0% found this document useful (0 votes)
92 views4 pages

Dismantling: Estimate of Bridge Proper and Protection Works

This estimate provides costs for bridge construction and protection works including: 1) Dismantling the existing timber bridge and piles. 2) Foundation works including excavation, pile installation, pile load testing, and concrete work. 3) Substructure works including concrete, reinforcement, backfilling, and bearings. 4) Superstructure works including concrete, reinforcement, wearing coat, railing, drainage, and expansion joints. 5) Approach works including concrete, boards, and slabs. 6) Construction of a temporary bamboo bridge.

Uploaded by

Hoque joynul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
0% found this document useful (0 votes)
92 views4 pages

Dismantling: Estimate of Bridge Proper and Protection Works

This estimate provides costs for bridge construction and protection works including: 1) Dismantling the existing timber bridge and piles. 2) Foundation works including excavation, pile installation, pile load testing, and concrete work. 3) Substructure works including concrete, reinforcement, backfilling, and bearings. 4) Superstructure works including concrete, reinforcement, wearing coat, railing, drainage, and expansion joints. 5) Approach works including concrete, boards, and slabs. 6) Construction of a temporary bamboo bridge.

Uploaded by

Hoque joynul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
You are on page 1/ 4

Br. No 1/2 Estimate .

Bridge proper

Estimate of Bridge Proper and Protection Works

AS per APWD's SOR for Rural Roads for All Divisions .

Sl. No./
Amount In
SOR Item Unit Rate (Rs.) Quantity
Rs.
Clause

Dismantling
Labour for dismantling all members of the timber
bridge (except piles) and stacking them at suitable
1/16.10 places as directed (all members will be under Rm 577.00 24.00 13848.00
custody of the contractor till taken over by the
department)

Labour for taking out old piles of the bridge and


2/16.9 Each 682.00 60.000 40920.00
staking them at suitable places as directed.

Foundation
3/11.1
Excavation for structures : Earth work in
excavation for foundation of structures as per
drawings and technical specification clause 305.1,
including setting out, construction of shoring and
bracing, removal of stumps and other deeleterious
matter and disposal up to 50m,, dressing of sides
and bottom and back filling in trenches with
excavated suitable material.

I. Ordinary soil
A. Manual
means
(I) upto 3.0m depth m3 61.00 0.000 0.00
(ii) 3m to 6m depth m3 90.00 200.820 18073.80
4/16.56
Bored cast-in-situ M35 grade R.C.C. pile
excluding reinforcement complete as per drawing
and technical specification and removal of m 11101.00 256.000 2841856.00
excavated earth with all lifts and lead upto 1000m.
(Pile diameter-1000mm)
5/16.61 Pile load test on single vertical pile in accordance
with IS:2911 (Part-IV)

a) Initial and routine load test tonne 330.00 360.000 118800.00


6/16.62
Cement concrete for reinforced concrete in pile
cap complete as per drawing and Technical
Specification of MORTH Section
1100,1500&1700

B. RCC Grade M25 ( Using Concrete Mixer) m3 6365.00 113.520 722554.80

473197098.xlsx
Br. No 1/2 Estimate .Bridge proper

7/16.63
Providing and laying of PCC M15 levelling course
100mm thick below the pile cap as per drawing
m3 5086.00 12.15 61794.90
and technical specification of MORTH Section
1100 & 1700

8/11.8
Supplying , fitting and placing TMT bar
reinforcement in foundation complete as per
tonne 67337.00 31.647 2131021.98
drawing and Technical Specifications clause 1000
& 1202.

9/16.41
Providing and construction of temporary island to
A(iii)
accommodate pile rig and other assessories
including casting of pile cap, all complete in depth Each 151360.00 0.000 0.00
of water up to 400cm (rate taken from item no.
16.41)
10/16.4 Providing and construction of one span service
1D road to reach island location from one pier Rm 2051.00 0.000 0.00
location to another pier location

Substructure
11/12.5 Plain/Reinforced Cement concrete, in Substructure
complete as per Drawing and Technical
Specifications as per MORTH Section
1500,1700,2200

F. RCC Grade M25(Using Concrete mixer)

I) Height up to 5.0m m3 6528.00 88.733 579246.18

II) Height 5.0m to 10.0m m3 6683.00 0.000 0.00


12/12.7
Supplying , fitting and placing TMT bar
reinforcement (Fe 415) in substructure complete
tonne 67418.00 10.422 702606.11
as per drawing and Technical Specifications
clause 1002, 1005, 1010 & 1202.

13/12.10 Backfill behind abutment, wing wall and return


wall complete as per drawings and technical
m3 1048.00 135.828 142347.74
specification clause 1204.3.8
i. Granular material.
14/12.12
Supplying, fitting and fixing in position true to
line and level elastomeric bearing conforming to
IRC:83(pt.II) section IX complete including all cm3 1.08 80640.00 87091.20
accessories as per drawing and Technical
Specification clause 1207.1.

473197098.xlsx
Br. No 1/2 Estimate .Bridge proper

Superstructure
Furnishing and placing reinforced / Prestressed
15/16.8 cement concrete in superstructure as per drawing
and Technical Specifications at clause 800,1205
and 1205 . A with crushed Stone.

B. RCC Grade M25 ( Using Concrete Mixer)

(II) For T-Beam and Slab


(p) Height up to 5.0 m m3 8010.00 95.50 764955.00
(q) Height 5.0 m to 10.0 m m3 8331.00 0.000 0.00
16/13.3 Supplying, fitting and placing un-coated TMT bar
reinforcement in super structure complete as per
tonne 70236.00 14.880 1045111.68
drawing and technical specifications clauses 1000
& 1202.
17/13.5
Providing and laying cement concrete wearing
coat M30 grade including reinforcement complete
m3 12292.00 14.243 175068.81
as per drawing and technical specifications clauses
800 and 1206.3. (B) With crushed stone.

18/13.6
Construction of RCC railing of M25Grade in cast
insitu with 20mm nominal size aggregate, true to
line and grade, tolerance of vertical RCC post not
to exceed 1 in 500 centre to centre spacing m 2722.00 65.040 177038.88
between vertical post not to exceed 2000mm as
per drawing and technical specifications clauses
800,900 and 1208.3.

19/16.92
Drainage spouts complete as per approved
Each 8012.00 20 160240.00
drawings and technical specification clause 1209.

20/16.98
Burried Joint (Providing and laying a burried
expansion joint, expansion gap being 20mm,
covered with 12mm thick, 200mm wide
galvanised wieldable structural steel plate as per
IS:2062, placed symmetrical to centre line of the m 1406.00 16.90 23761.40
join, resting freely over the top surface of deck
concrete, welding of 8mm dia. 100mm long
galvanised nails spaced 300mm c/c along center
line of the plate, all as specified in clause 2604.

PCC M15 ordinary grade (1:2.5:5) in levelling


21/13.1 course below approach slab complete as per
m3 5196.00 5.425 28188.30
1A drawing and technical specifications clause 800
&1211

Providing and fixing 20mm thick compressible


22/16.9
fibre board in expansion joint complete as per m 325.00 16.900 5492.50
9 (ii)
drawing & Technical Specification clause 2605.

473197098.xlsx
Br. No 1/2 Estimate .Bridge proper

RCC approach slab with M25 grade approach slab


including reinforcent and form work complete as
23/13.1
per drawing and technical specifications clauses m 11471.00 16.275 186690.53
2
800 & 1211.
A. with crushed stone.

24
Carrying out SSI and preparation of DPR
including design and drawing of bridge including
approaches and protection complete as directed by m 0.00 43.500 0.00
the Engineer. A) For Bridge length less than 25
m ( as per accepted rate)

Construction of cold weather Bamboo bridge over


all width 3.70m and clear road way 3.0m with
26/16.1 m 9805.00 40.000 392200.00
jungle wood post 20 to 25 cm dia 5 nos in each
row and rows being 2.0m apart

Sub Total (A) = Rs. 10418907.82


PROTECTION WORKS
Providing and laying pitching on slopes laid over
prepared filter media as per drawing and Technical
19 Specification Clause 1302
Cum 126.60 1091.000 138120.79
(i) Stone/Boulder
Providing and laying filter material underneath
20 pitching in slopes complete as per drawing and Cum 63.30 1455.000 92101.63
Technical Specification Clause 1302
21 Proiding and laying boulder apron for bed protection
with stone boulder of minimum size and weight as per
table 1300.1, no fragment weighing less than 25 kg laid Cum
dry complete as per drawing and technical specification
Clause 1301 357.54 1091.00 390076.95
620299.37
Providing and laying pitching on slopes laid over
prepared filter media as per drawing and Technical
19 Specification Clause 1302
Cum 126.60 1091.000 138120.79
(i) Stone/Boulder
Providing and laying filter material underneath
20 pitching and
Proiding in slopes
laying complete as per
boulder apron for drawing and
bed protection Cum 63.30 1455.000 92101.63
with
Technical Specification Clause 1302 weight as per
stone boulder of minimum size and
21 table 1300.1, no fragment weighing less than 25 kg laid Cum
357.54 1091.00 390076.95
dry complete as per drawing and technical specification
Clause 1301 620299.37