Assignment PDF
Assignment PDF
2. Tender
3. Project Management Objectives;
6. Total Float;
7. Activity.
b) Explain briefly the five phases of a construction project and draw a bar chart showing the sequence
of these phases. ( 9 : 21 )
Question 2
Project Planning & Scheduling is a major topic in Project Management. Explain the typical steps
required to generate a Time Schedule for any construction Project.
Assignment # 2
Critical Path Method (CPM)
Activity – On – Node (AON)
Question 1
a) Project Scheduling
b) Types of Networks;
e) Dependency;
f) Successor Activity;
project:
Question 3
Draw the AON for the following project, Calculate the Early and Late times of activities, Calculate
Project Duration, Highlight the Critical Path on the network, Calculate the Total Float for All
activities, and Draw Bar based on early times:
Question 4
What is the Project duration (PDmin) for the next project by using Precedence Diagramming Method
(PDM)? Given that the Contract Duration (PDmax) = 45 days, highlight and write the critical path.
Question 5
Construct the PDM network represented by the data below:
Assignment # 3
Critical Path Method (CPM)
Activity – On – Node (AON) with relationships
Question 1
The following table represents the activities required for a small project. The Contract calls for
completing the project within 40 days. Using Activity - On - Node (AON) method, calculate the
following:
For the project shown in the following table, you are required to:
1. Complete the missing data in the table
2. Draw the activity-on-node (AON) network if all Relations between activities are
FS=0. clarify the longest path on the network
Assignment # 4
Project Calendar
Question 1
Given that the project starts on Monday, 1- 1 - 2018, the contractor considers Friday and Saturday as
weekends, and the period from 8 to 10 January 2018 is non- working period. It is required to:
1. Calculate the CPM days and clarify the critical path on the network.
2. Calculate the project duration due to an increase of 3 days in the duration of activity B
3. Calculate the activity dates considering the given calendar and draw the bar chart using Calendar
days.
Question 2
The following tables illustrate the data for the CPM diagram for a project. The project
start date is thursday1st March 2018; Workdays per week equal six, and the week start
on Saturday. It is required to find activity dates (ES, EF, LS, and LF)
Assignment # 5
Critical Path Method (CPM)
Activity – On – Arrow (AOA)
Question 1
Draw the following network using The Activity-On-Arrow method considering the
following data:
Question 2
Draw the following network using AOA with the following data and Calculate the
Project duration:
Question 3
Using Arrow - Diagramming Method (ADM), draw the activity network of the
project shown in table and calculate the following:
1. The project early finish.
2. Show the longest path(S) on the network
3. CPM days of activities
4. Draw Bar chart based on late times
5. Total Float and Free float for non-critical activities
Assignment # 6
Project Resources
Question 1
The following table provides the activities of a construction project. Each activity
requires a specific amount of cement. Draw the Cement consumptions as Histogram
along the project duration.
Question 2
Assignment # 7
Cash Flow
Question # 1
The following table represents the activities required for a small project and the total
cost for each activity
Requirement:
1. Cash - Out flow (S - curve) considering Early times
2. Cash - Out flow (S - curve) considering Late times
Question # 2
The table shows the start and finish time for each activity in a construction project. The
activities costs and prices are also provided
Data: assume that a month has 30 days, calculations are prepared at the beginning
of each month.
It is required to:
1. Draw the cash Out flow (S-Curve)
2. Amount of money required after 3rd month
Question # 3
The activities for constructing an industrial workshop are listed in the next table