Name of The District: Subarnapur Name of The Block: Birmaharaj Pur Sl. No. Equipment Details Remarks Working Status (Yes / No)
Name of The District: Subarnapur Name of The Block: Birmaharaj Pur Sl. No. Equipment Details Remarks Working Status (Yes / No)
Working
Sl. No. Equipment Details Status Remarks
(Yes / No)
1 Router Yes
2 Switch Yes
3 VC End Point Yes
4 LED TV Yes
5 UPS No
6 UPS Battery No
7 UPS Back up time No No backup
8 Secondary Power Source Yes DG
9 Condition of Oswan Room Good
10 Voltage Status No Fluctuation 210 V, 220 V,230 V
11 Electrical Earthing Yes
12 AC (Air Conditioner) Status Yes
13 Connectivity(BSNL) Yes
14 Manpower in PoP Yes
.
OSWAN PoP Status Report
Name of the District: Subarnapur
Working Status
Sl. No. Equipment Details
(Yes / No)
1 Router Yes
2 Switch Yes
3 VC End Point Yes
4 LED TV Yes
5 UPS No
6 UPS Battery No
7 UPS Back up time No
8 Secondary Power Source No
9 Condition of Oswan Room Good
10 Voltage Status No
11 Electrical Earthing Yes
12 AC (Air Conditioner) Status Not Working
13 Connectivity(BSNL) Yes
14 Manpower in PoP Yes
Remarks
0 Backup
210 V,230 V,
Damaged in flood
g business hours.
any secondary power backup, VC can't happen. At any moment power cut happens.
DeGM Sign
OSWAN PoP Status Report
Name of the District: Subarnapur
Working
Sl. No. Equipment Details Status
(Yes / No)
1 Router Yes
2 Switch Yes
3 VC End Point Yes
4 LED TV Yes
5 UPS No
6 UPS Battery No
7 UPS Back up time No Back up
8 Secondary Power Source No
9 Condition of Oswan Room No
10 Voltage Status Yes
11 Electrical Earthing Yes
12 AC (Air Conditioner) Status No
13 Connectivity(BSNL) Yes
14 Manpower in PoP Yes
Main reason for block VC not being up during business hour is power back up. Both the Printlink ups and batteries is fau
block provide 1 kva ups which is give only 5 minutes of back up. So at the time of long duration power cut block VC not
condition of the Oswan room is bad and the new room work is on progress for shifting.
Remarks
Damage
Three phase connectivity to Oswan room
Damaged by Rats
hour is power back up. Both the Printlink ups and batteries is faulty. Bhq running live by
of back up. So at the time of long duration power cut block VC not being up in that time.
om is bad and the new room work is on progress for shifting.
DeGM Sign
OSWAN PoP Status Report
Name of the District: Subarnapur Name of the Block: Tarbha
Working
Sl. No. Equipment Details Status Remarks
(Yes / No)
1 Router Yes
2 Switch No Adapter faulty
3 VC End Point Yes
4 LED TV Yes
VC Room UPS submerged in flood
5 UPS No
water
6 UPS Battery No
7 UPS Back up time No 0 backup
8 Secondary Power Source No
9 Condition of Oswan Room No Water leakage, Damage & repair
10 Voltage Status No Fluctuation 210 V~230 V
11 Electrical Earthing Yes
12 AC (Air Conditioner) Status No
13 Connectivity(BSNL) No CPE Faulty
14 Manpower in PoP Yes