Protection Scheme For 132kV and 22kV Busbar Configurations PDF
Protection Scheme For 132kV and 22kV Busbar Configurations PDF
Abstract – New 132kV and 22kV GIS / Insulated busbar configurations will be adopted for HK
Electric’s MRS Substation. Unit busbar protection is used to ensure prompt and discriminative
isolation of the faulty busbar and to minimize the supply interruption to customers. Traditional
high impedance differential protection is applied as main protection for the busbars of the new
132kV and 22kV busbar configurations because it is simple, reliable and well-proven in HK
Electric
This paper describes a non-conventional design of the busbar protection system for the new 132kV
busbar configuration with an aim to enhancing the protection availability while maintaining
adequate selectivity and discrimination. For the new 22kV busbar configuration, special features
like feeder common overcurrent and earth fault (OCEF) protection, rough balanced back-up OCEF
protection and cross-tripping of bus-interconnector circuits are introduced to minimize the impact
of abnormal conditions such as protection / circuit breaker failure during fault in the 22kV system.
Keywords: Unit busbar protection, High impedance differential protection, Feeder common
OCEF protection, Rough balanced feeder / Busbar backup OCEF protection, Cross-tripping of
bus-inerconnector
1. INTRODUCTION
sections describe the protection schemes to be used at these The reliability of the busbar isolator has always been a
two new substations with new busbar configurations. concern for GIS with double-busbar configuration because
a single busbar isolator fault may lead to the loss of two
busbars, or half of the substation load for a 4-busbar GIS.
It was decided in the design stage to take a prudent
2. MRS 132KV SWITCHING STATION
approach in adopting a 6-busbar design for MRS 132kV
The new MRS 132kV Switching Station injects power to Switching Station. Any busbar isolator fault in this new GIS
the existing 132kV transmission network in Wan Chai area configuration will at most affect 1/3 of the substation.
so as to relieve the load congestion in adjacent areas. Due
to the crucial role and special location of this switching 2.2 BUSBAR PROTECTION FOR MRS 132KV GIS
station, it was decided to adopt a design with higher fault
tolerant capability for the 132kV busbar configuration and In HEC system, fully duplicated busbar protection
the associated busbar protection. systems of different operating principles with fault
clearance time within 0.14s are employed as a standard
arrangement in transmission substations to clear a busbar
2.1 MRS 132KV GIS BUSBAR CONFIGURATION fault. The burn through time of 0.5s is stipulated for the
GIS because of the following considerations:
MRS 132kV Switching Station comprises a 6-busbar GIS
with 20 bays (viz. 12 outgoing circuits, 2 275/132kV
i. For the best dependability, a 132kV GIS is usually
interbus transformer circuits, 4 bus-sections and 2 bus-
protected by two independent busbar protection systems
couplers) in double-busbar configuration as shown in Fig. 1.
(namely the 1st and 2nd Busbar Protection), each
Mai n 1 Main 2 Main 3
comprising check zone and discrimination zone
protections. Tripping of a busbar will be initiated by a
R eserve 1 Rese rve 2 Reserve 3 busbar protection system if both its check zone and
discrimination zone protections detect a busbar fault.
HEC
Requirement for IEC Requirement
22kV distribution network in Wan Chai area. Similar to
Existing GIS MRS 132kV Switching Station, most manufacturers only
Standard requirement extracted from IEC62271-203:
offer 3-position switches as their standard products in 22kV
Rated short
Protection Duration
circuit
stage of current
Performance criteria class GIS. Therefore, the reliability of the busbar isolator is
current
The enclosure s
hould be able t No external effect other than
also a concern to 22kV GIS since a busbar isolator fault
o withstand, wi
thout burning t < 40kA
1 0.2s the operation of suitable
pressure relief device.
will lead to tripping of the respective busbar causing
r.m.s.
hrough, an inte
rnal arc fault o 2 0.5s
No fragmentation (burn- significant supply interruption to the customers.
through is acceptable)
f 40kA r.m.s. o
f not less than No external effect other than
In order to achieve world class electricity supply [2],
0.5s.
40kA
1 0.1s the operation of suitable
pressure relief device.
typical 22kV closed-ring network [3], [4] similar to other
r.m.s.
No fragmentation (burn- 22kV zone substations in HEC is adopted in principle with
2 0.3s
through is acceptable)
enhancement on the 22kV busbar configuration to allow
better fault tolerant capability. Details of the protection
However, most European suppliers can only provide GIS schemes for the new busbar configuration are described in
in accordance with the IEC requirements. In order to the following sections.
ensure that at least one of the busbar protection systems can
operate within 0.14s under all circumstances so that the
3.1 MRS 22KV BUSBAR CONFIGURATION
standard IEC requirement of 0.3s can be adopted in the new
system, the following design of the 2nd Busbar Protection
system using high impedance differential principle is MRS Zone Substation is equipped with 4 x 50MVA
adopted: - 275/22kV zone transformers. To improve the fault
tolerant capability of the zone substation, the 22kV winding
i. Installing additional check zone protections so that each of each zone transformer is connected to two 22kV busbars
pair of main and reserve busbars will have its own check
via separate incomer cables. As a result, in total there will
zone protection, instead of one check zone for the whole
GIS. This will require additional check zone CTs on the be eight 22kV busbars which are connected in ring
bus-section circuits but the overall size and capacity of configuration via bus-interconnector cables. The rating of
the 132kV GIS are not affected. the 22kV busbars, incomer cables and bus-interconnector
cables is 1250A. Fig. 3 shows the simplified 22kV busbar
ii. Modifying the trip logic so that the check zone configuration of MRS Zone Substation.
protection alone can initiate the busbar tripping to clear
the busbar fault if the discrimination zone protection is Tx 1 Tx 2
protection alone can initiate the busbar tripping to clear B/I 8-1 B/I 4-5
the busbar fault if the check zone protection is locked B/I 7-8 B/I 6-7 B/I 5-6
Busbar 8 Busbar 7 Busbar 6
out, say due to open circuit of check zone CT wiring.
Busbar 5
due to 22kV busbar fault can be avoided, if the two source intentionally delayed by some tens of milliseconds. For
ends of a closed-ring feeder pair are connected to the two calculation of the appropriate CB opening time, please refer
busbars being fed by the same zone transformer. to IEC62271-100 (previously IEC60056) “High-voltage
It should be noted that connecting the two ends of the switchgear and controlgear – Part 100: Alternating-current
closed-ring feeders to different transformers should be circuit-breakers”.
avoided because unwanted load transfer current from one
busbar to another may flow in the closed-ring feeders under
3.2.2 22kV Single-Phase-To-Earth Fault
certain busbar configurations with possible overload of the
feeder cables. In addition, extreme care should be exercised As the 22kV windings of the zone transformer are delta-
during busbar reconfiguration and / or parallel switching of connected, a zig-zag connection earthing transformer
22kV feeders to avoid parallel operation of multiple Z/Tx’s connecting in series with a neutral earth resistor is installed
through the additional interconnections amongst busbars / on the 22kV side of each zone transformer to allow single-
substations in order to contain the 22kV fault level to the phase fault current to flow; otherwise, the earth fault
fault rating of primary equipment. protection may not be able to detect an earth fault in the
22kV system effectively. The combined impedance value
of the earthing transformer and neutral earth resistor is so
3.2 22KV FAULT LEVEL selected that the earth fault current should be kept below
3.2.1 22kV 3-Phase Fault the full load current of the zone transformer while it should
be sufficiently large to drive the protection systems to
22kV 3-phase fault level largely depends on the zone
operate firmly. In addition, this earthing design ensures
transformer impedance and the number of zone
that any 22kV single-phase-to-earth fault in the system
transformers operating in parallel. Besides, the 22kV fault
shall not cause a voltage dip in the LV supply to customers
level will also be affected by the system voltage, zone
exceeding 10% (i.e. voltage retained 90%).
transformer tap position and cable length to the fault point.
It is worth mentioning that most of the 22kV primary live
For safety reason, the 22kV system fault level must not
conductors (except those in the gas tank of GIS) are
exceed the 22kV switchgear’s short-time withstand
screened by earthed layer. Should they be interfered with
capability and fault breaking capacity (i.e. 25kA).
or the insulation break down, a 22kV single-phase-to-earth
To meet the system operation requirement, the
instead of phase fault is most likely to occur. With such
impedance of the 275/22kV zone transformer at MRS Zone
design, voltage dip caused by most 22kV fault, i.e. single-
Substation is carefully selected in the design stage so that
phase-to-earth faults, will have little impact (i.e. 10%
the maximum 22kV fault level will not exceed the 22kV
switchgear’s fault rating even when three zone transformers voltage dip) to the LV customers.
are connected in parallel. In addition, the advanced
Distribution Management System (DMS) in HEC’s System 3.3 PROTECTION ARRANGEMENT
Control Centre will continuously monitor the fault level of
the distribution network. Protection arrangement for MRS 275/22kV Zone
On the other hand, the minimum 22kV fault level may Substation is illustrated in Fig. 4 and detailed design is
occur if a zone transformer is in single operation which is described in the following sections.
very unlikely during normal operation mode. Protection
systems shall be designed to cater for all possible busbar
Transformer 1
transformer. To ensure that the 22kV CB will not be P ilot DIR PF I / E F I Pilot
W ire W ir e
New 132kV and 22kV busbar configurations with C.W. Chiu is a Corporate Member of
higher fault tolerant capability are adopted at MRS 132kV the Hong Kong Institution of Engineers.
Switching Station and MRS Zone Substation respectively to He joined the Hongkong Electric Co.,
render a better supply security. The paper briefly introduces Ltd. in 1979 and has been working with
the protection schemes which are designed to suit the new the Protection Section of the Technical
busbar configurations as well as to cope with the withstand Services Department under the T&D
capability of the switchgear to IEC62271-203 for 132kV Division as a Protection Engineer since 1995.
and IEC62271-100 for 22kV. MRS 132kV Switching
Station was energized successfully in early March 2010
while the commissioning of MRS 275/22kV Zone K.W. Yeung received his B.Eng.
Substation is scheduled for August 2010 tentatively. As the degree and M.Sc. degree in electrical
protection schemes at MRS 132kV Switching Station and engineering from The University of
275/22kV Zone Substation employ proven protection Hong Kong. He joined the Hongkong
principles but with some improvements, it is expected that Electric Co., Ltd. in 1995 as a graduate
the reliability of the protection schemes will increase when trainee. He is currently a Protection
compared with the conventional design at other existing Engineer in the T&D Division of the
substations; however, the actual protection performance Company and a Corporate Member of the Hong Kong
will be reviewed after gaining more operating experience in Institution of Engineers.
the coming years.
5. ACKNOWLEDGEMENT