Exercise
Project Budget
The Table below represents the tasks for a project. The labor column is in hours of effort. The labor
rate is $80/hour. The purchase column is from supplier’s quotes. The start and finish columns
represent the planned start and finish date for each activity. Create a project budget and determine
how much money is planned to be spent in each month.
# Labor Purchase Start Finish
Task 1 30 hours Feb 15 Feb 28
Task 2 80 hours Feb 20 Mar 1
Task 3 50 hours Mar 2 Mar 14
Task 4 10 hours $100,000 Mar 15 Mar 31
Task 5 100 hours Mar 15 Mar 31
Task 6 45 hours $350,000 Mar 15 Mar 31
Task 7 60 hours Apr 1 Apr 19
Task 8 210 hours Apr 20 Apr 27
Task 9 140 hours Apr 10 May 2
Task 10 90 hours $50,000 May 3 May 9
Task 11 160 hours May 10 May 22
Task 12 240 hours May 10 May 29
Task 13 200 hours May 10 Jun 7
Task 14 310 hours May 10 Jun 21
Task 15 270 hours Jun 22 Jun 29
Task 16 375 hours Jun 30 Jul 14
Task 17 60 hours $75,000 Jul 15 Jul 31
Task 18 150 hours Jul 15 Jul 31
Task 19 120 hours Aug 1 Aug 9
Task 20 80 hours Aug 10 Aug 25