17-QA-QC Manual
17-QA-QC Manual
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
TABLE OF CONTENTS
Item # Description Page #
Section 1: Project Quality Policy 3
1.1 Statement of Authority 3
Section 2: Introduction 4
2.1 Amendments and Re-issue 4
2.2 Quality Objectives 5
2.3 Terms and Definitions 5
Section 3: Management Responsibility 7
3.1 Quality Policy 7
3.2 Organization 7
3.3 Responsibility and Authority 8
3.4 Personnel and Resources 9
3.5 Management Review 9
Section 4: Quality System Outline 10
4.1 Quality System 10
4.2 Quality System Procedures 11
4.3 Quality System Documents 12
4.4 Contact Review 12
4.5 Document and Data Control 13
4.6 Purchasing 14
Control of Client Supplied and Contractor Supplied
4.7 16
Materials
4.8 Product Identification and Trace-ability 16
4.9 Special Process Control 17
4.10 Inspection and Testing 18
4.11 Inspection and Test Records 19
4.12 Inspection and Test Status 20
4.13 Control of Nonconforming Product 20
Page 1 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
TABLE OF CONTENTS
Item # Description Page #
4.14 Corrective and Preventive Action 21
Control of Measuring, Test and Inspection
4.15 23
Equipment
Handling, Storage, Packaging, Preservation and
4.16 24
Delivery
4.17 Control of Materials and Storage Guidelines 25
4.18 Internal Quality Audits 26
4.19 Audit Planning and Execution 27
4.20 Training 27
4.21 Statistical Techniques 28
4.22 Servicing 29
4.23 QA / QC Reports 29
4.24 Quality Management Report 30
4.25 Inspection Notification 31
4.26 Control of QA / QC Documents 31
4.27 Pre-commissioning Phase Quality Control Activities 32
4.28 Technical Queries 33
4.29 Waivers 33
4.30 Geo-technical / Soil Investigation 33
Compliance to the Client Standards and
4.31 33
Specification
Page 2 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
To achieve this goal the objective measure of these systems and processes
to provide a seamless organization during the prosecution of contracts /
projects undertaken by COST
COST laid down as a basic principle that, the Project construction activities
shall be conducted in accordance with the requirements of the Project
Quality Control Program and will be audited by the COST QA
Manager/management at various stages of the completion as defined in the
project quality assurance program.
____________________
Managing Director (COST)
Date: _______________
Page 3 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
SECTION 2: INTRODUCTION
This quality Plan is set forth to illustrate and specify clearly the general quality
policies, procedures, and practices required for the construction of the
contracts / projects undertaken by the Company.
This Quality Plan was visualized and prepared on the basis of the requirement of
the contract document. It serves as a reference and in line with any other
standards as may be required as a part of the client requirements and COST
Company’s internal QUALITY MANAGEMENT SYSTEM.
This Quality Plan and the work procedures outlined herein describe the COST
company Management System and is thought-out to make sure that quality
necessities are recognized and properly maintained.
The Quality Assurance Department shall periodically review and assess the
Quality Plan with the other departments to re-affirm its sufficiency,
effectiveness and compliance to Client’s quality requirements. The minimum
occurrence for review of the Quality Plan is once every six (6) months.
Amendments to the Quality Plan are made as required to reflect the client
requirements. Amendments are made by replacement of the affected
area(s) and are identified by modification reference and date. Amendments
are numbered one after the other until all the changes are incorporated..
Whenever the Quality Plan is revised, affected sections are superseded with
revised one and shall be removed and destroyed.
The Quality Plan amendment record indicates all the amendments in the
latest issue of the Quality Plan.
Page 4 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
A complete list of Quality Plan holders is retained and any amendments and
re-issue are automatically distributed to all concerned parties.
To ensure that approved methods and procedures are utilized for each
specific work phase of a project.
To minimize rework during the construction period.
To ensure that safety of personnel, the facilities and environment had
been carefully considered and adhered to.
To comply with international and Client codes and standards.
To demonstrate the fulfillment of the contract requirements as stipulated
in contract documents.
To ensure that, quality requirements are determined and satisfied
throughout all phase of the work (procurement, construction and pre-
commissioning phases).
To ensure that approved procedures, inspection and test plans,
management review and audit program are in place and utilized
throughout all work phases.
To provide means for early and prompt detection of deficiencies and its
timely and effective corrective action.
Hold point: work will be held until the inspection or test has been
satisfactorily completed.
Page 5 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
Quality Manual: a document stating the quality policy and describing the
quality system of an organization
Page 6 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
3.2 Organization
3.2.2 Resources:
Page 7 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
3.3.1 The Project Manager has the overall authority and responsibility
for executing the project successfully in time. His duties and
responsibilities includes but not limited to the following;
Representation to the Client for all matters related to the
contract.
Overall management of the project activities and control of
related personnel.
Coordinate with client and Head office with foreseen look
ahead plan to complete the task in a right time and in a
right manner.
Implementation of any step required to prevent delays,
budget overrun and conditions adverse to quality
objectives.
3.3.2 The QA/QC Manager directs all activities of the project quality
organization, reporting directly to the project manager but,
maintaining an operational link with the Client. His duties and
responsibilities are as follows;
He is the authorized company quality control representative
to the Client.
He is responsible for all matters pertaining to the quality
control plan.
He is responsible in ensuring that all Client requirements
are strictly adhered to.
Page 8 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
3.3.5 The third party inspection and testing agencies approved by the
Client shall be responsible for carrying out all test and inspections
requiring third party inspection and testing, ie, soil compaction
test, concrete sampling, compressive strength tests, NDT/NDE,
test equipment and measuring instruments calibration, instrument
calibration and others.
Page 9 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
3.5.1 The company Quality Steering team will conduct reviews chaired
by a member of Senior Management and /or a copy of minutes of
meeting shall be submitted for management review and action if
any as may be required. This management review meeting of the
Quality System shall be conducted every six (6) month in general
Review objectives:
Ensure the efficiency and appropriateness of the Quality
System.
Monitoring and evaluating the trends of nonconformity's within
the system.
4.1.1 The quality system employed in the project has been structured
in accordance with the requirements of the contract. The Quality
System was designed primarily to satisfy the managerial
requirements of COST Company and the Client.
4.1.4 The Quality System described in the Quality Plan shows that
COST Company has a planned and systematic approach in
Page 10 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
4.1.5 Details of who, what, how and when are properly defined in the
Quality plan and other referenced COST Company documents.
4.1.10 A two week look ahead inspection schedule for all inspection
activities shall be submitted to the Client representative one
week in advance on a weekly basis.
Page 11 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
4.3.1 The Project Quality Plan is the level 1 and governing document of
the quality management system. It makes reference to the scope
of work, project specifications and quality procedures meeting
the requirement of the Project Quality Statement
Page 12 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
4.4.1 General
4.4.1.1 Contracts review activities are completed in accordance
with established procedure for construction activities
prior to submitting an offer. Contracts review are carried
out to ensure that all tender documents and contracts
are reviewed to establish that all terms, conditions and
requirements of the clients are clearly defined and
understood.
4.4.2 Review
4.4.2.1 Tender documents are reviewed to determine the
company's ability to meet client requirements. This
review ensures that all relevant data is available and
adequately defined and that assumptions and
clarifications are obtained documented and resolved.
Before dispatch of proposal it is again reviewed with
reference to the check list / list of documents to be
submitted etc, to ensure that client’s requirement is met.
4.4.2.2 QA plan assures that each agreement is reviewed for:
1. Thorough and duly understanding of clients
requirements
2. Complete resolution of differences of understanding
3. Issues that may challenge the capability of COST
to fulfill the intended contract
Page 13 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
4.5.1 General
4.5.1.1 All documentations within COST quality system are
controlled by procedures such as:
4.6 Purchasing
Page 14 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
4.6.1 General
4.6.1.1 Supply of raw materials, fabrications, spare parts,
specialist services and finished items shall be processed
from the Client approved suppliers.
Page 15 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
1. Physical description
2. Specifications and standards
3. Delivery lead period
4. Quality requirements
Page 16 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
Page 17 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
4.10.1 General
4.10.1.1 Quality control plans describe the inspection and testing
requirements to verify that product specifications are met.
Inspection and testing activities are divided into the
following categories:
1. Receiving
2. In-process
3. Final
Page 18 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
Page 19 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
4.12.1 General
4.12.1.1 Following planned measurements, inspections, and
test;
The inspection and test status of all products is
identified by means of tags, labels, color codes, or
other suitable measures during the various stages of
production.
Page 20 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
4.13.1 General
4.13.1.1 Procedures and quality plans describe the methods
that ensure nonconforming products are evaluated,
identified, and segregated from the production flow or
installation process.
Page 21 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
1. Rework
2. Accept by concession
3. Re-classify
4. Reject or scrap
4.14.1 General
4.14.1.1 Procedures and quality plans detail the methods
for implementation of corrective and preventive
action to effectively eliminate the causes of actual
or potential nonconformance. The degree of
corrective or preventive actions taken is in
proportion to the associated risks.
Page 22 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
4.15.1 The Site QA/QC Supervisor and Inspectors shall verify that the
instruments, tools, equipment used in testing, and inspections
are properly calibrated and controlled. All instruments, tools
and equipment shall bear an individual identifying number by
etching or permanently marked on the instrument. Calibrated
control sheet shall be used to document item, identifying
number, location, description, accuracy method, interval, due
date, date calibrated, calibrated by, results and remarks. Any
instruments/equipment found defective and cannot be
repaired shall be replaced and noted in the QA/QC records.
Page 23 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
Page 24 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
4.16.1 General
4.16.2. Storage
4.16.2.1 Material Movement and Protection procedure
addresses general storage requirements. Subject
contract’s Standards and work instructions detail the
specific methods of storage required for that specific
contract and dedicatedly implemented by COST.
4.16.3. Packaging
4.16.3.1. Material Movement and Protection procedure
describes the general packaging requirements.
Specific packing, packaging, and marking
processes are documented as per client’s
format for the individual products.
4.16.4. Preservation
4.16.4.1. Preservation and segregation of product is
addressed under the storage section of Material
Movement and Protection procedure which will
be detailed on contract to contract basis.
Page 25 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
Page 26 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
Page 27 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
4.20 Training
4.20.1. General
Page 28 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
4.22 Servicing
Servicing is limited to services carried out during defect liability period
or warranty period for the projects carried out by COST. Since
maintenance shall be handled on case to case basis, it is not
applicable to make a documented procedure to describe each case,
but it shall be done as follows:
Page 29 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
4.23.1 The Site QA/QC inspector shall prepare a Daily Report at the
end of each working day containing all inspections/tests made
on the report day including:
Page 30 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
Page 31 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
4.26.1 The Site QA/QC Supervisor shall establish and maintain the
following records and files. It shall be his responsibility to see
and check that these records are properly maintained and
stored up to the project completion.
Page 32 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
Page 33 of 34
CONTEMPORARY STRUCTURE CO.
FOR CONTRACTING
QA / QC Manual Contract No. 3000775497
4.29 Waivers
4.29.3 A log detailing all waivers from the Client or COST QA/QC
and inspection requirements obtained during all wok phases
shall be maintained by COST. This log must indicate the
status of the waiver, a brief description and details of the
applicable purchase order and equipment or construction
process.
Page 34 of 34