Column1 East Bound West Bound North Bound South Bound LT 50 100 75 400 TH 500 700 300 400 RT 100 50 400 50

This document summarizes the design of a traffic signal with 4 phases (a, b, c, d) and the calculation of cycle length, green times, and amber times. It determines the critical traffic volumes for each phase to calculate the cycle length of 475 seconds. It then allocates green times for each phase based on their fraction of the critical traffic volume. Amber times are set at 5 seconds for phases a, b, and c and 6 seconds for phase d based on intersection widths. The final conclusion lists the green and amber times for each phase.

Uploaded by

Akash Gupta
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
34 views

Column1 East Bound West Bound North Bound South Bound LT 50 100 75 400 TH 500 700 300 400 RT 100 50 400 50

This document summarizes the design of a traffic signal with 4 phases (a, b, c, d) and the calculation of cycle length, green times, and amber times. It determines the critical traffic volumes for each phase to calculate the cycle length of 475 seconds. It then allocates green times for each phase based on their fraction of the critical traffic volume. Amber times are set at 5 seconds for phases a, b, and c and 6 seconds for phase d based on intersection widths. The final conclusion lists the green and amber times for each phase.

Uploaded by

Akash Gupta
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

AKASH GUPTA Experiment No.

9 31-May-20
170104010 Signal Design

i = 10*4 = 40 Note : Pedestrian movement across N-S is incorporated in phase b and across E-
j = 10*5 = 50 W in phase d.

Column1 East Bound West Bound North Bound South Bound


LT 50 100 75 400
Th 500 700 300 400
RT 100 50 400 50

Determination of Critical Movements (V/S values)


Phase a - Max(360/1440 , 60/1440) = 0.25
Phase b - Max(280/1800 , 115/1600, 420/1800 , 360/1600) = 0.225
Phase c - Max(140/1440 , 100/1440) = 0.097
Phase d - Max(90/1600 , 100/1600 , 490/1800 , 660/1800) = 0.367
Therefore, Cycle Length

C= 1.5 X (4 X 4) + 5 = 475 sec


1 - (0.25+0.225+0.097+0.367)
1 - (0.25+0.225+0.097+0.367)

Amber Time Calculation


v = design speed = 80 kmph = 22.22 m/sec
rt = reaction time for braking = 1 sec
dc = comfortable deceleration rate = 4 m/s2
L = design vehicle length = 5m
W = Width of intersection = 17m (N-S) , 28m (E-W)
Minimum amber time
t = rt + (v/2*dc) + (W+L)/v
t = 1 + 22.22/2*4 + (22,33)/22.22 = 4.77 sec (N-S) , 5.26 sec (E-W)

Amber time approximated to 5 sec for phase b. (North-South)


and 6 sec for phase d. (East-West)
Amber time assumed as 5 sec for phase a.
and 6 sec for phase c.

Green Time allocation


G = C - sum(amber time + all red time)
All red time = 1sec per phase
G = 475 - (2*(5+6) + 1*4) sec = 449 sec
See Table : Fraction of Green Time = (V/S)/SUM
Green Time = 449 * (Fraction of Green Time)

As per IRC, Requirement for Green time Tp = 7 + (W/1.2) = 21.17 sec , 30.33 sec
Tp approximated to 21 sec for phases a & b and 30 sec for phases c & d.

Check : (Tp - Amber time) should be less than Final value of alloted Green time
For Phase a & b, Tp - Amber time = 16 sec. (<108 sec & <120 sec) OK
For Phase c & d, Tp - Amber time = 24 sec. (<175 sec & <46 sec) OK

Green Time Allocation for different phases

Phase V/S Fraction of Green Green Time (sec) Final Value


Time
a 0.25 0.266240681576145 119.542066027689 120
b 0.225 0.23961661341853 107.58785942492 108
c 0.097 0.103301384451544 46.3823216187434 46
d 0.367 0.390841320553781 175.487752928648 175
SUM 0.939

Conclusion : Phase Green Time (sec) Amber Time (sec)


a 120 5
b 108 5
c 46 6
d 175 6