Michael Seyoum Construction Contract & Law Assessment Number 2: Assessment On Construction Claims and Disputes
Michael Seyoum Construction Contract & Law Assessment Number 2: Assessment On Construction Claims and Disputes
Assessment number 2:
Assessment on Construction Claims and Disputes
1. What do you understand by the concept of construction claims & remedies thereto;
including types of construction claims & their base;
The concept of construction claim is that the contractor requests the employer for additional
time or cost due to the employer fault or unforeseen force measure. Construction claims is
legal right of the contractor to demand for time, financial or other remedies.
Time claim: is to be initiated by the contractor for lost time due to the employers risk or other
force measures. Time claim related with the addition of time on the original contract period.
This type claims are caused by; delay on supply of design, delay on obstruction clearance,
adverse physical conditions, and others.
Financial Claim: is to be initiated by the contractor for lost time and finance. When there is
an occurrence on the project for finance related issues; such us variations, adverse physical
conditions, measurement change, delay on effecting payments, and others.
Other Remedies: when the contract is terminated, suspension of the construction works,
reduction of the progress of the execution of the works.
2. What are the underlined causes for the construction claims & disputes?
The causes of construction claims and disputes are the deviation from the promises made
under the construction contract during the performance of the construction contract.
Unclear contract document/bid document: during the tender period or later this might
occur on construction contract.
Inadequate administration of responsibilities: this type of construction claims are
caused by the leaders of the contracting parties’ performance.
Unforeseen or uncertain situations during the execution of the construction project
Changed conditions: when the expected ground condition is not available. For
example during design period the ground condition of the underneath material to be
excavated was common soil, but when constructing the road the material found is
rock. So this leads to construction claim.
Addition of works: addition of work might leads to construction claims
Delay for cost overruns and time extension
Breach related construction claim: when the construction contract is breached by the
contracting parties.
3. What are the requirements for the valid construction claims to exist?
Procedural requirement: the claimant should give prior notice to the other party about
the intention of the claim. This intention claim should have enough contractually
designated time. Not following this procedural requirement may result on total/partial
loss of the construction claim.
Substantive requirement: means giving justification of the construction claim by
specifically referring to the Construction contract of by the applicable law. The
construction contract means the all the relevant clause in the contract. The applicable
law means the relevant article of the law that is related to the contract (like civil code,
commercial law)
Proof requirement: means the submission of the relevant documentation which
supports or corroborates the construction claim under consideration. The relevant
documentations are delay justification, weather data, variation claims, additional
payment and others. In case of disputes the proof requirements in addition to the
relevant documentation, also includes factual witness, experts opinion, site visit and
inspections, and other mode of proof.
4. Briefly describe the construction claims management process;
Claim submittal: this is the first process of the construction claim. In order to get the
construction claim the claimant has to submit the construction claim within
reasonable time frame prearranged by the contract document. This claim submittal
process has three sub-process; claim notification, claim preparation and claim
submittal. On submitting the construction claim the claimant should prepare all the
necessary relevant documents, legal aspects, and other supporting documents for
submission and submit it.
Claim processing: claim processing process has three sub-process; claim handling,
dispute resolution, and claim approval. Claim handling is a process of checking the
claim if it legally or contractually supported or not, documents provided are valid and
reliable to substantiate the claim for consideration or not, and overall procedural
requirements have been followed or not. After verifying the validity of the claim
proper computations & evaluations will be carried out to present the proposed
compensation for the contractual parties the claim is applicable to. Dispute resolution
means solving the claim. the contractual parties will pass through different dispute
resolution system depending on their acceptance over the proposed compensation
varying from the simplest mediation by the consulting engineer to the final court
ruling in the form of litigation. There are three types of dispute resolution systems are
well applicable. Preventive dispute resolution system, Amicable dispute resolution
system and Judgmental dispute resolution system. Claim approval is the acceptance
of the claim resolution by the contracting parties. Once the contracting parties agreed
on the final result of the claim process then they will approve the claim.
Claim enforcement: this part is divided into two parts: namely claim enforcement and
claim closure. Claim enforcement means implementation the approved clam to
Michael Seyoum Construction Contract & Law
payment certificate or other modes, such us time extensions. Once the claim is
enforced then there will be claim closure.
The factors that should be considered to prevent construction claims and disputes are:
The non-judgmental dispute settlement methods are the dispute preventive and amicable
dispute settlement.
Dispute Preventive: This method will avoid the construction claims and disputes. Disputes
can be prevented by: having well designed project, having well studied project, having well
designed project, having a clear, accurate and complete tender dossier and document, having
a clear, accurate and complete contract document, having a balanced risk sharing and
allocating contract document, discharge the expected contractual & legal obligations by the
contracting parties, have good project governance. There are dispute prevention systems;
of specific project goals, the bonus will be shared among all sub-contractors on the
project
Amicable aspects: The very feature of amicable settlement is that the disputing parties shall
have full control both over the process & the outcome without the influence of third party.
There are some highly recognized amicable settlement methods;
Negotiation: is a give and take process. Negotiation requires legal power to decide,
knowledge on the dispute, skill on the art of negotiation, and good faith. There are
two types of negotiations, namely deal negotiation and dispute negotiation. Deal
negotiation is a type of negotiation to strike a deal. Dispute negotiation is a type of
negotiation to settle dispute arising out of the deal. Dispute negotiation could be
direct negotiation or assisted negotiation. Direct negotiation is held directly by the
contracting parties. The contracting parities might get assistance form their own
internal advisors.
7. Identify & discuss briefly the judgmental dispute resolution methods including their
common features;
8. What are the major differences between the PPA (2011) & the MDB-FIDIC (2006)
standard conditions of construction contracts as related to construction claims &
disputes management?
9. What do you understand by the concept & scope of alternative dispute resolution
(ADR) as applied to construction disputes?