Method Statement For Road OBJECTIVE: Preparation of Sub-Grade, Laying of Sub-Base, Water Bound Macadam

1. The document provides a method statement for road preparation including sub-grade preparation, laying of sub-base and water bound macadam. 2. Key steps include excavating the sub-grade, compacting in layers, laying sub-base in two 100mm layers, and laying water bound macadam in two 75mm layers with rolling and binding materials. 3. The method statement outlines responsibilities for quality checks and sign off at each stage of the process.

Uploaded by

Ranjit Singh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
190 views

Method Statement For Road OBJECTIVE: Preparation of Sub-Grade, Laying of Sub-Base, Water Bound Macadam

1. The document provides a method statement for road preparation including sub-grade preparation, laying of sub-base and water bound macadam. 2. Key steps include excavating the sub-grade, compacting in layers, laying sub-base in two 100mm layers, and laying water bound macadam in two 75mm layers with rolling and binding materials. 3. The method statement outlines responsibilities for quality checks and sign off at each stage of the process.

Uploaded by

Ranjit Singh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 8

L&T/UHDE/ROAD/P-10

LARSEN & TOUBRO LIMITED


ECC DIVISION
PROJECT: CIVIL WORKS FOR OFFSITE- Page 8 of 8
QUALITY
UTILITIES AT MRPL
MANAGEMENT
SYSTEM

METHOD STATEMENT FOR ROAD

OBJECTIVE: Preparation of sub-grade, laying of sub-base, water bound macadam,


bituminous & seal coat for roads.

REFERNCE: Client/Consultant AFC Drawings

INSTRUMENTS: Theodolite, Leveling Instruments, Line Dories, Templates, Water Tankers,


Rollers, Bitumen Heating Stoves, Templates Etc.,

Sl. No. Procedure Responsibility Check By Record


1 Check aggregates and bitumen QC QC Engineer Test Reports
for complying with specification Engineer
and BOQ items
2 Ensure all the approved Site Site Engineer
construction drawings are Engineer
available to mark the layout of
roads
3 Ensure all the record crossings, Site Site Engineer
cable crossings, pie crossings Engineer
and storm water drains culvert
works are completed in all
respects.
4 Remove all the materials stacked Site Site Engineer
in the areas of the layout of the Engineer
road.
5 Identify the camber of the roads Site Site Engineer
either one side or both side Engineer
camber depending upon the easy
draining of water from roads.
6 Mark the layout of the roads on Site Site Engineer
the ground along with the Engineer
curves.

A) (1) SUB-GRADE Site Site Engineer


Excavate to depth of 350-mm Engineer
and remove any foreign
substances, vegetation and loose
patches and dress to the shape of
camber and slopes.

REVISION NO. 0
DATE 27.07.05
APPROVED BY
L&T/UHDE/ROAD/P-10
LARSEN & TOUBRO LIMITED
ECC DIVISION
PROJECT: CIVIL WORKS FOR OFFSITE- Page 8 of 8
QUALITY
UTILITIES AT MRPL
MANAGEMENT
SYSTEM

B) Sprinkle slightly the water on sub-grade and Site Site Engineer


roll the sub-grade surface with 10 tonnes Engineer
capacity power rollers till the soil evenly
compacted to 95% of proctor density

C) Start the rolling operation from the edges Site Site Engineer
and proceeding towards center overlapping Engineer
with preceding passes to obtain required
camber pass.

D) After completion of rolling check the sub- Site Site Engineer


grade with templates placed at regular Engineer
intervals for required camber.

E) Dress the undulation developed during Site Site Engineer


rolling with earth and roll again the dressed Engineer
surfaces.

(2) SUB-BASE

A) Ensure the sub-grade is completely dry Site Site Engineer


before start to lay the sub-base. Engineer

B) In no case the aggregates shall be dumped Site Site Engineer


directly on the prepared surface. Engineer

C) Ensure the width of the sub-case course


shall be 150mm more on either side than of Site Site Engineer
the water bound macadam-weaving course. Engineer

D) The sub-base shall be laid on two layers to Site Site Engineer


compacted thickness of 200mm Engineer

REVISION NO. 0
DATE 27.07.05
APPROVED BY
L&T/UHDE/ROAD/P-10
LARSEN & TOUBRO LIMITED
ECC DIVISION
PROJECT: CIVIL WORKS FOR OFFSITE- Page 8 of 8
QUALITY
UTILITIES AT MRPL
MANAGEMENT
SYSTEM

E) Keep the template at regular Site Site Engineer


intervals to maintain the cambers Engineer

F) Lay the First two layers with tested Site Site Engineer
and approved grade – 1 aggregate to Engineer
a thickness of 100m each.

G) Start the rolling with power rollers Site Site Engineer


of 10-12 tonnes capacity from edges Engineer
and gradually progressing towards
center by overlapping the preceding
passes.

H) Apply the murrum screens gradually Site Site Engineer


on the surface to completely fill the Engineer
voids in the aggregates.

I) Dry rolling shall be done Site Site Engineer


accompanied by brooming Engineer
screenings shall not be damp or wet
at the time of application.

J) After complete application of the Site Site Engineer


screenings the surface shall be Engineer
sprinkled with water, swept and
rolled.

K) Sprinkle the water on surface and Site Site Engineer


continue the rolling operation with Engineer
sprinkling of water with sweeping
with additional screenings applied as
necessary until the coarse aggregate
has become well bonded and firmly
set its full depth and a grout has
been formed of the screenings.

L) Ensure the first layer fully set to the Site Site Engineer
satisfaction, lay the second layer in Engineer
the same procedure to obtain the
compacted thickness of 100mm

REVISION NO. 0
DATE 27.07.05
APPROVED BY
L&T/UHDE/ROAD/P-10
LARSEN & TOUBRO LIMITED
ECC DIVISION
PROJECT: CIVIL WORKS FOR OFFSITE- Page 8 of 8
QUALITY
UTILITIES AT MRPL
MANAGEMENT
SYSTEM

A) (3) WATER BOUND MACDUM COURSE Site Site Engineer


Check the finished surface of sub-base for Engineer
correct camber and slopes and carry out any
rectification and repairs if required.

B) Clear the surface of sub-base free of dust and Site Site Engineer
other extraneous materials Engineer

C) Spread Grade – II aggregates in two layers Site Site Engineer


and compacted thickness should be of 75mm Engineer
each.

D) Following the spreading of the coarse Site Site Engineer


aggregate, rolling shall be started with 8 to 10 Engineer
tonnes capacity.

E) Rolling shall be started from edges and Site Site Engineer


gradually progressing towards the centre by Engineer
overlapping the preceding passes to obtain
correct camber except on super-elevated
portions.

F) For super-elevated portion rolling should be Site Site Engineer


started from inner edge and proceeding Engineer
towards outer edge.

G) Apply the binding materials gradually over Site Site Engineer


the surface to completely fill the inter-sites. Engineer
Binding materials shall not be wet or damp at
the time of application.

H) The rate of spreading binding materials shall Site Site Engineer


not be less than 3 m3 to 4.5 m3 / 100m m3 Engineer
Accompanied by dry rolling and brooming
until no more binding material can be forced
into the voids of the coarse aggregate.

REVISION NO. 0
DATE 27.07.05
APPROVED BY
L&T/UHDE/ROAD/P-10
LARSEN & TOUBRO LIMITED
ECC DIVISION
PROJECT: CIVIL WORKS FOR OFFSITE- Page 8 of 8
QUALITY
UTILITIES AT MRPL
MANAGEMENT
SYSTEM

Site Site Engineer


I) Sprinkle the water on the surface and Engineer
sweep with brooms to make even
surface.

J) Continue the rolling operation with Site Site Engineer


water sprinkling & brooming with Engineer
additional binding materials necessary
until the coarse aggregate had been
thoroughly keyed, well-bounded and
firmly set in its full depth and a grout
has been formed of binding materials.

K) After the final compaction of WBM Site Site Engineer


course allow road to dry. Any hungry Engineer
spots shall be filled with binding
materials & lightly sprinkle with
water in necessary and rolled to
obtain the compacted thickness of
80mm.
L) Site Site Engineer
No traffic shall be allowed on the road Engineer
until the macadam set.
M) Site Site Engineer
Allow the WBM surface to Engineer
completely dry and set for some
duration. Site Site Engineer Joint record for
N) Engineer completion
Check the camber of WBM surface
with templates and levels.

(4) BRUSHING AND CLEANING


A) Site Site Engineer
Ensure the WBM surface is Engineer
completely dry and set.
B) Site Site Engineer
Clean the WBM surface with brooms Engineer
and coir brushes to remove all excess
binding materials and to expose the
aggregates surfaces visible

(5) SEMIGROUT SURFACE


A) Ensure all the surface of WBM cleaned and Site Site Engineer
REVISION NO. 0
DATE 27.07.05
APPROVED BY
L&T/UHDE/ROAD/P-10
LARSEN & TOUBRO LIMITED
ECC DIVISION
PROJECT: CIVIL WORKS FOR OFFSITE- Page 8 of 8
QUALITY
UTILITIES AT MRPL
MANAGEMENT
SYSTEM

all loose and foreign matter removed. Engineer

B) Keep the templates at equal intervals to Site Site Engineer


spread the aggregates to correct camber. Engineer

C) Ensure to prevent the aggregate from mixing Site Site Engineer


or being coated with dust or any objectionable Engineer
matter before spreading.

D) Spray a thin layer of bitumen of grade 80/100 Site Site Engineer


for bonding the semi grout surface aggregates Engineer
with WBM surface.

E) Spread the coarse aggregates of size with Site Site Engineer


Metal No. 1 & stone dust at the rate of 2 Engineer
CUM/ 100SQM uniformly to the thickness of
35mm.

F) Roll the surface with 10 tonnes capacity Site Site Engineer


roller, rolling shall be started longitudinally at Engineer
the sides and proceed towards the centre of
the pavement and overlapping on successive
passes.

G) Ensure compacted coarse aggregates shall Site Site Engineer


posses a firm even surface, true to the grades Engineer
and cross sections and present a texture which
will allow uniform penetration of asphalt.

H) If any irregularities appear after rolling, they Site Site Engineer


shall be reminded by loosening the surface Engineer
and removing or adding coarse aggregates
may be required.

FIRST APPLICATION OF BITUMEN.


A) Bitumen of grade 80/100 shall be heated to Site Site Engineer
the temperature of 204˚C by heating with Engineer
pressure stoves.

REVISION NO. 0
DATE 27.07.05
APPROVED BY
L&T/UHDE/ROAD/P-10
LARSEN & TOUBRO LIMITED
ECC DIVISION
PROJECT: CIVIL WORKS FOR OFFSITE- Page 8 of 8
QUALITY
UTILITIES AT MRPL
MANAGEMENT
SYSTEM

B) Ensure before applying bitumen the Site Site Engineer


surface is thoroughly dry for its entire Engineer
depth.

C) Apply the bitumen with pressure Site Site Engineer


distributor so to distribute the bitumen in a Engineer
uniform spray.

D) Apply the bitumen at the rate of 1.5 Kg/m2 Site Site Engineer
liquid seal coat of hot Premix Asphalt Engineer
(80/100 Grade) by pressure distributor and
blinding the surface with Grid and stone
dust at 1 CUM/ 100 SQM and rolling with
10 tonnes smooth wheel roller to proper
camber or super elevation and gradient
etc.

E) The temperature shall be checked often Site Site Engineer


with the thermometer to maintain the Engineer
temperature of bitumen for spraying.

F) The distributor shall be able to spray to Site Site Engineer


normal width of not less than 2 mtrs. Engineer

FILLING SURFACE VOIDS WITH


INTERMEDIATE AGGREGATES

G) After the first application of bitumen and Site Site Engineer


while still in warm, a thin layer of dry Engineer
intermediate aggregate consisting of
12.50mm metal chips shall be spread at
the rate of 21.3m2 /100 m2 and broom
the surface to produce uniform covering.

H) Roll the surface until thoroughly Site Site Engineer


compacted and all intermediate aggregate Engineer
get interlocked.

I) Roll the surface thoroughly until grits get Site Site Engineer
interlocked and uniform in texture. Engineer

REVISION NO. 0
DATE 27.07.05
APPROVED BY
L&T/UHDE/ROAD/P-10
LARSEN & TOUBRO LIMITED
ECC DIVISION
PROJECT: CIVIL WORKS FOR OFFSITE- Page 8 of 8
QUALITY
UTILITIES AT MRPL
MANAGEMENT
SYSTEM

J) Check the surface of the road with the Site Site Engineer Joint record
temperature for correct camber Engineer for
completion
K) Roll the surface with 8 to 10 tonnes Site Site Engineer
capacity smooth wheeled roller with Engineer
minimum of 5 to 6 passes for through
compaction.

L) Continue the rolling operation until all Site Site Engineer


material is firmly bedded in the binder Engineer
and presents a uniform closed surface.

M) Check the road surface for camber and Site Site Engineer
slopes. Engineer

OPENING FOR TRAFFIC] Site Site Engineer


Engineer
N) Traffic shall be allowed on the road
after 24 hours

REVISION NO. 0
DATE 27.07.05
APPROVED BY