Methodologies For The Analysis of Both Short-Term and Long-Term Network Risk
Methodologies For The Analysis of Both Short-Term and Long-Term Network Risk
Paper 0024
Paper 0024
and Hanson, in a seminal paper, compare ‘four common Figure 1 – Case Study Network Configuration
methodologies used for distribution reliability assessment’ There are a number of options for carrying out the project,
[6]. Standard textbooks describe all four in detail, and apply such as whether to rebuild in situ or on an adjacent green
them to power systems [7]. The choice of methodology for field site. The in situ solution costs less, but could involve
the present research was described in detail in a previous longer circuit outages and consequently a greater risk.
paper by the present authors [8]. The decision was made to
use Analytical Simulation, supplemented where appropriate The rebuilt NP would have an expected lifetime of at least
by the other three approaches (Network Modelling, Markov 40 years, and this raises questions as to whether the
Modelling, and Monte-Carlo Simulation). The approach was straightforward replacement of the existing configuration is
illustrated in that paper by three different case studies taken the best solution to those challenges to network reliability
from within the CE Electric UK network. that are likely to arise over the next 40 years. One option
concerns a separate 132 kV double circuit, not shown in
132 KV CASE STUDY Figure 1, which feeds two other loads from a different GSP,
but which passes within a few metres of the NP. It would be
Figure 1 shows the network around a nodal point (NP), relatively straightforward to connect this double circuit into
which is a 132kV switching station whose aged assets are the NP by the installation of additional switchgear, but the
due for replacement. The network operates as a closed ring cost of doing so and the customer benefits delivered need to
and whilst load D (at Substation D) is clearly supplied via be understood. The additional interconnection would give
the nodal point, network studies indicate that a proportion of an extra supply option for all six loads, thereby increasing
load B is also supplied via the nodal point under normal network flexibility and possibly overall reliability, and has
operating conditions. Load A, load C and the remainder of been included as part of the construction project.
load B are supplied directly from Grid Supply Point (GSP).
Double circuits are used throughout this part of the network. Conversely, it could be possible to eliminate NP from the
Dotted lines indicate underground cable, solid lines indicate network altogether. Figure 2 shows a possible
overhead lines, and X indicates a circuit breaker. The reconfiguration which does this. This would cost
replacement of the assets at the nodal point is a major significantly less than the replacement of NP, and leave a
construction project, expected to last over two summer simpler network, although one with rather fewer operational
seasons (when UK demand is lowest), and to cost around options and possibly with an increased level of risk.
£8M. During construction works, principally when
transferring circuits from the old equipment to the new, one However, the biggest issue in rebuilding for the next 40
or more circuits will be out of service, and consequently the years concerns challenges which can perhaps only be
risk to customer supplies during these periods will increase. qualitatively perceived at present. These challenges could
include global warming, greater levels of distributed and
renewable generation, demand side management, smart
grids, active network management, and restructuring of the
industry. Any solution adopted for the rebuilding or
replacement of NP must at least attempt to address some or
all of these challenges.
Paper 0024
Paper 0024
To do this, a separate modelling technique was devised, to possible intermediate solution, in terms both of capital cost
measure the robustness or resilience of the network to cater and of network risk. Scoring it by this methodology gives an
for a number of possible future scenarios. For initial trial of average vulnerability index of 52, an intermediate value.
this technique, a list of 10 such scenarios was used, as
shown in Table 1. Each of the six loads was assessed under CONCLUSIONS
each of the 10 future scenarios, and scored on a scale from 0
(no vulnerability) to 10 (extremely vulnerable). The level of risk inherent in electricity distribution networks
is perceived to be increasing in the short term and still more
Scen- Description in the long term. Several investment options are available to
ario mitigate that risk, including renewal or reinforcement of
assets, reconfiguration of the network, and more radical
1 Loss of two incoming circuits on one 132 kV tower
operating solutions including various kinds of active
2 Loss of two incoming circuits due to cable damage
network management. Choosing the most cost effective of
3 Loss of some or all busbars due to fire or flood
these options is the responsibility of managers, who need
4 Restricted supply from normal GSP (say to 50%)
appropriate ways of measuring and ranking network risk in
5 Increased failure rates of ageing assets order to make informed decisions. This paper has described
6 Political sensitivity of customers to loss of supply and illustrated by case study two such measurements, a
7 Location: vulnerability to weather or damage short-term one using expected annual £k, and a longer term
8 Amount and intermittency of connected generation one using a vulnerability index.
9 Amount and complexity of active network mgt.
10 Sensitivity to a tighter regulatory environment REFERENCES
Table 1 – Future scenarios assessed for vulnerability [1] L.A. Freeman, D.T. Van Zandt, L.J. Powell, 2005,
"Using a Probabilistic Design Process to Maximise
The results of such analysis have to be regarded as Reliability and Minimise Cost in Urban Central
provisional at this stage. For more reliable results, a greater Business Districts", Proceedings, CIRED 18th
amount and variety of expert knowledge would need to be International Conference on Electricity Distribution.
incorporated, to determine [2] J.G. Slootweg, P.M. Van Oirsouw, 2005, “Improving
• Whether the list of possible scenarios was realistic Reliability Calculations in Routine Network Planning:
and exhaustive Theory and Practice”, Proceedings, CIRED 18th
• Whether each scenario should be equally weighted International Conference on Electricity Distribution.
(on a score of 1 to 10), or whether some should [3] M. Oravasaari, J. Pylvaneinen, J. Jarvinen, A.
carry a greater weighting than others, and Maniken, P. Verho, 2005, “Evaluation of Alternative
• What the likely level of vulnerability would be, for MV Distribution Network Plans From Reliability
each load under each scenario Point of View”, Proceedings, CIRED 18th
The provisional results are, nonetheless, interesting. As a International Conference on Electricity Distribution.
base run, the existing network was evaluated for future [4] R.E. Brown, J.H. Spare, 2004, “Asset Management,
robustness. For each load, the 10 vulnerability scores were Risk and Distribution System Planning”, IEEE PES
summed to give a score out of 100. The range was from 37 Power System Conference and Exposition.
(for Load A, the most robust and least vulnerable) up to 52 [5] D.E. Nordgard, K. Sand, O. Gjerde, M.D. Catrinu, J.
for load C (the least robust), giving an average vulnerability Lassila, J. Partanen, S. Bonnoit, J. Aupied, 2007, “A
score of 45 out of 100. Risk Based Approach to Distribution System Asset
Management and a Survey of Perceived Risk
With the less robust configuration of Figure 2, these scores Exposure Among Distribution ompanies”,
increase to give a range from 51 (Load A) to 66 (Load D), Proceedings, CIRED 19th International Conference on
with an average of 56 out of 100. This increase in Electricity Distribution
vulnerability could be used by CE Electric UK management [6] R.E. Brown, A.P. Hanson, 2001, “Impact of Two-
to assess whether the long term risk incurred by simplifying Stage Restoration on Distribution Reliability”, IEEE
the network was acceptable. This would require familiarity Transactions on Power Systems, pp 624-629.
with using the vulnerability index, and confidence in its [7] R. Billinton, R.N. Allan,, 1996, Reliability Evaluation
reliability as an index of risk. of Power Systems, 2nd Edition, Plenum Press, New
York and London.
The vulnerability index could also be used to assess other [8] S.R.Blake, P.C. Taylor, A.M. Creighton, 2008,
possible configurations. For example, a network without “Distribution Network Risk Analysis”, MedPower 6th
NP, but with four circuits instead of two at Load B and an Conference 2008.
additional busbar on the 132 kV side of Load B, would be a [9] www.solver.com/risksolver