To,
The Team Leader,
M/s Highway Engineering Consultant in
Association with M/s L Telford Consulting Engineers Pvt. Ltd.
Hotel Holiday Home,
Shakti Nagar, Main Badrinath Road,
Karanprayag, Dist.- Chamoli, Uttarakhand – 246444
E-mail :
[email protected]Subject: Construction and Upgradation including specialized slope treatment of
existing road to 2-lane with paved shoulder from existing km. 458.900 to km.
459.475 (design ch. 456.200 to ch. 456.800) of Patalganga landslide of NH-
07 under Chardham Priyojna on EPC basis in the state uttarakhand. (Design
length = 0.600 km). - Regarding : Diversion of Road.
Reference: LOA No.: NHIDCL/Patalganga Landslide/NH-07/2018/299
dated10.12.2018
Agreement Dated 17.12.2018
Our Letter No.- BC/AE/HEC/19-20/1039, dated 12.02.2020
Dear Sir,
In the aforesaid contract we have to execute tunnel work on the hill side of road so that the
moving vehicles do not face the hazard/ danger from the likelihood of impact from rollover
of rocks/ debris from steep hill slope for which a cushion of earth-fill supported by retaining
wall is in built in the tunnel proposal.
It is however pertinent to mention here that ensuring of smooth passage of traffic on the
project road is also to be facilitated as this road being the trunk road feeding the entire
Alaknanda Valley, requirements of Defense forces as well as the rush of Chardham Yatris
necessitates uninterrupted and trouble free traffic movement. Towards this end it is essential
to maintain adequate road width at the location where the tunnel construction is under way
and part of the road width gets utilized in laying of tunnel invert and additional space is
required for working& operation of construction machinery, stacking of materials, shuttering,
carrying out reinforcement bending/ cutting work etc.& other activities associated with the
construction job.
Evidently not much space/ road width is left for safe passage of the traffic rush on project
road owing to above mentioned constricted site conditions which warrants construction of
protection walling in the shape of gabions etc. on valley side for creation of sufficient road
width so that the traffic through this bottle necked reach passes unhindered along with the
above considerations as detailed in foregoing paras.
The cost estimate based on proposals for creation of adequate road/width diversion in this
reach has accordingly been prepared which is however not covered under the provisions of
contract and needs to be considered under change of scope proposals. Towards this end it is
requested to issue a change of scope notice under clause 13.2.1 since the work is beyond the
provisions of schedule-B.
We shall submit the requisite documents as per clause 13.2.2 since the Drawings are under
process upon receipt of Change of Scope Notice.
Thanking you and assuring our best services as always.
Thanking you
Yours faithfully
For Bharat Construction (I) Pvt. Ltd.
RAJEEV GARG
Authorized Signatory
Encl: As above
CC: General Manager (Project), NHIDCL E-mail – [email protected]
CC: DGM, NHIDCL, Site office, Rudraprayag, E-mail:
[email protected]