MOS - Plumbing

This document provides a method statement for plumbing and sanitation installation works for the Sibiya 132/33 kV Substation Project. It outlines the scope of work, materials, site preparation, and work methodology for tasks such as excavation, installation of external cold water and sewerage pipes, installation of pipes in box-out shafts and sunken floors, and installation of sanitary fixtures and fittings. The method statement aims to ensure the plumbing and sanitation systems are installed safely and according to approved drawings and specifications.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
901 views19 pages

MOS - Plumbing

This document provides a method statement for plumbing and sanitation installation works for the Sibiya 132/33 kV Substation Project. It outlines the scope of work, materials, site preparation, and work methodology for tasks such as excavation, installation of external cold water and sewerage pipes, installation of pipes in box-out shafts and sunken floors, and installation of sanitary fixtures and fittings. The method statement aims to ensure the plumbing and sanitation systems are installed safely and according to approved drawings and specifications.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 19

SARAWAK ENERGY BERHAD

DOCUMENT REVIEW STATUS

STATUS 1: WORK MAY PROCEED.


STATUS 2: REVISE AND RESUBMIT. WORK MAY PROCEED SUBJECTED TO
INCORPORATION OF COMMENTS INDICATED.
STATUS 3: REVISE AND RESUBMIT. WORK MAY NOT PROCEED.
STATUS 4: REVIEW NOT REQUIRED. WORK MAY PEOCEED.
STATUS 5: REJECTED AND RESUBMIT. WORK MAY NOT PROCEED.

PERMISSION TO PROCEED SHALL NOT CONSTITUTE ACCEPTANCE OR APPROVAL OF DESIGN


DETAILS, CALCULATIONS, ANALYSIS, TEST METHOD, OR MATERIALS DEVELOPED OR SELECTED BY
CONTRACTOR AND SHALL NOT RELIEVE CONTRACTOR FROM FULL COMPLIANCE WITH CONTRACT
TECHNICAL SPECIFICATIONS AND DRAWINGS.

SEB_____________________________ DATE ___________________

0.2 12.03.20 FOR REVIEW AND APPROVAL HADOUMI NAJIB NAJIB


0.1 13.09.19 FOR REVIEW AND APPROVAL ANDREW JULIUS JULIUS
DESIGNED DRAWN CHECKED APPROVED
REV DATE DESCRIPTION
BY BY BY BY
EMPLOYER:

SARAWAK ENERGY BERHAD


MENARA SARAWAK ENERGY,
NO.1, THE ISTHMUS,
93050 KUCHING,
SARAWAK.

CONTRACTOR/SUPPLIER:
PESTECH SDN BHD
NO.26, JALAN UTARID U5/14, SEKSYEN U5
BANDAR PINGGIRAN SUBANG,
40150 SHAH ALAM, SELANGOR

CONSULTANT:

PROJECT:
SIBIYU 132/33 kV SUBSTATION PROJECT

PROJECT DETAIL:
SIBIYU 132/33 kV SUBSTATION PROJECT

TITLE: SCALE: THIS SHEET:


1
Method Statement for Plumbing and Sanitation Installation N.T.S
NEXT SHEET:
-

DRAWING NO.: FORMAT: REV.


PLS150129-SBY-M-MST-MW-0001
A4 0.2
PESTECH SDN BHD
Project: SIBIYU 132/33KV SUBSTATION PROJECT Contract No. PLS150129
Method Statement for Plumbing and Sanitation
Doc. Title:
Installation Rev. No.: 0.2
Doc. No. : PLS150129-SBY-M-MST-MW-0001

METHOD STATEMENT
MECHANICAL & ELECTRICAL

PLUMBING AND SANITATION INSTALLATION


1.0 TITLE

Method statement for plumbing and sanitation system installation works.

2.0 REFERENCE DOCUMENT

i. Project technical specification


ii. IFC drawings
iii. Approved shop drawings
iv. Approved material sample board

3.0 SCOPE OF WORK

3.1 GENERAL DESCRIPTION


This method statement details all the installation of cold water plumbing and sanitary
system.

3.2 PLANT AND EQUIPMENT


• Excavator
• Fitting tools

3.3 MATERIAL
• UPVC Pipe
• HDPE Pipe
• Joints and fittings

3.4 SITE PLANNING AND PREPARATION


a. Approval of materials pipes, fittings, jointing and all other sanitary materials
shall be submitted and approved before works commence.
b. The plumbing lines shall be positioned according to the drawings or with
approval from the QAQC engineer before start of work.

4.0 WORK METHODOLOGY

4.1 EXCAVATION

• Mark layout of the pipeline and obtain approval from the Client’s
representative. Barricade sides of trenches to be excavated.
• Start excavation works (Using manual labour or an excavator machine). Ensure
that the width does not exceed the maximum specified.
• Use a leveling instrument to make depth markings all along the length of the
excavation. In certain situations, it may not be practical to use a leveling
instrument in a plumbing or sewerage installation. In such cases, a tube level
could be used.
• Additional care should be exercised for excavations deeper than 1.5m,
especially in loose soils. Arrangements should be made for shoring the sides
of trenches.
• Filled in soil invariably settles taking the pipe with it, disturbing alignments.
• Ensure that excavated earth is always stored away from the edge of the
trench.

4.2 INSTALLATION OF EXTERNAL COLDWATER PIPE (HDPE)

• Mark pipe lines in ground according to working drawing and provide


barricading.
• Excavate trenches to required depths as per working drawings.
• Prepare base of trench for laying pipes, as per technical specifications.
• Cut the pipe to the required length with hacksaw or pipe cutter.
• Clean the pipe ends with a file or sand paper to remove bums.
• Clean the pipe ends and inside of socket to be jointed with cloth.
• Fixed the pipe end into the pipe fittings and tighten.
• Lay the pipes on the prepared base and support them at adequate intervals.
• Test the pipes for leaks under pressure in the presence of client’s
representative.
• Provide encasement with sand/granular material, if specified.
• Backfill trenches in layers including compaction.

4.3 INSTALLATION OF EXTERNAL SEWERAGE PIPE (UPVC PIPE)

• Mark pipe lines in ground according to IFC drawings.


• Excavate trenches to required depths with proper barricading.
• Prepare base for laying pipes.
• Cut uPVC pipe to the required length with hacksaw or pipe cutter.
• Clean the pipe ends with a file or sand paper to remove bums.
• Clean the pipe ends and inside of socket to be jointed with cloth.
• Apply a layer of solvent cement evenly on the pipe end and inside of socket.
• Push home the pipe end into the socket, hold firm for 20-30 seconds.
• Lay the pipe according to specified gradient in pipe trench and backfill the
trench.
• Backfill trenches in layers including compaction.
4.4 INSTALLATION OF BOX-OUT SHAFT PIPE

• Mark for pipes on the box-out shaft walls according to details in the working
drawings.
• Fix brackets as per details shown on the working drawings. A clear gap of 25
to 50mm shall be maintained between pipe and wall surface.
• Clamp pipe assemblies on to the brackets. Make sure the pipes are in ‘line’
(horizontal runs) or in ‘plumb’ (vertical stacks). Where expansion /
contraction will be a concern, ensure that pipes are not rigidly held to
brackets.
• Make cut-outs on the shaft walls for branch pipes at locations shown on the
drawings.
• Insert sleeves wherever required. Ensure that annular space in sleeves is not
more than 25mm.
• Provide branches on the pipe assembly for connections to internal pipework.
Provide isolating valves on water supply pipes at locations shown on working
drawings; at easily reachable heights.
• Test the pipes for leaks under specified pressure for the specified duration.
• Tests must be witnessed and approved by client’s representative.

4.5 INSTALLATION OF PIPE SUNKEN FLOOR OR SUSPENDED IN CEILING

• The type of support and bracket commonly used in plumbing services is shown
in the attached appendix.
• Make sure that base water-proofing of toilet floors is completed.
• Locate and mark positions of soil and waste outlets.
• Assemble pipe headers and connect them to branches left in the shaft for this
purpose. Pre-fabricate wherever possible.
• Make sure that pipes are in proper slope and are supported adequately.
Always ensure that the spacing of supports is as per specifications. Ensure
that floor traps are installed in level (not tilted) so that the water seal is not
diminished.
• Test the pipes and attend to leaks, if any.
• Keep all open ends plugged to prevent ingress of construction debris
• Select the type of bracket suitable to be used for the pipe line, such as cold-
water piping, sanitary piping, etc.
• Special brackets and support (fabricated) may be used at critical position.
Spacing (interval) of pipe support and bracket. The spacing (interval) of pipe
support and bracket are subjected to the pipe size and pipe material.
4.6 INSTALLATION OF SANITARY FIXTURES AND FITTINGS

• Remove outlet and flush out tank to remove any dust or foreign matter before
connecting pipe work. Apply thread tape to outlet fittings.
• All pipe work must be supported so that there is no added strain on the tank.
Apply thread tape to all fittings to prevent leakage.
• Install sanitary fixtures, faucets and washroom accessories. Use screws with
nylon washers to fix sanitary ware and PTPE tape for installation of faucets to
pipework.
• Check fittings for leaks and firmness. Refit them if necessary. Ensure that
proper tools are used. They must not make scratches or any other kind of
damages on the chrome plated fixtures.
• Commission the toilets in the presence of the SEB.
• Handover the toilets formally using the forms provided for the purpose.

4.7 INSTALLATION OF WATER TANK


• Water pump will be installed once all housekeeping plinths and other
plumbing works are completed.
• Flush and clean water tank(s) and distribution pipework with potable water to
remove dirt and any foreign matter.
• Fill the tank(s) with water.
• Open the farthest draw-off points or drain plug/valve to draw water.
• Drain out chlorinated water and fill the system with potable water.
5.0 Organization, Responsibilities & Supervision
SITE TECHNICAL KEY PERSONAL

Ref. Key Roles Key Responsibilities

1. Project Manager • Responsible for overall planning, control and execution of the project in a cost-effective manner.
Mohd Najib • Overall authority in determination of all quality related matters affecting the project.
• Responsible to coordinate and handling with Employers for finalizing project and its related activities.
• Responsible to complete the Project within the schedule completion time frame.
2. Construction Manager • Managing construction activities to comply with schedule, budget and quality requirements.
Mohd Najib • Supervising and monitoring of all construction activities assisted by site engineer.
• To ensure all site staff are clear with the scope of works and time schedule.
• Organizing and managing all construction personnel, contractors and subcontractors for smooth execution of the project.
• Ensuring that all materials and equipment used in the construction work have passed all tests specified in the contract.
• Ensuring the sufficiency of resources to carry out the construction activities.
3. Project Engineer (Civil) • Assist the PM to monitor project milestones and updating of project progress schedule together with scheduler.
Mohammad Hadoumi • Attend progress meetings with the client and prepare minute of meeting.
• Attend technical meetings and assist to resolve technical issues
4. QAQC Engineer • Coordination with Construction manager and project engineer on QAQC matters.
(Civil) • To carry out stage and final inspection and Preparation of associated reports.
Mohammad Hadoumi • To raise NCR and initiate corrective action if the work done is not as per Specification, Method Statement or as per approved
drawing.
• Ensure that all materials used and work performed are in accordance with the specifications.
• Carry out internal inspection and after verifying the work done, raise Inspection for client/consultant Inspection.
• To check and ensure that the work done is as per Project Specification, Method Statement and as per approved drawings
5. Site Supervisor • Assisting Site Engineer on Site Supervision and Construction work
Ahmad Fakhruddin • Coordinating all the related works between sub-contractors in order to ensure smooth flow of works.
6. Safety and Health • Compliance with the Employer's Environment, Health and Safety Policy
Officer • Implementation and management of the Contractor's Environment, Health and Safety Management Plan
Robert Kenny • Implementation and management of the Contractor's Emergency Planning and Response Plan;
7. Site Safety Supervisor To assist SHO for the following;
Alexander Empam • Compliance with the Employer's Environment, Health and Safety Policy
• Implementation and management of the Contractor's Environment, Health and Safety Management Plan
• Implementation and management of the Contractor's Emergency Planning and Response Plan;
6.0 QUALITY ASSURANCE
6.1 Inspection and Test Plan (ITP)

ITEM TEST METHOD FREQUENCY STANDARD/ ACCEPTANCE PERSONNEL INCHARGE INSPECTION FORM
OF TEST CRITERIA TESTED VERIFIED WITNESSED
Material Visual Prior to use / • Approved /Accepted Material Site C.O.W / QAQC Client’s Rep • Request for Inspection Notice
Receiving inspection installation by Client (SEB) Supervisor / Engineer (Witness) (P15-2)
Inspection • Material/Product Catalogue Site Engineer (Review) • Incoming Inspection Checklist
for Civil Material (Site) (P07-3A)
• Delivery Order
Setting Out On Site Each Location • Verify and confirm the levels Site C.O.W / QAQC Client’s Rep • Request for Inspection Notice
Measurement and alignment of drain line as Supervisor / Engineer (Witness) (P15-2)
Checking per IFC drawing. Site Engineer (Review) • Inspection Checklist - Cold
Water Installation Works or
Plumbing & Sanitary
Cold water Visual Each Location • Pipe and sleeve installed as Site C.O.W / QAQC Client’s Rep • Request for Inspection Notice
pipe inspection per IFC drawing Supervisor / Engineer (Witness) (P15-2)
Installation • Pipe support/hanger correctly Site Engineer (Review) • Inspection Checklist - Cold
installed Water Installation Works
Pressure Test Whole cold- • Criteria follow as the SEB Site C.O.W / QAQC Client’s Rep • Request for Inspection Notice
water pipeline Project Technical Supervisor / Engineer (Witness) (P15-2)
Specification. Site Engineer (Review) • Inspection Checklist - Cold
Water Installation Works
Water Tank Visual All units • Location and system Site C.O.W / QAQC Client’s Rep • Request for Inspection Notice
Installation inspection installation shall be as per Supervisor / Engineer (Witness) (P15-2)
approved drawings. Site Engineer (Review) • Inspection Checklist - Cold
• Water Tank accessories is in Water Installation Works
good condition
Sanitary Visual Each Location • Pipe and sleeve installed as Site C.O.W / QAQC Client’s Rep • Request for Inspection Notice
Pipe inspection per IFC drawing Supervisor / Engineer (Witness) (P15-2)
Installation • Pipe support/hanger correctly Site Engineer (Review) • Inspection Checklist - Plumbing
installed & Sanitary
Leakage Test Whole • Criteria follow as the SEB Site C.O.W / QAQC Client’s Rep • Request for Inspection Notice
sanitary Project Technical Supervisor / Engineer (Witness) (P15-2)
pipeline Specification. Site Engineer (Review) • Inspection Checklist - Plumbing
& Sanitary
7.0 ENVIRONMENT, SAFETY AND HEALTH
7.1 Introduction
Occupational injuries and fatalities occur every day in the workplace. These injuries often
occur because employees are not trained in the proper job procedure. One way to
prevent workplace injuries is to establish proper job procedures and train all employees
in safer and more efficient work methods. Establishing proper job procedures is one of
the benefits of conducting a Job Safety Analysis (JSA) – carefully studying and recording
each step of a job, identifying existing or potential job hazards (both safety and health),
and determining the best way to reduce or eliminate these hazards.

Precautions are to be taken for protection of persons and properties from injury or
damage. All site personnel must adhere to safety requirements:

• Only experienced personnel are allowed at working area.


• Site personnel must be briefed and be well versed with all site safety measures.
• Site personnel must be in proper safety working attire e.g. safety boots and helmets
must be worn at all times.
• Site safety member should be available at all times and must be able to respond
correctly to emergency.
• When working at night, proper and adequate lighting must be provided.

7.2 Personal Protective Equipment


• Hand gloves
• Long sleeves
• Safety boots
• Safety helmet
• Safety vest

7.3 Safety Plan


• There must be sufficient working space and clearance as directed by superintending
officer. No works shall be allowed to continue if contractor fail to provide adequate
working space.
• Safety helmets and safety footwear should always be worn.
• All soft spots or holes shall be identified and barricaded if necessary.
• The site shall be kept clear of unnecessary obstruction such as reinforcement rods,
timber with protruding nails, etc.
• First aid boxes in the charge of a responsible person have to be kept at sites.
7.4 Emergency Response Plan
In case if tripping, electrocuted or accident happened during works:

• Stop the work and inform supervising personnel immediately of the


incident/accident.
• Record all information such as work type, workers, equipment involve & etc. in the
incident/accident.
• Immediately study / investigate what could have caused the incident.
• Give detail information to authorized person on all the activity and incident that
occurs.
• Repair or normalize the equipment/structures involve to normal condition if
permitted and send the injured personnel to clinic or hospital nearby.
• For detail action, kindly refer to project safety manual.

EMERGENGY
COMMANDER
MOHD NAJIB

INCIDENT
EVACUATION SAFETY COUNTER & SECURITY CONTROLLER
CONTROLLER/
CONTROLLER FIRST AIDER
HISTORIAN OTHMAN SAHOK
ROBERT KENNY NAUL UNIE BELASAN
ALEXANDER EMPAM
CLEOPATHRA DHIEMAH
MHD. HADOUMI BIN JAMBAI
SALDAN

Chart 2: Emergency Response Team (ERT)


HAZARD IDENTIFICATION, RISK ASSESSTMENT & DETERMINING CONTROL PROJECT : SIBIYU 132/33KV SUBSTATION
(HIRADC) HIRADC : PSB/ SAFE/ SIBIYU/ 031
PREPARED BY REVIEWED BY APPROVED BY SCOPE: M&E/ ENGINEERING
ACTIVITY : PLUMBING AND SANITATION
NAME ANDREW CHAN ROBERT KENNY JULIUS JONG
INSTALLATION
POSITION CIVIL ENGINEER SAFETY & HEALTH OFFICER PROJECT MANAGER REVISION: 0.1
SIGNATURE
DATE

HAZARD IDENTIFICATION RISK ASSESSMENT


LEGAL REQUIREMENT

CONDITION ***
STEP SEQUENCE OF BASIC CURRENT RISK RISK CONTROL/ RECOMMENDED
NO JOB STEP CONTROL * ** RISK ACTION AND DATE
HAZARD EFFECT RANKING
LIKE SEV PERSON

SCORE

LEVEL
IN CHARGE

1 Examine the A NR 1. Trip and fall Minor injury 1. Comply with 2 3 6 M 1. Routine maintenance 1. Site
location SWMS and check list Supervisor
SWP 2. Maintenance by 2. Site
2. Ensure all competent mechanics Engineer
protruding 3. Maintenance as per
debris manufacturer’s
removed recommendation
3. Barrication 4. Crane’s legal
and with requirement (PMA)
signage 5. Inspection as per check
4. Proper access list
& egress
5. PPEs: safety
helmet, cotton
gloves and
safety shoes
HAZARD IDENTIFICATION RISK ASSESSMENT

LEGAL REQUIREMENT

CONDITION
*** PERSON
STEP SEQUENCE OF BASIC CURRENT RISK RISK CONTROL/ RECOMMENDED
RISK IN CHARGE
NO JOB STEP CONTROL ACTION AND DATE
* ** RANKING
HAZARD EFFECT
LIKE SEV

SCORE

LEVEL
2 Mobilization of A NR 1. Hit by moving Major injury 1. Operator’s 3 9 M 1. Site
machineris machi-neries COTT 1. Operator with valid Engineer
2. Property 2. Trained COTT 2. SHO
3. damage signalman 2. Well trained signalman
3. Proper 3. Workers with lifting
supervision work experience
4. Regular training for
lifting crews
5. Proper supervision by
PICs

3 Parking of crane A NR 1. Toppling of Major injury 1. SWMS & SWP 2 3 6 M 1. Site civil
during operation crane 2. Ground 1. Comply with SWMS and supervisor
2. Hit by Property inspection SWP 2. SHO
3. Struck by damage 3. Safety 2. Parked on stable ground
4. Soft ground clearance 3. Operator to follow
5. Electro-cution transmission instruction
lines 4. Fully extend the out
4. Barrication & riggers on the timber/
signage steel paddings
5. Strictly to use steel
plates if the grounds is
soft
6. Barricade with signage
7. PPEs: safety helmet,
shoes
HAZARD IDENTIFICATION RISK ASSESSMENT

LEGAL REQUIREMENT

CONDITION
*** PERSON
STEP SEQUENCE OF BASIC CURRENT RISK RISK CONTROL/ RECOMMENDED
RISK IN CHARGE
NO JOB STEP CONTROL ACTION AND DATE
* ** RANKING
HAZARD EFFECT
LIKE SEV

SCORE

LEVEL
4 Parking of load A R 1. Obstructions Major injury 1. Traffic 2 2 4 L 1. No obstruction during 1. Site
loaders/ lorries 2. Struck by boom controller loading and unloading supervisor
3. Knock by crane Property 2. Signalman works
damage 3. Trainings 2. Traffic controller to
4. Barrication maintain the swift flow
with signage of vehicles
3. Clear views between
signalman and the
operator
4. Regular training for
lifting work crews
5. Barricade with signage
the working area
5 A R 1. Under capacity Major injury 1. Capacity 2 3 6 M 1. Check weight of load 1. Site
Loading and crane rated crane and use only rated crane supervisor
unloading 2. Collision of Property 2. Traffic 2. Signalman to guide truck
vehicle damage controller into crane position
3. Struck by lifting 3. Trained 3. Hold hooks by the
gears signalman handle
4. Finger pinch in 4. Regular 4. Do not readjust hook
between loads training for after load is lifted
5. Loads snap off lifting crews 5. Watch for swinging
6. Knocked by 5. Supervisions loads
swinging loads 6. Barrication 6. Proper PPEs: safety
with signage helmet, safety shoes &
7. Proper PPEs leather gloves
7. Stay clear of swinging
path and watch for the
movement of swing
Legends

A – Occupational Safety and Health Act 1994


B – OSH (Classification, Packaging and Labeling of Hazardous Chemicals) Regulations 1997
C – OSH (Prohibition of Use of Substance) Order 1999
D – OSH (Use and Standards of Exposure of Chemicals Hazardous to Health) Regulations 2000
E – OSH (Notification of Accident, Dangerous Occurrence, Occupational Poisoning and
Occupational Disease) Regulations 2004
F – Factories and Machinery Act 1967
G – FM (Steam Boiler and Unfired Pressure Vessel) Regulations 1970
H – FM (Electric Passenger and Goods Lift) Regulations 1970
I – FM (Fencing of Machinery and Safety) Regulations 1970
J – FM (Safety, Health and Welfare) Regulations 1970
K – FM (Notification, Certification of Fitness and Inspection) Regulations 1970
L – FM (Building Operations and Work of Engineering Construction) (Safety) Regulations 1986
M – FM (Noise Exposure) Regulations 1989
N – Arm Act 1960

Conditions
R – routine
NR – non routine
Likelihood (L) Score

Most likely The most likely result of the hazard/ event being realized 5

Possible Has a good chance of occurring and is not unusual 4

Conceivable Might be occur at sometime in future 3

Remote Has not been known to occur after many years 2

Inconceivable Is practically impossible and has never occurred 1

Severity (S) Score


Numerous fatalities, irrecoverable property damage and
Catastrophic 5
productivity
Approximately one single fatality major property damage if hazard is
Fatal 4
realized
Serious Non-fatal injury, permanent disability 3
Minor Disabling but not permanent injury 2
Negligible Minor abrasions, bruises, cuts, first aid type injury 1
Risk Priority Number (RPN) = (L * S)

Where L = Likelihood
S = Severity

RPN Score Control Measures


A risk identified as LOW may be considered as acceptable and further reduction may not
Green
be necessary. However, if the risk can be resolved quickly and efficiently, control
(1-4)
measures should be implemented and recorded.
A MEDIUM risk requires a planned approach to controlling the hazard and applies
Orange
temporary measure if required. Actions taken must be documented on the
(5-12)
risk assessment form including date for completion.
A HIGH risk requires immediate action to control the hazard as detailed in the hierarchy
Pink of control. Actions taken must be documented on the risk assessment form including date
(15-25) for completion.

Severity (S)

Likelihood (L) 1 2 3 4 5

5 5 10 15 20 25

4 4 8 12 16 20

3 3 6 9 12 15

2 2 4 6 8 10

1 1 2 3 4 5
Type of job: Plumbing and Sanitation Installation
Job Safety Analysis
Date: 13/9/2019

Personal Protective Equipment to be worn: Safety boot, safety vest, safety helmet & hand glove

Basic Job Steps Potential Hazards Recommended Action or Procedure

1. Examine the location 1. Trip and fall 1. Routine maintenance check list
2. Maintenance by competent mechanics
3. Maintenance as per manufacturer’s
recommendation
4. Crane’s legal requirement (PMA)
5. Inspection as per check list
2. Mobilization of 2. Hit by moving 1. Operator with valid COTT
machineries machineries 2. Well trained signalman
3. Workers with lifting work experience
4. Regular training for lifting crews
5. Proper supervision by PICs

3. Parking of crane during 1. Toppling of crane 1. Comply with SWMS and SWP
operation 2. Hit by 2. Parked on stable ground
3. Struck by 3. Operator to follow instruction
4. Soft ground 4. Fully extend the out riggers on the timber/
5. Electrocution steel paddings
5. Strictly to use steel plates if the grounds is soft
6. Barricade with signage
7. PPEs: safety helmet, shoes

4. Parking of load loaders/ 1. Obstructions 1. No obstruction during loading and unloading


lorries 2. Struck by boom works
3. Knock by crane 2. Traffic controller to maintain the swift flow of
vehicles
3. Clear views between signalman and the
operator
4. Regular training for lifting work crews
5. Barricade with signage the working area

5. Loading and unloading 1. Under capacity crane 1. Check weight of load and use only rated crane
2. Collision of vehicle 2. Signalman to guide truck into crane position
3. Struck by lifting gears 3. Hold hooks by the handle
4. Finger pinch in 4. Do not readjust hook after load is lifted
between loads 5. Watch for swinging loads
5. Loads snap off 6. Proper PPEs: safety helmet, safety shoes &
leather gloves
7. Stay clear of swinging path and watch for the
movement of swing
APPENDICES
Contract No. : RFI Form No.:
Project : SIBIYU 132/33kV SUBSTATION
PLS-150129
Client : SARAWAK ENERGY BERHAD Date: Rev. No. :A
REQUEST FOR INSPECTION FORM
Requested by : Received by :

Date/Time : Date/Time :

The following works are/ will be ready for inspection at ________________(time) on ___________________(date )
COLD WATER INSTALLATION WORKS
Zone :________________________ Structure Element :______________________
Gridline :________________________ Level :______________________
A Inspection Items
Acceptability
Item No. Description Remarks & Rectification
Yes No
1 Pipe sleeve installed as per stated size in the drawing
2 Pipe installation based on approved drawings
3 Pipe material as to specification
4 Pipe support/hanger
5 Correct Valve use
6 No visible damage
7 Leakage test is conducted
8 Pressure test is conducted
9 Underground crossing pipe material to specification
10 Pipe properly concealed
11 Water tank location & Installation (if any)
12 Water Tank accessories is in good condition (if any)

B Inspection Response
Inspection passed, works are allowed to proceed.
Remedial work listed to be carried out. No further inspection required.
Remedial work listed to be carried out. Re-inspection required.

C Remedial Action

Prepared / Inspected by: Verified by: Witness by:

____________________ ____________________ ______________________


Site Engineer COW / QAQC Engineer Client Representative
Name: Name: Name:
Date : Date : Date :
RFI Form No.:
Project : SIBIYU 132/33kV SUBSTATION Contract No.: PLS-150129

Client : SARAWAK ENERGY BERHAD Date: Rev. No. :A


REQUEST FOR INSPECTION FORM
Requested by : Received by :

Date/Time : Date/Time :

The following works are/ will be ready for inspection at ________________(time) on ___________________(date )
PLUMBING & SANITARY INSTALLATION WORKS
Zone :________________________ Structure Element :______________________
Gridline :________________________ Level :______________________
A Inspection Items
Acceptability
Item No. Description Remarks & Rectification
Yes No
1 Pipe sleeve installed at specified size
2 Pipe installation based on approved drawings
3 Pipe material as to specification
4 Pipe support/hanger
5 No visible damage
6 Leakage test is conducted
7 Flow test is conducted

B Inspection Response
Inspection passed, works are allowed to proceed.
Remedial work listed to be carried out. No further inspection required.
Remedial work listed to be carried out. Re-inspection required.

C Remedial Action

Prepared / Inspected by: Verified by: Witness by:

____________________ ____________________ ______________________


Site Engineer COW/ QAQC Engineer Client Representative
Name: Name: Name:
Date : Date : Date :