engineering Consultant will communicate directly with all
study team members as needed relative to scheduling, pre-workshop, workshop and
post workshop activities.
PRE-WORKSHOP ACTIVITIES
H-5
Guide to Value Engineering
5. Preparing cost, energy, life cycle cost, space models, etc. contingent on supply
by Client of the information needed for their preparation.
The Client will distribute the project documents and materials to be studied to the
study team members at least five working days prior to the workshop start. All team
members except the cost estimator are to spend _ (4-16) hours reviewing the project
documents and materials prior to the start of the workshop. The cost estimator will
spend (12-24) hours reviewing the documents and validating the cost estimate
provided by the Client.
WORKSHOP
The workshop will be initiated by presentations from the Client, who will describe
the objectives of the Assignment and any constraints that will be placed on the study
team. The designers will explain specifically how the design accomplishes the Client’s
objectives and the details of that design. The workshop will include a detailed
function engineering of the major project elements. The team will generate a list of
ideas for project improvement followed by an evaluation of those ideas. This
evaluation will include input from key Client decision makers before proceeding with
development of recommendations. On the last day of the workshop, a presentation
of the recommendations will be provided to the Client decision makers and key
representatives of the design team.
To ensure that the study team has complete information about the project criteria,
the Client will provide at a minimum, the Client Assigned Manager and appropriate
key members of the design team for the first day and last day presentations as well as
the mid-point review meeting.
POST WORKSHOP
H-6
Guide to Value Engineering
SCHEDULE
DELIVERABLES
This value study effort will include the following deliverables, all of which are related
to the results of the workshop. These deliverables are:
1. Study Team Presentation Handout
2. Preliminary Value Study Report
3. Draft of the Final Value Study Report
4. Final Value Study Report
The Preliminary Report will be prepared in the Value Engineering Consultant report
format, and will be a compilation of the handwritten products developed in the
workshop.
The draft Value Study Report will be prepared in the Value Engineering Consultant
report format. The purpose of this draft report is to give the Client and other
appropriate reviewers the opportunity to check the final Value Study Report prior to
its final issuance.
The final Value Study Report is the final documentation of the VE study. The report is
a finalized version of the Draft Report including the incorporation of the Client’s
comments. The submittal of the final report concludes the Assignment.
THE CONSULTANT will provide the Client with the following number of copies of each
report:
1. Preliminary VE Study Report (fill in # of copies desired)
2. Draft of Final VE Study Report (fill in # of copies desired)
3. Final VE Study Report (fill in # of copies desired)
H-7