Dismantling: Estimate of Bridge Proper and Protection Works
Dismantling: Estimate of Bridge Proper and Protection Works
Bridge proper
Sl. No./
Amount In
SOR Item Unit Rate (Rs.) Quantity
Rs.
Clause
Dismantling
Labour for dismantling all members of the timber
bridge (except piles) and stacking them at suitable
1/16.10 places as directed (all members will be under Rm 577.00 24.00 13848.00
custody of the contractor till taken over by the
department)
Foundation
3/11.1
Excavation for structures : Earth work in
excavation for foundation of structures as per
drawings and technical specification clause 305.1,
including setting out, construction of shoring and
bracing, removal of stumps and other deeleterious
matter and disposal up to 50m,, dressing of sides
and bottom and back filling in trenches with
excavated suitable material.
I. Ordinary soil
A. Manual
means
(I) upto 3.0m depth m3 61.00 0.000 0.00
(ii) 3m to 6m depth m3 90.00 200.820 18073.80
4/16.56
Bored cast-in-situ M35 grade R.C.C. pile
excluding reinforcement complete as per drawing
and technical specification and removal of m 11101.00 256.000 2841856.00
excavated earth with all lifts and lead upto 1000m.
(Pile diameter-1000mm)
5/16.61 Pile load test on single vertical pile in accordance
with IS:2911 (Part-IV)
473197098.xlsx
Br. No 1/2 Estimate .Bridge proper
7/16.63
Providing and laying of PCC M15 levelling course
100mm thick below the pile cap as per drawing
m3 5086.00 12.15 61794.90
and technical specification of MORTH Section
1100 & 1700
8/11.8
Supplying , fitting and placing TMT bar
reinforcement in foundation complete as per
tonne 67337.00 31.647 2131021.98
drawing and Technical Specifications clause 1000
& 1202.
9/16.41
Providing and construction of temporary island to
A(iii)
accommodate pile rig and other assessories
including casting of pile cap, all complete in depth Each 151360.00 0.000 0.00
of water up to 400cm (rate taken from item no.
16.41)
10/16.4 Providing and construction of one span service
1D road to reach island location from one pier Rm 2051.00 0.000 0.00
location to another pier location
Substructure
11/12.5 Plain/Reinforced Cement concrete, in Substructure
complete as per Drawing and Technical
Specifications as per MORTH Section
1500,1700,2200
473197098.xlsx
Br. No 1/2 Estimate .Bridge proper
Superstructure
Furnishing and placing reinforced / Prestressed
15/16.8 cement concrete in superstructure as per drawing
and Technical Specifications at clause 800,1205
and 1205 . A with crushed Stone.
18/13.6
Construction of RCC railing of M25Grade in cast
insitu with 20mm nominal size aggregate, true to
line and grade, tolerance of vertical RCC post not
to exceed 1 in 500 centre to centre spacing m 2722.00 65.040 177038.88
between vertical post not to exceed 2000mm as
per drawing and technical specifications clauses
800,900 and 1208.3.
19/16.92
Drainage spouts complete as per approved
Each 8012.00 20 160240.00
drawings and technical specification clause 1209.
20/16.98
Burried Joint (Providing and laying a burried
expansion joint, expansion gap being 20mm,
covered with 12mm thick, 200mm wide
galvanised wieldable structural steel plate as per
IS:2062, placed symmetrical to centre line of the m 1406.00 16.90 23761.40
join, resting freely over the top surface of deck
concrete, welding of 8mm dia. 100mm long
galvanised nails spaced 300mm c/c along center
line of the plate, all as specified in clause 2604.
473197098.xlsx
Br. No 1/2 Estimate .Bridge proper
24
Carrying out SSI and preparation of DPR
including design and drawing of bridge including
approaches and protection complete as directed by m 0.00 43.500 0.00
the Engineer. A) For Bridge length less than 25
m ( as per accepted rate)
473197098.xlsx