Prof. Sam.: Regards
Prof. Sam.: Regards
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
-----Original Message-----
From: Nicolas Mendoza Manalo [mailto:[email protected]]
Sent: Thursday, September 25, 2008 10:44 AM
To: [email protected]
Subject: Question
The client is granted us to pay all materials on site and they agreed to
incorporate it in Interim Payment Certificate but they said they would
deduct it in pro-rata basis whenever we are submitting application for
Interim payment certificate eventhough that the materials are not yet
completely installed...is this a right practice? Or should I tell to
them to deduct the full amount of materials on site paid for us once the
materials are completely installed. Please clarify.
If you get paid for all the materials brought on site through one
payment certificate, then any portion thereof that would still remain on
site (not installed) should appear as material on site, in the
subsequent (cumulative) payment certificates as well.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
-Student
Batch June 2008
-----Original Message-----
From: Ian Milford [mailto:[email protected]]
Sent: Thursday, September 25, 2008 4:50 PM
To: Prof. Sam
Subject: Querie on EOT - Al-Tayer Stocks
Hi Dr Sam.
I have a very quick question relating to an EOT claim which we have submitted.
We have submitted a claim on the 7th July 2008 for delays we have experienced on a particular
project. The Engineer has failed to respond within 42 days as noted within the contract.
If you are quite confident about your entitlement to EOT and also about the accuracy of your
delay impact analysis, then a revised programme showing the revised date of completion could
be sent to the Engineer stating that you are proceeding according to that, as there was no
response within the period required by the contract.
Since you have your entitlement to EOT and the number of days are correct, it is unlikely that a
professional Engineer would determine anything to the contrary. If he does, then it would amount
to a dispute which would eventually be resolved in your favour through the specified dispute
resolution process.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Many thanks
Ian
Kind Regards
Ian Milford
Project Manager
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Kind regards,
Vic
-----Original Message-----
From: ANANDA WEERAKOON [mailto:[email protected]]
Sent: Tuesday, September 09, 2008 12:55 PM
To: [email protected]
Subject: Re: A Big Thank You + Q&A
Dear Sir,
Please help me to solve this problem.
Provisional sum included in the Contract is also part of the scope of works to the Main
contractor (obligations and responsibilities) is it correct? Yes. If provisional sum
allocated in the Contract but none of them was carried out and was deleted by Engineer
(the reason was not to awarded any contractor directly) can the Engineer deduct
Contractor,s prelims (any portion) as a variation ? . No. Any Preliminaries (which are not
“Specified Requirements”) are at Contractor’s risk, and the Contractor has already
considered that the PS work may or may not be executed. If any provisional sum is
awarded to the Main Contractor via instruction issued by Engineer (BOQ rate is
applicable) can the Contractor claim additional prelims? No. If however, the work that
was either defined or that could be inferred from the originally available information is
increased significantly through the instruction issued to expend the PS, then to the extent
that the Contractor can prove that the risks he priced in the Preliminaries are affected by
such increase, he can claim an additional payment. (This may seem to be unfair to the
Employer because the converse would not be applicable, but that is due to the
Employer’s own making. If items are provided next to a PS item for the tenderers to
price all costs related thereto, such as attendance, special attendance, builder’s work,
mark-ups etc. without leaving any room whatsoever for the Contractor to resort to pricing
them in the Preliminaries, and if the Consultant/Employer analyze the tenders properly
and ensure such items are properly priced and no components thereof are distributed over
the Preliminaries prior to an award, then the Contractor would not have any claim
regarding additional Preliminaries.)
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
The verbal instruction to omit the work for execution by the Employer is a variation. (The Contractor should
have confirmed it in writing at that time in order to avoid complications such as this.) Even otherwise, the
Engineer still has a responsibility to confirm his verbal instruction in writing.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Please Verify.
Thank you very much.
Abdul Azeez.
Had the damage been detected earlier, no payment would have been certified.
Failure by the Engineer to detect the damage does not absolve the Contractor of his
obligation. The Engineer has authority to correct any previous payment certificate,
vide any subsequent payment certificate.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Thanks & Regards
Rama Prasad.S
Project Manager
ETA - Power Projects Division
-----Original Message-----
From: Munyori, James [mailto:[email protected]]
Sent: Thursday, August 28, 2008 1:31 PM
To: [email protected]
Subject: RE: A Big Thank You + Q&A