0% found this document useful (0 votes)
76 views

Cost Estimate

This cost estimate document contains a work breakdown structure (WBS) with estimated hours, labor rates, and total costs for internal and external labor on a training project. The total estimated cost is $993,300 which includes $573,000 for labor costs and $330,000 for external labor costs, plus $90,300 in reserves. The largest costs are for course design and development training modules that will use both internal and external resources.

Uploaded by

Randa S Jowa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
76 views

Cost Estimate

This cost estimate document contains a work breakdown structure (WBS) with estimated hours, labor rates, and total costs for internal and external labor on a training project. The total estimated cost is $993,300 which includes $573,000 for labor costs and $330,000 for external labor costs, plus $90,300 in reserves. The largest costs are for course design and development training modules that will use both internal and external resources.

Uploaded by

Randa S Jowa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 2

Cost Estimate

Project Name: Date:


Note: Enter your WBS, hours, labor rates, etc. Add/delete rows and columns as needed and check all formulas (bolded below)

Internal $/hour Internal External $/hour External Total


WBS Categories Labor $ Total Labor $ Total Labor
1. Initiating 200 $ 65 $13,000 $ - $ 13,000
2. Planning 600 $ 60 $36,000 $ - $ 36,000
3. Executing $ - $ - $ -
3.1 Course design and development $ - $ - $ -
3.1.1 Supplier management training 600 $ 60 $36,000 600 $ 150 $90,000 $126,000
3.1.2 Negotiating skills training 300 $ 55 $16,500 300 $ 150 $45,000 $ 61,500
3.1.3 Project management training 400 $ 60 $24,000 400 $ 150 $60,000 $ 84,000
3.1.4 Software applications training 400 $ 60 $24,000 400 $ 150 $60,000 $ 84,000
3.2 Course administration 400 $ 55 $22,000 300 $ 250 $75,000 $ 97,000
3.3.Course evaluation 300 $ 55 $16,500 $ - $ 16,500
3.4 Stakeholder communications 300 $ 55 $16,500 $ - $ 16,500
4. Monitoring and Controlling 500 $ 55 $27,500 $ - $ 27,500
5. Closing 200 $ 55 $11,000 $ - $ 11,000
Subtotal
Reserves $ - $ - $ -
Total 4,200 243,000 2,000 850 330,000 573,000

Assumptions
ll formulas (bolded below).

Non-labor $ Total Cost

$ 13,000
$ 36,000
$ -
$ -
$ 100,000 $ 226,000
$ 50,000 $ 111,500
$ 50,000 $ 134,000
$ 50,000 $ 134,000
$ 80,000 $ 177,000
$ 16,500
$ 16,500
$ 27,500
$ 11,000
$ 903,000
90,300.0
330,000 $ 993,300