Assignment 1: Part 1: Project Management Experience
Assignment 1: Part 1: Project Management Experience
The processes that belong in each process group, what they do and which knowledge area they
represent can be confusing. This post (based on the info in PMBOK) discusses about each
process group and briefly explains the processes that belong in each process group. The
knowledge area they represent is indicated in brackets after the process. This post could serve
as reference for project managers and also help someone preparing for PMP certification.
Initiating:
Processes required to establish the scope of the project, refine the objectives and define the
course of action required to attain the objectives of the project.
Develop Project Management Plan (Integration): Process of documenting actions
necessary to define, prepare, integrate and coordinate all subsidiary plans. Outputs: Project
Management plan.
Collect requirements (Scope): Process of defining and documenting stakeholders'
needs to meet the project objectives. Outputs: Requirements documentation, requirements
management plan and requirements traceability matrix
Define scope (Scope): Process of developing a detailed description of the project and
product. Outputs: Project scope statement, project document updates
Create WBS (Scope): Process of subdividing project deliverables and project work into
smaller, more manageable components. Outputs: WBS, WBS dictionary, scope baseline,
project document updates (WBS - Work Breakdown Structure)
Define activities (Time): Process of identifying the specific actions to be performed to
produce the project deliverables. Outputs: Activity list, activity attributes, milestone list
Sequence activities (Time): Process of identifying and documenting relationships
among the project activities. Outputs: Project schedule network diagram, project document
updates
Estimate activity resources (Time): Process of estimating the type and quantities of
material, people, equipment, or supplies required to perform each activity. Outputs: Activity
resource requirements, resource breakdown structure, project document updates
Estimate activity duration (Time): Process of approximating the number of work
periods needed to complete individual activities with estimated resources. Outputs: Activity
duration estimates, project document updates
Develop Schedule (Time): Process of analyzing activity sequences, durations, resource
requirements and schedule constraints to create the project schedule. Outputs: Project
schedule, schedule baseline, schedule data, project document updates
Estimate costs (Cost): Process of developing an approximation of the monetary
resources needed to complete project activities. Outputs: Activity cost estimates, basis of
estimates, project document updates
Determine budget (Cost): Process of aggregating the estimated costs of individual
activities or work packages to establish an authorized cost baseline. Outputs: Cost
performance baseline, project funding requirements, project document updates
Plan quality (Quality): Process of identifying quality requirements and/or standards of
the project and product and documenting how the project will demonstrate
compliance. Outputs: Quality management plan, quality metrics, quality checklists, process
improvement plan, project document updates
Develop Human Resource plan (Human Resource): Process of identifying and
documenting project roles, responsibilities and required skills, reporting relationships and
creating a staffing management plan. Output: Human Resource Plan
Plan communications (Communication): Process of determining project stakeholder
information needs and defining a communication approach. Outputs: Communication
management plan, project document updates
Plan risk management (Risk): Process of defining how to conduct risk management
activities for a project. Output: Risk Management plan
Identify Risks (Risk): Process of determining which risks may affect the project and
documenting their characteristics. Output: Risk register
Perform Qualitative risk analysis (Risk): Process of prioritizing risks for further
analysis or action by assessing and combining their probability of occurrence and
impact. Output: Risk register updates
Perform Quantitative risk analysis (Risk): Process of numerically analyzing the effect
of identified risks on overall project objectives. Output: Risk register updates
Plan risk response (Risk): Process of developing options and actions to enhance
opportunities and to reduce threats to project objectives. Outputs: Risk register updates, risk
contract related decisions, project management plan updates, project document updates
Plan procurements (Procurements): Process of documenting project purchasing
decisions, specifying the approach and identifying potential sellers. Outputs: Procurements
management plan, procurements statement of work, make-or-buy decisions, procurement
documents, source selection criteria, change requests
Executing:
Processes performed to complete the work defined in project management plan to satisfy the
project specifications.
Direct & Manage project execution (Integration): Process of performing the work
defined in the project management plan to achieve the project's
objectives. Outputs: Deliverables, work performance information, change requests, project
management plan updates, project document updates
Acquire project team (Human Resource): Process of confirming human resource
availability and obtaining the necessary team to complete project
assignments. Outputs: Project staff assignments, resource calendars, project management
plan updates
Perform quality assurance (Quality): Process of auditing the quality requirements and
the results from quality control measurements to ensure appropriate quality standards are
used. Outputs: Organization process assets updates, change requests, project management
plan updates, project document updates
Develop project team (Human Resource): Process of improving the competencies,
team interaction and the overall team environment to enhance project
performance. Outputs: Team performance assessments, enterprise environmental factors
updates
Manage project team (Human Resource): Process of tracking team member
performance, providing feedback, resolving issues and managing changes to optimize project
performance. Outputs: Enterprise environmental factors updates, organization process assets
updates, change requests, project management plan updates
Distribute Information (Communication): Processing of making relevant information
available to project stakeholders, as planned. Output: Organization process assets updates
Manage stakeholder expectations (Communication): Process of communicating and
working with stakeholders to meet their needs and addressing issues as they
occur. Outputs: Organization process assets updates, change requests, project management
plan updates, project document updates
Conduct procurements (Procurements): Process of obtaining seller responses,
selecting a seller and awarding a contract. Outputs: Selected sellers, procurement contract
award, resource calendars, change requests, project management plan updates, project
document updates
Processes required to track, review and regulate the progress and performance of the project.
Monitor & Control project work (Integration): Process of tracking, reviewing and
regulating the progress to meet the performance objectives defined in the project management
plan. Outputs: Change requests, project management plan updates, project document updates
Perform Integrated Change control (Integration): Process of reviewing all change
requests, approving changes and managing changes to the deliverables, organization process
assets, project documents and project management plan. Outputs: Change requests status
updates, project management plan updates, project document updates
Verify scope (Scope): Process of formalizing acceptance of the completed project
deliverables. Outputs: Accepted deliverables, change requests, project document updates
Control scope (Scope): Process of monitoring the status of the project and product
scope and managing changes to the scope baseline. Outputs: Work performance
measurements, organization process assets updates, change requests, project management
plan updates, project document updates
Control schedule (Time): Process of monitoring the status of the project to update
project progress and managing changes to the schedule baseline. Outputs: Work performance
measurements, organization process assets updates, change requests, project management
plan updates, project document updates
Control costs (Cost): Process of monitoring the status of the project to update the
project budget and managing changes to the cost baseline. Outputs: Work performance
measurements, budget forecasts, organization process assets updates, change requests,
project management plan updates, project document updates
Perform quality control (Quality): Process of monitoring and recording results of
executing the quality activities to assess performance and recommend necessary changes.
Outputs are quality control measurements, validated changes, validated deliverables,
organization process assets updates, change requests, project management plan updates,
project document updates
Report performance (Communication): Process of collecting and distributing
performance information including status reports, progress measurements and
forecasts. Outputs: Performance reports, organization process assets updates, change
requests
Monitor and control risks (Risk): Process of implementing risk response plans,
tracking identified risks, monitoring residual risks, identifying new risks and evaluating risk
process effectiveness throughout the project. Outputs: Risk register updates, organization
process assets updates, change requests, project management plan updates, project document
updates
Administer procurements (Procurements): Process of managing procurement
relationships, monitoring contract performance and making changes/corrections as
needed. Outputs: Procurement documentation, organization process assets updates, change
requests, project management plan updates
Closing:
Process performed to finalize all activities across all process groups to formally close the project
or phase.
Close project or phase (Integration): Process of finalizing all activities across all of
the project management process groups to formally complete the project or
phase. Outputs: Final product, service or result transition, organization process assets updates
Close procurements (Procurement): Process of completing each project
procurement. Outputs : Closed procurements, organization process assets updates