Test - Monitoring and Evaluation Pre-Test
Test - Monitoring and Evaluation Pre-Test
test
Question 1 of 20.
What are the four phases of the project cycle as defined by the IFRC?
Question 2 of 20.
From the following statements, select the SIX key steps for good M&E as defined by the IFRC
Question 3 of 20.
An assessment to verify compliance with established regulations or procedures, especially financial.
An assessment, as systematic and objective as possible, of an ongoing or completed project, programme
or policy, its design, implementation and results.
Question 4 of 20.
The routine collection and analysis of information to track progress against set plans and check compliance
to established standards.
An assessment to verify compliance with established regulations or procedures, especially financial.
An assessment, as systematic and objective as possible, of an ongoing or completed project, programme
or policy, its design, implementation and results.
Question 5 of 20.
Which ONE of these statements is NOT one of the IFRC’s key standards and practices for ethical and
accountable M&E?
M&E should uphold the fundamental principles of the International Red Cross and Red Crescent
Movement.
M&E should only be carried out by members of the community where the project is being implemented.
An M&E system should ensure that stakeholders can provide comment and voice any complaints about
IFRC work.
M&E should respect the customs, culture, and dignity of human subjects.
Question 6 of 20.
Which ONE of these statements is NOT a consideration for the scope of an M&E system?
Question 7 of 20.
Which THREE of the following statements are a way to describe evaluation types?
Question 8 of 20.
To precisely measure the situation before project implementation, so that we can measure what difference
the project made.
To repeat the same measurements done during initial assessment to double check it is correct.
Question 9 of 20.
A table that builds on your logframe to detail key M&E requirements for each indicator and assumption.
A table with four rows and four columns in which the key aspects of a project are summarised.
A table which summarizes key measurement information for the logframe indicators and assumptions.
A roadmap that guides you on how to actually collect data on your indicators and assumptions.
Question 10 of 20.
Question 11 of 20.
Question 12 of 20.
Which SIX of the following are a type of data collection method or tool? Select all that apply.
Direct observation.
Survey.
Checklist.
Questionnaire.
Question 13 of 20.
Triangulation is used to cross-check data to better ensure it is valid, reliable and complete.
Triangulation means using different sources and/or methods for data collection (and analysis).
Question 14 of 20.
What is “variance”?
The change between an outcome and output.
The difference between an indicator’s target and the actual value recorded.
Question 15 of 20.
It is where ongoing measurement of the indicators and variance against the targets are recorded.
Question 16 of 20.
Looking for trends, clusters or other relationships between different types of data.
Question 17 of 20.
Which ONE of these is NOT a key stage in data analysis (as defined by IFRC)?
Analysis.
Validation.
Preparation.
Which TWO of the following should NOT be included in a good project/ programme report?
Question 19 of 20.
All projects should allocate at least 20% of their budget to their M&E activities. Otherwise, there is a risk the
activities will not be sufficient.
Projects should generally allocate between 3% and 10% of the overall budget to their M&E activities. The
bigger the project, the smaller the percentage should be.
Projects should not normally allocate more than 2% of their overall budget to their M&E activities. The
money is for implementing activities, not for M&E.
Question 20 of 20.
Which ONE of the following statements is INCORRECT regarding use of information collected through M&E?
The information should be used for project management, to inform decisions and improve implementation.