What Is Project Management
What Is Project Management
A project in any organization is collaboration across departments to achieve a single well defined objective. The
process of planning, organizing and managing resources to achieve the organizational objective is called project
management.
Project management is very important in production of goods and services. Idea generation to final production of
product or service, each step can be categorized as individual projects. Any project requires a project manager, who
leads the project to its logical conclusion
Project Characteristics
Timeline: A project has a definite timeline with measurable starting and end point.
Resources: A project has limited resource of capital and manpower.
Tools: Special type of tools and techniques are used for project management (Gantt Charts, etc.)
Team: Project management requires diverse team stretching across departments and functions
A typical project is divided into following phases. Each phase of the project has its own importance and impact on
overall success of the project.
Initiation Phase: In this phase of the project, feedback received from customers is analyzed and
brainstorming is done as to develop new product or modify existing product to meet the new demands.
Project Definition Phase: In this phase of the project efforts are made to define the solution for the problem
posed by customers.
Feasibility Study: In this phase, planning of the project is made and definite milestones are established.
Project Execution: In this phase all activities and milestones established in the earlier phase are executed in
a timely and orderly manner. This phase utilizes maximum of all resources.
Project Conclusion: This is the last phase of the project. In this phase, final product or service is handed
over to the operations team for commercial production.
Project management activities are mainly divided into three main categories Planning, Scheduling and Controlling.
Time scheduling
Definition
Time scheduling is a collection of techniques used to develop and present schedules that show
when work will be performed.
DEFINATION
Scheduling in project management is the listing of activities, deliverables, and milestones within a project. A
schedule also usually includes the planned start and finish date, duration, and resources assigned to each
activity. Effective project scheduling is a critical component of successful time management.
In fact, when people discuss the processes for building a schedule, they are usually referring to
the first six processes of time management:
3. Sequence activities.
4. Estimate resources.
5. Estimate durations.
1. Master project schedule. A master schedule tends to be a simplified list of tasks with a timeline or
project calendar.
2. Milestone schedule or summary schedule. This type of schedule tracks major milestones and key
deliverables, but not every task required to complete the project.
3. A detailed project schedule. This is the most thorough project schedule, as it identifies and tracks
every project activity. If you have a complex, large, or lengthy project, it’s important to have a
detailed project schedule to help track everything.
In other words, a gantt chart is a super-simple way to keep you out of a project
pinch!
What are the key parts of a Gantt chart?
A Gantt chart is made up of several different elements. So let’s take a quick look
at 8 key components so you know how to read a Gantt chart:
Task list: Runs vertically down the left of the Gantt chart to describe project
work and may be organized into groups and subgroups
Timeline: Runs horizontally across the top of the Gantt chart and shows
months, weeks, days, and years
Dateline: A vertical line that highlights the current date on the Gantt chart
Bars: Horizontal markers on the right side of the Gantt chart that represent
tasks and show progress, duration, and start and end dates
LOB (line-of-business)
1. An LOB (line-of-business) is a general term that describes the products or services
offered by a business or manufacturer. A company that manufactures solid state disk
drives, for example, might claim their LOB is data storage.
2. An LOB application is one of the set of critical computer applications that are vital to
running an enterprise. LOB applications are usually large programs that contain a
number of integrated capabilities and tie into databases and database management
systems.
3. In some large enterprise cultures, the term line-of-business (LOB) is used as a
synonym for corporate division.
Network Technique: Meaning,
Objectives and Advantages
Network technique is a technique for planning, scheduling (programming) and
controlling the progress of projects. This is very useful for projects which are
complex in nature or where activities are subject to considerable degree of
uncertainty in performance time.
3. Minimises total cost where the cost of delays and cost of resources required
to carry out the tasks can be measured.
2. Identifies the critical activities and focus them to provide greater managerial
attention.
(ii) Its accuracy depends on the estimation of the data used in the network.
Define the required tasks and put them down in an ordered (sequenced) list.
Create a flowchart or other diagram showing each task in relation to the others.
KEY TAKEAWAYS
PERT charts were first created by the U.S. Navy's Special Projects Office in 1957 to
guide the Polaris nuclear submarine project.
A PERT chart uses circles or rectangles called nodes to represent project events or
milestones. These nodes are linked by vectors, or lines, that represent various tasks.
A PERT chart allows managers to evaluate the time and resources necessary to
manage a project.
How Do PERT Charts Work?
A PERT chart uses circles or rectangles called nodes to represent project events or
milestones. These nodes are linked by vectors or lines that represent various tasks.
Dependent tasks are items that must be performed in a specific manner. For example, if an
arrow is drawn from Task No. 1 to Task No. 2 on a PERT chart, Task No. 1 must be
completed before work on Task No. 2 begins.
Items at the same stage of production but on different task lines within a project are
referred to as parallel tasks. They're independent of each other, but they're planned to
occur at the same time.
https://images.app.goo.gl/mTp7ot6ShK8Ap4Fg9
Definition of Crashing (In Project
Management Terms)
Crashing is a schedule compression technique used to reduce or shorten the project schedule.
The PM can various measures to accomplish this goal. Some of the common methods used
are
5 Other Definitions
1. Crashi
technique in which resources are added to the project for the least cost possible. Cost and schedule
tradeoffs are analyzed to determine how to obtain the greatest amount of compression for the least
incremental cost.
2. Crashi
purposes of decreasing total period of time (also known as the total project schedule duration). The
diminishing of the project duration typically take place after a careful and thorough analysis of all
possible project duration minimization alternatives in which any and all methods to attain the maximum
schedule duration for the least additional cost.
3. When
activity normally takes this many Project Management Triangle days or weeks. We could make it take
less time, but to do so would cost more money. Spending more money to get something done more
quickly is called “crashing”. There are various methods of project schedule crashing, and the decision
to crash should only take place after you’ve carefully analyzed all of the possible alternatives.The key
is to attain maximum decrease in schedule time with minimum cost.
4. Crashi
getting the highest level of efficiency.
5. Crashi
compress the schedule. In crashing, you review the critical path and see which activities can be
completed by adding extra resources. You try to find the activities that can be reduced the most by
adding the least amount of cost. Once you find those activities, you will apply the crashing technique.
Second, such organization has certain difficulties in the inter-departmental cooperation and exchanges;
Third motivation is not strong enough for project participants, they think the project is an additional burden,
and not directly related to their career development and upgrading;
Fourth, in such organizational structure, sometimes no one should assume full responsibility for the project,
often the project manager is only responsible for part of the project, others are responsible for the other parts of
the project, which leads to difficulties in coordination situation.
Second, the project team’s decision is developed within the project, the reaction time is short; Third, in
this project, members work with strong power, high cohesion, participants shared the common goal of
the project, and individual has clear responsibilities.
Second, the project team itself is an independent entity, prone to a condition known as “Project
inflammatory” disease, that is, there is a clear dividing line between the project team and the parent
organization, weakening the effective integration between project team and the parent organization;
Third, the project team members lack of a business continuity and security, once the project ended,
return to their original functions may be more difficult.
Second, project is the focus of work, with a formal designated project manager will make him give
more attention to the project, and responsible for the coordination and integration work between different
units;
Third, when there are multiple projects simultaneously, the company can balance the resources to
ensure that all the projects can progress to complete their respective costs and quality requirements;
Fourth, the anxiety of project members is reduced greatly after the end of the project, while they are
strongly associated with the project, on the other hand, they have a “home” feeling about their functions.
The disadvantage is that this organizational structure:
First, the matrix structure has exacerbated the tensions between functional manager and project
manager;
Second, under any circumstances, sharing equipment, resources and personnel among different
projects will lead to conflict and competition for scarce resources;
Third, in the process of project implementation, the project manager must negotiate and consult with the
department managers on various issues, which leads to the delay in decision making;
Fourth, matrix management is not according to the principles of unified management, project members
have two bosses, the project manager and functional managers, when their commands are divided, it will
make members at a loss.
Typically, this is depicted as the project planning and control cycle. The importance of
project planning and control cycle — or the project control cycle — cannot and should
not be understated.
Human Aspects of Project Management
Introduction
One of the biggest challenges project managers face is balancing, organizing,
winning, overcoming, placating, supporting, guiding, leading, and as appropriate,
modifying the human aspects involved with the project. The key areas to be
addressed include:
Project sponsorship and leadership
The organization structure and culture
The project team
Communication
Performance Reviews
Performance reviews is a technique employed in project management that is used to
gauge, compare, and analyze the performance of work in progress against
the baseline of the project. The benefit of conducting performance review is that it
can dictate the fate of the project within the organization.
There are many things that are measured, compared and analyzed in performance
reviews and these include the actual implementation and completion dates of the
project as well as the remaining time for work in progress.
There are different techniques that are used to conduct performance reviews and
these include the following:
Critical chain method: This method compares the amount of buffer remaining
from the buffer required to protect the delivery date. It is used to determine the
status of the schedule.
Earn value management: It is used to assess the degree of variation of the
scheduled baseline using the schedule variance and schedule performance.
Trend analysis: This method examines the performance of the project over time.
It helps determine if the performance of the project is deteriorating or improving.
Critical path method: It compares the progress along the critical path to determine
the status of the schedule. It has a direct impact on the project’s end date.
Procurement Performance Reviews In project management, the procurement performance
reviews refer to the structured review of the progress of the sellers when it...
Work Performance Information Part of the executed project management plan includes the
routine collection of work performance information. The information gathered is important,...
Documentation Reviews Poor project management can be tracked to the insufficient planning
and documentation. The lack of understanding of the information can...
Performance Reporting Effectively managing a project is a many layered process and effort,
and there are a number of components that need...
Performance Reports Effectively managing a project is a many layered process and effort,
and there are a number of components that need...