752 1514 1 PB PDF
752 1514 1 PB PDF
Abstract – Energy is one of the important inputs for economic progress of a country. Power generation is a key
parameter in the development of recent economies and the augmentation of productivity. The main objective of the
present paper is to review; compare the performance of SEB’s and effect on energy sector in India. The paper
discusses the more important of the problem areas holding up significant economic gains that could be realized
through cost reductions, operation of market forces, needed levels of investments and targeting of resources to
promote equitable growth. The slow rate of progress is a matter for concern.
The state governments were unenthusiastic and conflicting to the unbundling of electricity boards, but
according to the power research and recent studies, restructuring has improved the performance of these boards. The
present research paper concludes with few case studies of unbundling of SEBs in India.
Fig. 1. Graphical projection of the power supply position in cifferent state/system/region (April to September, 2008).
Fig. 2. Graphical projection of the energy peak demand and peak met in different state/system/region (April to
September, 2008).
There are many profitable and hurting insights that According to Figure 1, in the northern region / state,
we get from the statistics in these studies. Figures 3 and especially Uttar Pradesh requirement is more i.e. 31,946
4 are signifying the graphical projection of power supply MU with the deficit of 17.3 % which shows that power
position in different regions. supply requirement is high.
Apart from the failure of SEBs to raise However, in Punjab demand is 23,293 MU with the
investments, it is the uneconomic pricing of electricity. deficit 8.7 %, which is the 2nd largest demand in the
104 R. Rameshwar, R. Agrawal and M.K. Pathak / International Energy Journal 11 (2010) 101-110
region. On the other hand, if we consider the eastern 3.8 % in Uttar Pradesh, Punjab and Orissa states
state, Orissa shows the 2nd highest demand i.e. 10172 respectively.
MU with the deficit of 1.7% in the region. It is one of Moreover according to the energy data available
the states in the power sector, where the SEB is from the general review 2007 of Central Electricity
structured and well organized. Authority (CEA), the State-wise energy available (in
With reference to Figures 5 and 6, there was a GWH) / Transmission and Distribution Loss (%) were
shortfall monitored in 2008 between peak demand and monitored in the states of Orissa, Punjab and Uttar
peak met of 10,564 MW with deficit of 22.2 %, 8,737 Pradesh are 16,036.37 GWH / 40.86 %, 35,956.22
MW with deficit of 16.3 % and 3,137 MW with deficit GWH / 26.61 % and 51,937.13 / 33.49 %, respectively.
Fig. 3. Graphical projection of the power supply position in Fig. 4. Graphical projection of the power supply position
northern state/system/region (April to September, 2008). in eastern state/system/region (April to September, 2008).
Fig. 5. Graphical projection of the energy peak demand and Fig. 6. Graphical projection of the energy peak demand
peak met in northern state/system/region (April to and peak met in eastern state/system/region (April to
September, 2008). September, 2008).
7. ELECTRICITY LEGISLATION IN INDIA (supply) Act, 1948 was exclusively meant to comprise
and regulate the activities of these utilities [6]. The
The electricity legislation that has evolved in India over
straight structure of power utilities came into question
the years, in many ways, reflects the worldwide trends.
worldwide on grounds of efficiency during the 1990s.
By 1948, there were considerable advances in power
India too was affected by this international concern for
generation technology, giving rise to economies of scale
efficiency, which gave rise to electricity reforms.
in power generation. This together with the advances in
Indian power sector has also experienced a speedy
transmission technology, made it possible to transmit
change where India’s installed capacity was 1.362 MW
power at high voltages over long distances.
in 1947 but rose to 127.673 MW as on October, 2006
The result was the concern of typical state owned,
[1]. Reforms and privatization is important to look upon
centralized power generation, transmission and
the required amount of power, where government is
distribution utilities in the form of State Electricity
unable to provide the same.
Boards (SEBs) in the country. In fact, the Electricity
R. Rameshwar, R. Agrawal and M.K. Pathak / International Energy Journal 11 (2010) 101-110 105
As today, Indian energy strategy is coal based with Electricity Boards and the Power Grid Corporation
major 65% power comes from coal-fired plants and rest Limited.
from other energy sources. Power sector reforms are For optimum utilization of generating resources the
commonly acceptable on the basis that a state authority company has planned to create a strong national grid in
leads to poor productivity, services and financial returns. a phased manner to bringing out the security and the
As a part of restructuring exercise, Power Grid reliability in power system operation [4].
Corporation of India Limited (PGCIL) was set up to
9.1 Identifying the Main Problem in SEBs
look after T and D.
It was strong willed that distribution would be Independent power producers (IPPs) are demanding that
privatized in phase manner. Even most of the states in they have been allowed to sell power to third parties
India adopted and initiated this scheme of privatization straight as a substitute of selling to SEBs. The most
for better results to reduce theft, corruption and improve critical issue is finance under the PPA between IPPs and
the revenue collection strategy, efficiency and reliability SEBs. One basic requisite for identifying effective
of the distribution system. solution is the correct identification of the problem
itself. The weak finances of the SEBs are generally and
8. REFORMS IN POWER SECTOR incorrectly diagnosed as the basic problem of the sector.
The central problem of the sector is its politicization,
Through the sign of liberalization in the 1992,
which prevents the restoration of SEB finances and
governments across the world began to reassess the
blocks many other desirable developments. The policy
structure of the electricity industry. Various
making process would benefit greatly in effectiveness if
governments also viewed privatization and competitive
the central problem of the sector is recognized.
markets opportunity for reducing participation in their
Following identification principles are important as:
own power sector.
• Avoiding of any measures that contribute to further
Exceptionally steeped in the amount outstanding as
entrenching of the politicizing process
they were, many were no longer in a position to finance
future expansion of their power projects. They, as a • Priority to measures that would insulate the sector
result, used this as a means to shift at least part of their from the adverse effects of politicization
responsibilities to private participants. These principles continue to be overlooked, which
The main purpose behind this was to get private is cause for concern. Much damage has resulted from
parties to invest in generation, while leaving the the adoption of the MOU approach to project selection,
complex matter of network operations and long-term without either stipulation of a screening and pre-
planning with the central organization. Indian qualification mechanism or transparent regulatory and
government has to a pro-active role in unleashing and approval procedures in position.
accelerating the process of reform in the power sector in Table 5 is indicating the grid performance analysis
the country. using power supply position through different factors
According to the Tables 3 and 4, Central and States like energy requirement, availability and shortage
power reforms are expressed to be acquainted with the comparing with peak demand and peak met in different
different scenarios of reforms at a glance. With the regions of India, which shows the situation of its trading
beginning of economies liberalization in 1990s, and security of national grid.
solutions were sought to the crisis in power sector. THE CASE OF ORISSA STATE
Major role was played by international financial
institution to reform plans in the growing power State Overview
industry. Reform plans intended to introduce private The Orissa State Electricity Board (OSEB) is a statutory
players into the sector beginning with generation. body working with different corporations in the state
SEBs was unbundled and plans were made to named as Grid Corporation of Orissa Limited
privatize distribution. Additionally, independent (GRIDCO), Orissa Hydro Power Corporation Limited
regulatory commissions were also set up during the (OHPC), Orissa Power Generation Corporation Limited
period and achieved major milestones are indicated (OPGC), Central Electricity Supply Corporation Limited
below. (CESCO), Northern Electricity Supply Corporation
Limited (NESCO), Southern Electricity Supply
9. GRID MANAGEMENT AND TRADING Corporation Limited (SOUTHCO), Western Electricity
In order to expand the scope of power trade in the Supply Corporation Limited (WESCO) with an
coming years, it would be necessary to plan a suitable independent regulatory administration i.e. Orissa
tariff structure for the inter-system energy exchanges Electricity Regulatory Commission (OERC) established
which would be attractive to all and that would enable in April 1996 to promote responsibility in the power
best possible operation of the regional systems. The sector and invite the private sector investment in the
obligatory managerial structure at the regional and state.
national level has already been created to encourage
efficient integrated operation in the form of Regional
106 R. Rameshwar, R. Agrawal and M.K. Pathak / International Energy Journal 11 (2010) 101-110
Table 5. Grid performance analysis (provisional) power supply position during the year 2008 and 2007.
Energy
April –September, 2008 April-September, 2007 Annual Growth
Energy Energy Energy Energy Energy Energy
Energy Shortage Energy Shortage
Requirement Availability Requirement Availability Requirement Availability
(MU) (MU) (MU) % (MU) (MU) (MU) % % %
Northern 112256 101877 -10379 -9.2 112841 104925 -7916 -7.0 0.5 -2.9
Western 121322 102405 -18917 -15.6 111480 97924 -13556 -12.2 8.8 4.6
Southern 101753 94580 -7173 -7.0 91228 89236 -1992 -2.2 11.5 6.0
Eastern 41664 39489 -2175 -5.2 37868 36645 -1223 -3.2 10.0 7.8
North
4940 4198 -742 -15.0 4421 3911 -510 -11.5 11.7 7.3
Eastern
All India 381935 342549 -39386 -10.3 357838 332641 -25197 -7.0 6.7 3.0
Peak
April –September, 2008 April-September, 2007 Annual Growth
Peak Peak Peak
Peak Met Peak Shortage Peak Met Peak Shortage Peak Met
Demand Demand Demand
(MW) (MW) (MW) % (MW) (MW) (MW) % % %
Northern 34036 29504 -4532 -13.3 32462 29495 -2967 -9.1 4.8 0.0
Western 37171 27634 -9537 -25.7 36371 26732 -9639 -26.5 2.2 3.4
Southern 27576 25035 -2541 -9.2 25682 24194 -1488 -5.8 7.4 3.5
Eastern 12210 11435 -775 -6.3 11284 10562 -722 -6.4 8.2 8.3
North
1744 1343 -401 -23.0 1589 1347 -242 -15.2 9.8 0.3
Eastern
All India 109962 93046 -16916 -15.4 102428 90022 -12406 -12.1 7.4 3.4
Source: CEA-Vidyut Bharati, October, 2008
Orissa is the first state to have undertaken reform thermal 44.50% and captive generating plants (CGPs)
and restructuring in power sector to build efficient 2.7%.
power supply structure and to meet the investment needs The 17th Electric Power Survey (EPS) has
of the sector. The Orissa Electricity Regulatory (OER) projected peak demand of 4,459 MW at the end of XI
Commission established by the Government of Orissa Plan (2012) and installed capacity requirement of about
under OER Act, 1995 is deemed to be a state 6,778 MW. Energy requirement is projected to grow
Commission u/s 82(1) of the Electricity Act, 2003. from 18,076 MU in 2007-08 to 27,149 MU in 2011-12
The demand for power has been growing [7].
increasingly and to meet the higher demand, necessary
Regulatory Involvement and its Impact
planning for capacity addition is required.
The installed capacity as of 30.06.2007 in the state OERC gave its order on intra-state open access in June
is 3,822 MW out of which hydro constitutes 52.80 %, 2005. Long term (>25 years contract) and short term
(others) customers are specified and the phasing plan is
108 R. Rameshwar, R. Agrawal and M.K. Pathak / International Energy Journal 11 (2010) 101-110
given. Compared to Andhra Pradesh, Orissa has chosen Regulatory Involvement and its Impact
to introduce open access rather slowly, with customers
According to the recent decision made by the
having > 5 MW connected load getting the facility by
government, PSEB is heading towards bankruptcy to
April 2008 and those with > 1 MW by January 2009’
adjust the cash subsidy due to board against earlier
[8].
loans. PSEB was facing a deficit of $ 171.5 million in
Government is also trying to establish Regulatory
the financial year of 2008 but the decision of the state
Information Management System (RIMS) for entering,
government not to give cash subsidy of $300 million to
monitoring, analyzing and exchange of utility data
adjust the earlier loans.
applicable to finance, operation, technical and planning.
In 2000-01, there was a shortfall in power of
Utilities can also seek data on such matters and
12.05% at peak demand and 10.3% in terms of gap
communicate with regulator easily and effectively. between demand and supply. But in the last decade the
Additionally, establishing unique Integrated Tariff average rate of growth on demand of electricity had
Module (ITM) and interfacing the same with RIMS. been 6%. Around $0.06 was the average cost of power
Private Sector Generation supply per unit in Punjab recorded in the year 2001-02,
which was among the lowest rate in India [3], [9]. PSEB
It is mentioned that Calcutta Electric Supply was not rewarded for this reduction in cost of supply by
Corporation (CESC), Kolkata discussed with the the government. Thus, the fiscal position of the board is
Government of Orissa for setting up 2,000-MW power unstable with sickness.
plant (coal-based) around Talcher at a cost of $171.5
Private Sector Generation
billion.
However private player viz. Jindal Steel and Power PSEB recently launched an important initiative for
(JSPL) has revised its contract with the State Rajpura power plant with the contracted generating
Government to increase the capacity of the proposed capacity of 1,200 MW ± 10% (1,080-1,320 MW) coal
plant and also took the new steps to set up a 900 MW based thermal power plant at Nalash village, near
captive power plant [8]. Rajpura, District Patiala, Punjab.
As per the Ministry of Power (MoP), Government
Private Sector Distribution
of India’s guidelines, the project will be given to a
Reliance Energy took over the management of the three developer on the basis of tariff based competitive
district distribution companies; BSES in 2001 had issued bidding. Accordingly, Nabha Power Limited (NPL)
bonds worth $85.8 million at a 12.5 % interest in favour invites the proposals for the same.
of GRIDCO to cover its arrear dues. New thermal power plant at Gidderbaha (2400
GRIDCO, while securitizing its past dues of $236.4 MW ± 10%) has been proposed in the state near Village
million to NTPC, had pledged the BSES bonds to Ghagga, Tehsil Gidderbaha, District Muktsar on
NTPC. The other companies such as Tata Power, AEC- Bathinda-Abohar National Highway and the information
Ahmadabad, NTPC, and CESC have also shown interest for bidders have been provided. The selection of the
in private distribution network [8]. project developer will on the basis of tariff based
competitive process as per the government guidelines.
THE CASE OF PUNJAB STATE
Private Sector Distribution
State Overview
With recent updates, private participation in distribution
The Punjab State Electricity Board (PSEB) is a
under the PPP approach is the best decision because
constitutional body formed on 1st Feb.1959 under the
private managements may lead in professional
Electricity Supply Act. 1948. The board’s net generation
efficiency and bring the required investments.
during the year 2006-07 was 36,412.055 MU. This
The Punjab Government has ambitious plans to
board is serving T and D network to more than 19,172
build a wide distribution network for power in
km2 consumers comprising of 15,843 km2 general, 336
association with private players. It is assumed that PSEB
km2 industrial and 2,791 km2 agricultural connections
is in the process of developing a comprehensive plan for
approximately [8], [9]. Punjab has given approval for
T and D.
20.78 % of its budget to be spent on the energy sector in
2007-08. THE CASE OF UTTAR PRADESH STATE
The state put emphasis on reducing the T and D
State Overview
losses and take full advantage of the utilization of
existing capacities, adopting non-conventional sources On January 14th, 2000, UP Power Corporation, UP State
for power generation and the increase of captive power Power Generation and UP Hydel Power Corporation had
plants. Total installed capacity in Punjab in 1990-91 was been formed by re-organising UP State Electricity Board
3,049 MW, which increased to 4,626 MW in 2006-07. (UPSEB). At the time of inception the total installed
Per capita consumption of electricity in the state is capacity of UPSEB, including thermal and hydro, was
940kWh, nearly 2.5 times the all India number of 2,635 MW which has now been raised to 4,621 MW.
390.3kWh. However, MoP has further pointed out that the amount
of $137.3 million that has already been released to UP
under 'Accelerated Electrification of 308 km2 area
villages and 30,769 km2 of houses, now merged with
R. Rameshwar, R. Agrawal and M.K. Pathak / International Energy Journal 11 (2010) 101-110 109
Rajiv Gandhi Grameen Vidyutikaran Yojana, needs to SERC and should also not involve itself in the day-to-
be utilized in the first instance before any further day operations of the SERC.
allocations could be made [8]. These regulatory institutions should have sufficient
Since 2005, a total of $1,072 million has been funds, manpower, technology and authority to regulate
sanctioned for rural electrification during the 10th plan the public-private mix experiment in the power sector.
and $2,358 million could be availed in the 11th plan
based on the performance of UPSEB.
ACKNOWLEDGEMENT
Regulatory Involvement and its Impact
The authors acknowledge and extend thanks to the
The UP Power Corporation is of the view that the Ministry of Power (MoP), Central Electricity Authority
average cost of supply of power is $0.09 per unit while (CEA), National Power Training Institute (NPTI), etc.
the average selling cost is only $0.06 per unit. After the for their continuous help in all aspect for providing
five years of the reforms in the power sector, the power data, was particularly helpful in the development
financial position of the UPPCL remains precarious. of the work. Special gratitude is also expressed to
According to the financial year 2004-05, cash losses of anonymous referees for their efforts, valuable comments
the UPPCL were $592 million, which too after it and suggestions.
received a subsidy of $215 million from the state
government [8].
REFERENCES
The UPERC has declared the Electricity Supply
Code for the improvement of the situation which [1] Bansal R.C. and Hammons T.J., 2007. A Discussion
contains all aspects related to consumer services, billing on the Restructuring of Indian Power Sector. IEEE:
and connections. University of the South Pacific. Suva, Fiji. pp. 01-
06.
Private Generation and Distribution
[2] Government of India, 2008. Annual Report. New
According to the New Tata Projects, there are reports of Delhi/India: Ministry of Power and Central
Tata Power Company’s (TPC) strategy to setup thermal Electricity Authority.
and hydro power projects in the state. [3] Sharma Dhiraj, 2007. India’s State Electricity
Also, TPC has decided to set up a 600 MW hydro Boards (SEBs): An Efficiency Perspective. Indian
power plant near by Shrinagar. This project worth of all Management Studies Journal: 127-148.
processes including rehabilitation, land and building a [4] Government of India, 2008. Annual Report. New
dam is expected to be around $322 million. A new 1,000 Delhi/India: Power Grid Corporation India Limited.
MW capacity thermal power plant at Bawana near [5] U.S. Energy Information Administration, 2008.
Singrauli is also proposed by TPC to the state Country Analysis Briefs – India [On-line serial],
government [8], [9]. Retrieved August 15, 2009 from the World Wide
Web: http://www.eia.doe.gov/cabs/India/Backgroun
10. CONCLUSION d.html
[6] Pramod, D. and M. Shrikant, 2005. Electricity
All the Indian SEBs without exception are on the edge
Reforms & Green Power Development Regulatory
of economic failure due to restricted tariff policies, low
and Tariff Issues. Pune, India: WISE Publication.
capacity utilization of existing plants and high incidence
[7] Government of India, 2007. Annual Report.
of thefts. Re-establishment of financial health of SEBs
Bhubaneshwar, India: Orissa Electricity Regulatory
and the development in their operational performance is
Commission.
one of the most critical issues in the power sector.
[8] Prayas Energy Group, 2005. [Review of the book
This is only possible through organizational
on: India Power Sector Reforms Update, Prayas:
restructuring of SEBs. Accordingly, the only solution is
Pune]. Studies in Energy, Issue-11, 1-36.
the unbundling of each SEB into separate generation,
[9] Government of India, 2008. Annual Report. New
transmission and distribution utilities, rationalization of
Delhi/India: Planning Commission.
tariffs, setting up independent regulators at the central
[10] Anjali, G., Manisha, K. and Rakesh, K., 2003.
and state levels and for clearing their growing dues with
Regulatory reforms in India: effectiveness,
central utilities. State like Orissa, Punjab, Uttar Pradesh
efficiency and impacts. New Delhi, India: TERI-
and few have already unbundled and corporatized their
UNDP.
SEBs. Other states are expected to carry out reforms
[11] Sudipta, G., 2002. Restructuring power sector for
soon.
efficiency: Need of the hour. Department of
The CERC should use its provisions under section
Commerce and Farm Management. Midnapore:
36 for fixing fair and reasonable rates for the use of
Vidyasagar University, pp.1-4.
intervening facilities in case of open access users by
[12] Hansuttam Finance Ltd., 2005. Overview of Power
formulating new regulations.
Sector in India. New Delhi: HFL, pp. 03-24.
Also, CERC should exercise its powers under
[13] Prayas Energy Group, 2004. [Review of the book
Section 61 to guide the state commissions by prescribing
on: India Power Sector Reforms Update, Prays:
principles and methodologies for determining tariffs
Pune]. Studies in Energy, Issue -8, 1-43.
applicable to generating companies and transmission
lines. Government should ensure the effectiveness of the
110 R. Rameshwar, R. Agrawal and M.K. Pathak / International Energy Journal 11 (2010) 101-110
[14] Kannan, K.P. and P.N. Vijayamohanan, 2000. [18] Pradeep, S.K., 2001. Ethics in Innovation- Power
Plight of the Power Sector in India: SEBs and their (Electricity) Sector Reforms in India. Special
Saga of Inefficiency. In Working Paper No. 308. Reference to the Rajasthan State. Jaipur: India, pp.
Thiruvananthpuram, India: Centre for Development 06-16.
Studies: 08-35. [19] Anoop, S., 2007. Policy Environment and
[15] Subhash, M and Bansal N.K., 2006. Sectorial Regulatory Reforms for Private and Foreign
Analysis for Electricity Demand in India. Shri Mata Investment in Developing Countries- A Case of the
Vaishno Devi University, Katra/India: SMVDU: 1- Indian Power Sector. Kanpur/ India: ADB Institute
10. Discussion, Paper No. 64.
[16] Ajay, P., 2004. Review of the India Infrastructure [20] Bhupendra, S.K., 2008. Energy Security and India-
Report - Reforms in Electricity-Tariff Policy in the China Cooperation. New Delhi/India: Ministry of
Electricity Sector: A Review. New Delhi: India: External Affairs, pp. 01-10.
152-195. [21] TERI, 2005. Fortnightly News abstracts on
[17] Jagdish, S., 2003. Power Sector Reforms In Delhi- economy, energy and environment. Vol. 1. New
The Experience So Far. New Delhi: India, pp.05-22. Delhi: Newswire.