1-Introdution and Route Desgin
1-Introdution and Route Desgin
Dasharatha Achani
MECHOCEAN
Eng. Solutions
9-Aug-16
9-Aug-16 Page 2 www.mechocean.com Dasharatha Achani
MECHOCEAN
Course content Eng. Solutions
Design Overview
Route Selection
Pipeline Hydraulics
Structural Design of pipeline
Fabrication, Welding and ECA
Stability
Span assessment and correction
Upheaval and Lateral Buckling
Pipeline construction and installation
Riser Design
Text Book:
• Subsea Pipeline Engineering, by Andrew C. Palmer & Roger A.
King
• Subsea Pipelines and Risers, BY Yong Bai AND Qiang Bai
Shallow water
Deep water
Very deep water
Ultra deep water
9-Aug-16 www.mechocean.com Dasharatha Achani
MECHOCEAN
Elements of Subsea Production Systems Eng. Solutions
Process facilities
Risers
Protection structure
Control umbilical X-mas tree
Riser base Flow lines
Template
Riser Installation
(Steel/Flexible)
J-Tube Installation
Umbilical
Reel lay
Flowline
(Steel/Flexible)
Installing Flowlines
Subsea Isolation
Valve (SSIV)
Courtesy of Shell
Manifold
Images
9-Aug-16 courtesy of Acergy Australia
www.mechocean.com Dasharatha Achani
MECHOCEAN
Subsea Controls and Valves for high reliability Eng. Solutions
Subsea Controls
Courtesy
9-Aug-16 of Cameron valves
www.mechocean.com Dasharatha Achani
MECHOCEAN
Flowline Jumpers (Tie-in Spools) & Diverless Connectors Eng. Solutions
Flowline Jumper
(Flexible)
CHRISTMAS TREES
Subsea Protection
(Rockdump/Mattresses
etc.)
Pipeline Crossings
Subsea
Concept and
processing systems design, Electric power
supply/distribution
operations/control
Marine
Operations, Multiphase flow
Process technology surveillance,
operations technology
inspection
Environmental technologies
Detail engineering
Feasibility Study
Commissioning
Screening Study Operation
Construction
Procurement
Installation
Fabrication
Concept Stduy Maintenance
Hook-up
Pre-engineering or FEED
•Document that a •Identify all relevant •Develop and mature •Further mature and •Further develop,
business opportunity alternative facilities the selected ultimately freeze the detail and specify
or a hydrocarbon & concepts and assess concepts. selected concept for technical solutions
discovery is relevant new •Evaluate and select project sanction established in the
profitable, and that technologies commercially available •Negotiate potential FEED to the level of
technically feasible •Evaluate facility processes (relevant technology purchase detail required for:
facilities concepts do alternatives and for onshore) agreements purchasing
exist establish shortlist of •Select concept and (relevant for onshore) fabrication
•Document that the concepts provide a firm design construction
appraisal status and basis for FEED installation/hook-up
subsurface data are
adequate for start of commissioning
concept studies operation
•Establish a realistic
schedule for the
project planning phase
contractors company
Engineering Procurement
contractors contractors
Equipment
contractors contractors
9-Aug-16 www.mechocean.com Dasharatha Achani
MECHOCEAN
Types of pipelines Eng. Solutions
Trunk pipelines
• Crude export
• Gas export
• Usually large diameter pipelines
Infield pipelines
• Production
• Gas Injection
• Water Injection
Pipeline route
Pipeline design
• Flow issues – Pipe size
• Pressure & temperature – Wall thickness
• Corrosion protection
• Coatings – Corrosion protection, thermal insulations and
impact protection
Linepipe selection
Installation issues
On-bottom stability
Upheaval and lateral buckling
Freespan and correction
Routing Design
9-Aug-16
9-Aug-16 Page 29 www.mechocean.com Dasharatha Achani
MECHOCEAN
EXPECTATION Eng. Solutions
Seabed obstructions
Seabed features
Construction limitations
Platforms
Wells
Wrecks
Pipelines
Cables
Fixed items
• Minimum clearances
DNV 2000 - 500 m (1640 ft)
API 1111 - 91 m (300 ft) (guidance)
FPSO & semi-sub drill rig
Anchor spread typically
~2 km (1.2 mile) radius
Other countries
Exclusion zones
Dredging areas
Shipping lanes
Other companies’ acreage
Fishing grounds
SAC ( Special areas of conservation)
Rocks
Sandwaves
Pock marks
Mud slides
Mud volcanoes
Iceberg scars
Mobile sandwaves
Route along troughs
Lower pipeline to trough level - pre-sweep
Shore approach
Platform approach
Pipeline crossing
Bend radius
Trenching
Laybarge draught
• 3rd generation typically 12 m (40 ft)
Perpendicular usually gives shortest beach pull
Environmental wave loading is minimised
Beach pull
• Trenching is preferred
Tunnel pull
• Expensive option
Horizontal drilling
J-tube riser
Pipeline pulled directly into platform
Vessel does not pass platform
No dog-leg spool
Route influenced by
Obstructions
• e.g. platforms, wells, shipwrecks, cables, pipelines
Seabed features
• e.g. rocks, sandwaves, mud slides
Other users of seabed
• e.g. exclusion zones, dredging, shipping lanes, fishing, SSSIs
Limitations of construction equipment
• e.g. shore and platform approach, crossings, trenching
Route survey
Feasibility Study
Desk Study
Conceptual design
SANCTION
Offshore survey
FEED
Detail design
Pre-lay As-built
Construction
Time
Cost effective
One day offshore = 8 weeks for an engineer
Reports:
Types of soil or rock at or below seabed
Thickness of layers
Engineering characteristics
• Density
• Porosity
• Strength
ALIGNMENT SHEETS
Definition:
A drawing which illustrates a length of pipeline – typically 2 km to 3 km
(1.2 miles to 1.9 miles) – and which indicates key features
Purpose:
Provides the information required to produce the material take-off (MTO)
Summarises key information required to installation contractor
Seabed features
Boulders / shipwrecks
Survey data ( soils information etc.)
Installation data
Pipelay tolerance
Lay tension
Crossings
Backfill requirements
Pipeline properties
Curvatures and tangent points (TP)
Concrete and / or corrosion coating
Wall thickness
Buckle arrestor spacing
Field joint details
Anode spacing
Fittings
9-Aug-16 www.mechocean.com Dasharatha Achani
MECHOCEAN
ALIGNMENT SHEETS - SUMMARY Eng. Solutions
Routing Design
Curve Stability