Activity On Node: Es Ef
Activity On Node: Es Ef
Activity on Node
PDM-Precedence Network 5 2 2 1
Site Metal
CM612 Electric
1
Roofing
5
Description Finish to start (FS) Start to start (SS) Finish to finish (FF) Start to finish (SF)
LS Duration LF • Allows the overlap of concurrent activities without the need for
splitting. Hence fewer activities are used.
10-02-2015
50
How to draw a PDM
• Each activity is represented by a rectangular box showing all of
40 the pertinent activity data
110
• The activity boxes are linked with arrows, representing
100 relationship
• Four different relationships among the activities with lag
80
– FS lag 0‐(zero) is the most common
90
Relationship Types
Activity FS Lag Activity
– FS (Finish to Start) A B
– SS (Start to Start)
Start of B is dependent on Finish of A
– FF (Finish to Finish)
– SF (Start to Finish) • Lag = 0 Activity B can start immediately after A has finished
• Lag = X Activity B cannot start until X days after A has finished
10-02-2015
4 6 6
Pour Concrete 1 day Remove Formwork
Activity 0 Activity
1 day 1 day
A B
2 day
One day lag allows for
concrete curing
4 6 8
Pour Concrete
Activity 2 day Activity
A B
Strip Formwork
1 day
2 day
1 2
Floor Slab
section
Start to Start (SS) Example 4 3
Activity
A 2 3 4
1
Formwork/ Formwork/ Formwork/ Formwork/
Rebar Slab Rebar Slab Rebar Slab Rebar Slab
SS Lag Activity 2 days 2 days 2 days 2 days
B
1 2 3 4
M/P/E M/P/E M/P/E M/P/E
Rough-in Rough-in Rough-in Rough-in
Start of B is dependent on Start of A 2.5 days 2.5 days 2.5 days 2.5 days
SS is used when the succeeding activity is slower ( i.e. larger duration) M/P/E rough-in
2 day
Note: Succeeding activity is slower
10-02-2015
1 2
Floor Slab
section Start to Start (SS)
Example (Continued) 4 3 example
Formwork/Rebar
Slab 8 days 4 6 4
Activity Activity
A B
2 days M/P/E Rough-in
10 days 2 day 0
4 6 6
Activity Activity
Formwork and rebar floor slab
A B
4 6 6 Activity
A
Activity Activity
A B
SF Lag
2 day 0
4 6 8 Activity
B
Activity Activity
A B
Finish of B is dependent on Start of A
2 day 2 day
4 5 4
Install and start Complete Complete
Dewatering Excavation Activity Activity
foundation backfilling
(finish milestone) A B
2 days 2 days 0
Dewatering will discontinue 2 days
after the start of backfilling Stop
Dewatering
4 6 6
(finish milestone)
Activity Activity
Install and start A B
dewatering Excavation Foundation Backfilling
2 days 2 days
Stop Dewatering
2 days
10-02-2015
15 5
F I
BACKWARD PATH
PDM Calculations Step 1
EF j ES j D j
ES EF ES EF i j
i j
LS LF LS LF
Total Float 10 30
TFL LF EF Mobilize Underground
i i i
5 10
NTP Utilities
Free Float 0 or 1 5
ES j FSij EFi
ES j SSij ESi 20
FFLi
EF j FFij EFi Obtain Permits
EF j SFij ESi 5 One Start Needed --
The Beginning
Calculations
10
A
30 Becomes 3 The Forward Pass
A 3
0 10 10 14
B
10 5 20 10 20
4 NTP B
0 4 Mobilize FS Site Survey
C 8 10 0 4
20
30
C Early _ Finishactivity Early _ Startactivity Durationactivity
8
Early _ Start follower Early _ Finishactivity Lag _ ValueBetween_them
m
Backward Pass –
Drawing Precedence Calculations -- Float
3 13 13 17
0 10 11 16 16 25
20 40 90 10 20
A
10
C
5
H
9
Mobilize Site Survey
0
1 11 11 16 16 25 10 0/2 4 ?/2
10
START 5 15 15 19
0 0 7 7 11 11 16 25
TF = LF -EF
120
0 30
B
50
D
80
G FINISH FF = ESfollower- lagbetween-activities – EFactivity (minimum for
7 4 5 4
all followers)
0 7 7 11 11
16
16
20 20
25
22 The same rules apply:
7 13 13 16
60 70 100 110 •At least one pusher has FF = 0
E
6
F
3
K
4
L
2
•TF along a simple chain is all the same
10 16 16 19 19 23 23 25 •FF/TF on activities not on connecting arrows
Drawing Precedence –
Calculating the Floats Finish to Start Relationships
Example
Total & Free Float
Pour Concrete 1 day Remove Formwork
1 day 1 day 45 58 62 71
K FS N
One day lag allows for
concrete curing
13 0/6 4 9 ?/6
51 64 68 77
Pour Concrete
1 day
Strip Formwork
• TF = LF - EF always = 6
• FFK = ESfollower - Lag K-N - EFK
= 62 - 4 - 58 = 0
1 2
Floor Slab
section
Example 4 3
45 58 49 58 1 2 3 4
M/P/E M/P/E M/P/E M/P/E
K SS N Rough-in Rough-in Rough-in Rough-in
13 4 9 2.5 days 2.5 days 2.5 days 2.5 days
64 77 68 77
Formwork and rebar floor slab
1 2
Floor Slab
section
Example (Continued) 4 3
45 58 49 58
2 days M/P/E Rough-in K SS N
10 days
13 0/19 4 9 ?/19
64 77 68 77
Example
K FF N
13 4 9 Install Drywall Boards
10 days
60 73 68 77
Example
Total & Free Float
Install and start Complete Complete
Dewatering Excavation
foundation backfilling 45 58 40 49
(finish milestone)
K SF N
Dewatering will discontinue 2 days
2 days
13 0/28 4 9 ?/28
after the start of backfilling Stop
Dewatering 73 86 68 77
(finish milestone)
28
BACKWARD PASS
25
20/6
ESj - FSij - EFi 15 18 ESj - Sfij - ESi ESj - SSij - ESi
20/0 15 - 2-13 28 - 7 - 15 14/14
F 23 28 38 - 1 - 23
6 13
FS2 3 SF7 EFj - FFij - EFi
K
ESj - SSij - ESi B 35 38 5 46 - 2 - 28
EFj - FFij - EFi
14/0 FF2, SS1
6-5-1 7
26 33
31 - 2 - 13 37 42
FF2 21 31 SS2 0/0
ESj - FSij -EFi ESj - SSij - ESi
SS5 0/0 21 - 0 - 21 G 23 - 2 - 21
38 46
ESj - FSij - ESj
0/0 11 - 0 - 1 11 21 FS0 10 0/0 N
EFj - FFij - EFi28 33 ESj - SSij - ESi
1 11 FS0 C ESj - SSij - ESi35 45 33 - 2 - 31 31 - 3 28
8
10 16 - 5 - 11 L 38 46
A ESj - SSij - ESi 0/0
SS3
11 21 SS5 0/0 28 - 10 - 16 5 31 37 FS1
10 16 31
ESj - FSij - Efi
28 33 M ESj - FSij - EFi
1 11 11 - 0 - 11 4/1 H SS10, FF2
FS0 11 21 ESj - FFij - EFi 6 38 - 1 - 37
15 FS2
D 23 - 1 - 21 31 37
FF1 16 31 ESj - FSij - EFi
FF0 10
3/3 28 - 2 - 23 FS3
15 25 ESj - FSij - EFi
ESj - FFij -EFi 16 - 5 - 11
16 23 14/14 ESj - FSij - EFi
3/0
11 - 0 - 11 7 11 FS5 I 11 14 31 - 3 - 14
7
E J
4 19 26 3
FS0
10 14 25 28 TF/FF
ESj - FSij - EFi
11 - 0 - 11 TFi = LFi - EFi