Soal-Soal Latihan Network Planning

This document contains 12 sample problems for network planning. Each problem presents a network diagram with activities, duration times, and predecessor relationships. The problems increase in complexity, with some including dummy activities.

Uploaded by

Fadhlan Putra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
112 views

Soal-Soal Latihan Network Planning

This document contains 12 sample problems for network planning. Each problem presents a network diagram with activities, duration times, and predecessor relationships. The problems increase in complexity, with some including dummy activities.

Uploaded by

Fadhlan Putra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Soal-soal Latihan Network Planning

Soal no. 1 : Soal no. 2 :


Activity Duration (t) Predecessor Activity Duration (t) Predecessor
A 5 - A 5
B 4 - B 4 A
C 8 A C 8 A
D 3 A D 3 A
E 7 B E 7 B
F 5 D dan E F 5 C
G 4 D dan E G 4 E
H 3 C H 3 D dan G
I 7 C I 9 F
J 7 F dan I J 11 H dan I

Soal no. 3 (dummy) : Soal no. 4 :


Activity Duration (t) Predecessor Activity Duration (t) Predecessor
A 8 - A 4 -
B 4 - B 14 A
C 5 A C 5 A
D 3 A D 2 A
E 4 C E 12 D
F 5 B dan D F 7 B
G 7 E dan F G 4 C dan E
H 3 E dan F H 5 F dan G

Soal no. 5 : Soal no. 6 :


Activity Duration (t) Predecessor Activity Duration Predecessor
A 3 - A - Overhaul Machine 1 7 -
B 4 - B - Adjust Machine 1 3 A
C 5 - C - Overhaul Machine 2 6 -
D 4 A D - Adjust Machine 2 3 C
E 8 A E - Test the System 2 B dan D
F 3 B dan D
G 5 C

Soal no. 7 : Soal no. 8 (dummy) :


Activity Duration (t) Predecessor Activity Duration Predecessor
A 10 - A - Membuat Spec. 3 -
B 5 - B - Fabrikasi 4 A
C 3 B C - Rancang Pondasi 7 A
D 4 A dan C D - Rekrut Operator 2 A
E 7 A dan C E - Beli Material 5 C
F 15 E F - Inspeksi, Uji Coba 5 B
G 3 D G - Latih Operator 3 D dan B
H 6 D H - Buat Pondasi 3 E
I 8 F dan H I - Transportasi 6 F
J 4 G J - Pasang & Start Up 7 G, H, dan I
Soal no. 9 (dummy) : Soal no. 10 (dummy):
Activity Duration (t) Predecessor Activity Duration (t) Predecessor
A 5 - A 5 -
B 4 - B 4 -
C 8 - C 8 -
D 3 A D 3 A
E 7 A E 7 A
F 5 C F 5 C
G 4 C G 4 C
H 3 B dan D H 3 B dan D
I 9 F dan H I 9 H
J 11 F J 11 F dan H
K 8 E dan I K 8 E dan I
L 10 G dan J L 10 G dan J

Soal no. 11 (dummy) : Soal no. 12 (dummy) :


Activity Duration (t) Predecessor Activity Duration (t) Predecessor
A 2 - A 8 -
B 8 - B 3 -
C 5 A C 7 -
D 4 B D 4 B
E 4 B E 5 A
F 5 C F 4 C, D, dan E
G 9 D G 11 E
H 8 D H 3 F dan G
I 7 E I 8 H
J 9 H dan I J 9 H
K 9 F, G, dan J K 10 H
L 7 I L 5 J dan K