CPM Analysis (Critical Path Method) PDF
CPM Analysis (Critical Path Method) PDF
Second. If activity (X) 8-day activity added as a predecessor of activity F, does it change the CP?
Third. Top management asked you to shorten the project time to be 50 days, what does it
mean for your project?
Fifth. If your resource Ahmed is the sole resource to execute C & D, how does it change
project schedule, if you know that all these tasks (C & D) need a full-day effort from Ahmed?
Answers (1)
Third. TF = -8 , no room
Fourth. No changes at CP
Fifth. CP ,still, equals 58 (dependency based on common resources Ahmed, resource- leveling)
Exercise (2)
Find the critical path of the following project:
ID Activity Duration Predecessors
2 A 2 days
3 B 3 days A
4 C 4 days A
5 D 5 days A
6 E 6 days B FS+4 days, C,D
7 F 6 days B,C,D FS+3 days
Solution (2)
By Tables:
ID Activity D(Days) Predecessors ES EF LS LF TF
2 A 2 12/1/2009 12/2/2009 12/1/2009 12/2/2009 0 days
3 B 3 A 12/3/2009 12/5/2009 12/4/2009 12/6/2009 1 day
4 C 4 A 12/3/2009 12/6/2009 12/7/2009 12/10/2009 4 days
5 D 5 A 12/3/2009 12/7/2009 12/3/2009 12/7/2009 0 days
6 E 6 B FS+4 days, C,D 12/10/2009 12/15/2009 12/11/2009 12/16/2009 1 day
7 F 6 B,C,D FS+3 days 12/11/2009 12/16/2009 12/11/2009 12/16/2009 0 days
By PDM:
3 3 5
4 1 6 FS(4) 10 6 15
1 2 2 3 4 6 11 1 16
A C
1 0 2 7 4 10 11 6 16
F
3 5 7
FS(3)
11 0 16
D
3 0 7
CP is ADF = 16 days
Exercise (3)
Solution (3)
3 3 5
3 0 5
1 2 2 10 2 11
A FF(4) D
1 0 2 10 0 11
6 4 9
6 0 9
CP=ABCD = 11
ID Activity Duration Predecessors
2 A 2 days
3 B 3 days A
4 C 4 days A
5 D 5 days A
6 E 6 days B, C,D
7 F 6 days B,C,D