Production Scheduling PDF

The document discusses various concepts related to production scheduling including: - Scheduling involves deciding when work will start and be completed over a certain duration. - Factors like customer demand, material availability, and equipment capacity affect scheduling. - The Master Production Schedule (MPS) provides a weekly breakdown of production requirements and is updated continuously. - Operation scheduling involves assigning job orders to machines and deciding the processing sequence using priority rules. - Sequencing rules like shortest processing time and critical ratio are used to schedule jobs on machines.

Uploaded by

Raajitha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
262 views

Production Scheduling PDF

The document discusses various concepts related to production scheduling including: - Scheduling involves deciding when work will start and be completed over a certain duration. - Factors like customer demand, material availability, and equipment capacity affect scheduling. - The Master Production Schedule (MPS) provides a weekly breakdown of production requirements and is updated continuously. - Operation scheduling involves assigning job orders to machines and deciding the processing sequence using priority rules. - Sequencing rules like shortest processing time and critical ratio are used to schedule jobs on machines.

Uploaded by

Raajitha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 21

Scheduling

 When and in what sequence the work will be done


 Involves deciding
- when the work will start
- in certain duration of time how much work will be
completed
 It is time phase of loading (Assignment of tasks or
work to a facility)
Factors affecting scheduling
 External factors:
-Customer demand
-Customer delivery date
-Stock of goods already available with dealers and stockiest
 Internal factors
- Stock of finished goods with firm
- Time interval to process finished goods from raw material
- Availability of material quantity and specification
- Availability of equipment (no. of m/c, capacity)
- Availability of manpower (no. and kind of skills)
Master Production Schedule
 Resembles a central office which
possesses information about all the
orders in hand
 MPS is weekly breakdown of the
production requirement
 As orders are received, they are
marked on master schedule
depending on their delivery dates
 MPS is updated continuously
 It shows the work ahead, yet to be
completed
Advantages of MPS Limitations of MPS
 Simple and easy to  Provides only overall
understand picture
 Can be kept current  Does not give detained
 Low cost to make and information
maintain
 A certain % of weekly
capacity can be allocated for
rush orders

Applications
 In big firm for purpose of loading of entire plant
 In R&D organisations
 Overall planning in foundries, computer centres and repair
shops
Operation Scheduling
 Most important in Job shop production as batch size is very small,
Machines and workers are versatile (can perform different operations

Activities in Operation Scheduling


 Assigning job orders to different machines
 Deciding sequence of processing on different machines (priority rule)
 Planning the route of movement of material during processing
 Issuing dispatch list to various work centers containing info. about
-Work centers a customer order should be processed at,
-The customer order to be processed first,
-Time of processing it should take.
 Tracking progress of various scheduled jobs, revising the schedule in
case of delays.
Problems due to lack of proper scheduling
 Delay in meeting due dates of orders
 High Work-In-Process (WIP) inventory
 High average completion time of job
 No information on the current status of a job
 Low utilization of workers and work stations
 High overall setup time for machines.
 High cost of production/operation
Types of Operation scheduling
 Forward Scheduling
-As early as possible approach to be used for assigning customer orders
-as soon as a work center is free to process a job, they should be assigned
the job.
 Backward scheduling
- Based on As late as possible approach with condition that the jobs get
ready by their due dates
- thus process planning starts with assigning the job to last workstation in
the sequence
- can be useful in case there is some delay in availability of resources
General
machine/m
an loading
Sequencing rules: ‘n’ jobs on one machine
These are required to decide about the sequence of the
jobs on work station
 First Come First Serve (FCFS): Jobs are processed in their sequence
of arrival
 Last Come First Serve (LCFS):
 Due date method: Job with closest due date done first
 Shortest Time of Processing (STP)rule: Jobs with shortest
processing time done first
 Priority based service
 Random method
Sequencing rule contd..
 Critical ratio rule (CR): Jobs with the smallest CR are run first

 CR = time remaining / work remaining


due date of job ‘i’ - today’s date
CRi=
remaining processing time of job ‘i’

• With each passing minute the CR for jobs changes


• Task with shorter remaining time and longest processing
time will get priority
• A job with negative CR (due date already gone) should be
given prioity
Performance measures
 Completion time
 Epoch at which the job is completed
 Makespan
 Completion time of the last job processed
 Lateness and tardiness
 Lateness of job j
 = (completion time of job j)-(due date of job j)
- if it is positive it is tardiness
-if it is negative it is earliness (0 tardiness)
 5 jobs labelled as 1,2 ,3 4 and 5 are to be processed in a
machining centre
 Sequence the jobs by FCFS, STP, Due date method and
Critical ratio methods and compare the results
Job no. Processing time Due date
1 11 61
2 29 45
3 31 31
4 1 33
5 2 32
Sequencing ‘n’ jobs on 2 machines
Johnson’s method
 Johnson's rule is a method of scheduling jobs in two work
centers.
 Its primary objective is to find an optimal sequence of jobs to
reduce makespan (the total amount of time it takes to complete all jobs).
 It also reduces the amount of idle time between the two work
centers.
 The method minimizes the makespan in the case of two work
centers.
 Furthermore, the method finds the shortest makespan in the
case of three work centers if additional constraints are met
Johnson rule contd..
The technique requires several preconditions:
 The time for each job must be constant.
 Job times must be mutually exclusive of the job sequence.
 All jobs must be processed in the first work center before
going through the second work center.
 All jobs are equally prioritized.

https://en.wikipedia.org/wiki/Johnson%27s_rule
Johnson's rule is as follows:
 List the jobs and their times at each work center.
 Select the job with the shortest activity time.
 If that activity time is for the first work center, then
schedule the job first. If that activity time is for the
second work center then schedule the job last.
 Eliminate the shortest job from further consideration.
 Repeat steps 2 and 3, working towards the center of the
job schedule until all jobs have been scheduled.
Example: Each of five jobs needs to go through work center A
and B. Find the optimum sequence of jobs using Johnson's
rule.
Job times (hours)
Job Work center A Work center B
A 3.2 4.2
B 4.7 1.5
C 2.2 5.0

D 5.8 4.0

E 3.1 2.8
Solution
1. The smallest time is located in Job B (1.5 hours).
- Since the time is in Work Center B, schedule this job last.
- Eliminate Job B from further consideration.

? ? ? ? B
2. The next smallest time is located in Job C (2.2 hours).
- Since the time is in Work Center A, schedule this job first.
- Eliminate Job C from further consideration.
C ? ? ? B

3. The next smallest time after that is located in Job E (2.8 hours).
- Since the time is in Work Center B, schedule this job last.
- Eliminate Job E from further consideration.
C ? ? E B

4. The next smallest time after is located in Job A (3.2 hours).


-Since the time is in Work Center A, schedule this job first.
-Eliminate Job A from further consideration.
C A ? E B

5. The only job left to consider is Job D.

C A D E B
So, the jobs must be processed in the order C → A → D → E → B, and must be
processed in the same order on both work centers.
Assignment Method: ‘n’ products on ‘m’ machine
One machine does on job only
1. Perform row reductions
 Subtract minimum value in each row from all other row values
2. Perform column reductions
 Subtract minimum value in each column from all other column
values
3. Line Test
 Cross out all zeros in matrix using minimum number of
horizontal & vertical lines.
 If number of lines equals number of rows in matrix, optimum
solution has been found, stop.
4. Matrix Modification
 Subtract minimum uncrossed value from all uncrossed values &
add it to all cells where two lines intersect. Go to Step 3.
Assignment
Cooker
Example
Food 1 2 3 4
Beans 10 5 6 10
Peaches 6 2 4 6
Tomatoes 7 6 5 6
Corn 9 5 4 10

Row reduction Column reduction Line Test


5 0 1 5 3 0 1 4 3 0 1 4
4 0 2 4 2 0 2 3 2 0 2 3
2 1 0 1 0 1 0 0 0 1 0 0
5 1 0 6 3 1 0 5 3 1 0 5

Number lines <> number of rows so modify matrix


Assignment Example
Modify matrix Line Test

1 0 1 2 1 0 1 2 # lines = # rows
0 0 2 1 0 0 2 1 so at optimal solution
0 3 2 0 0 3 2 0
1 1 0 3 1 1 0 3
Cooker Cooker
Food 1 2 3 4
Beans 1 0 1 2 Food 1 2 3 4
Peaches 0 0 2 1 Beans 10 5 6 10
Tom 0 3 2 0 Peaches 6 2 4 6
Corn 1 1 0 3 Tomatoes 7 6 5 6
Corn 9 5 4 10
l
Orders completed in 6 hours
Total number of hours = 21