CQF Internet User Manual For Suppliers - ENG PDF
CQF Internet User Manual For Suppliers - ENG PDF
Table of contents
1 INTRODUCTION ........................................................................................................... 3
1.1 Definitions ............................................................................................................................. 3
2 FUNCTIONAL ARCHITECTURE ................................................................................... 3
3 CQF HOMEPAGE ......................................................................................................... 5
3.1 User Profiles – Login enabling ............................................................................................5
3.2 "Contact us" function .......................................................................................................... 6
3.3 "Login" function .................................................................................................................... 7
4 ACCESS PROFILE MANAGEMENT ............................................................................. 8
4.1 Change Password .............................................................................................................. 9
5 UPLOADING MANUFACTURING AND CONTROL PLANS ......................................... 10
5.1 List of Manufacturing and Control Plans uploaded ......................................................... 11
6 UPLOADING A PRODUCTION PLAN ..........................................................................13
6.1 List of entered Production Plans ...................................................................................... 15
6.2 Production Plan edit .......................................................................................................... 15
6.3 Production Plan delete ...................................................................................................... 16
7 UPLOADING A TESTING NOTICE ...............................................................................17
7.1 Entering a new Purchase Order ....................................................................................... 18
7.2 Testing notice ..................................................................................................................... 19
7.3 Testing notice products .................................................................................................... 20
7.4 First Category material testing notice confirmation......................................................... 21
7.5 Second and Third Category material testing notice confirmation .................................. 23
7.6 New contact person ........................................................................................................... 27
7.7 List of Testing Notices, modification and cancellation .................................................... 27
8 OFF LINE TESTS (OLT).............................................................................................. 28
8.1 Off Line Tests List ............................................................................................................. 29
9 REPORT ..................................................................................................................... 30
9.1 Analytic Notices Report ..................................................................................................... 30
9.2 Synthetic Report ................................................................................................................ 31
9.3 Manufacturing and Control Plans Report ........................................................................ 31
9.4 Production Plans List ......................................................................................................... 31
9.5 Documents Reports ........................................................................................................... 32
10 QUALITY APPROVAL ..............................................................................................32
10.1 First category materials ..................................................................................................... 33
10.1.1 Factory/Site Acceptance Tests performed without the presence of Enel
Inspectors................................................................................................................................... 33
10.1.2 Factory/Site Acceptance Tests performed in the presence of Enel Inspectors ....39
10.2 Second and Third Category Materials ............................................................................. 43
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 1/63
Scope: CQF User Manual for Suppliers
10.2.1 Factory/Site Acceptance Tests not First Supplies performed without the presence
of Enel Inspectors ...................................................................................................................... 43
10.2.2 Factory/Site Acceptance Tests in First Supplies performed without the presence
of Enel Inspectors ...................................................................................................................... 47
10.2.3 Factory/Site Acceptance Tests performed in the presence of Enel Inspectors .... 53
10.2.4 Factory/Site Acceptance Test not First Supplies with Documental Verification ...56
10.3 Factory/Site Acceptance Test with negative outcome.................................................... 61
10.4 Testing Notices search tool............................................................................................... 61
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 2/63
Scope: CQF User Manual for Suppliers
1 INTRODUCTION
Supplies purchased under a contract between Enel and the Supplier are subject to a quality
verification process concerning the supply of the ordered material.
The internet area contains a web application http://CQF.CESI.IT that allows the Supplier to
enter:
- Contracts
- Manufacturing and Control Plans (MCP)
- Production Plans (PP)
- Testing notices
- Offline testing (OLT)
without the need to send them by fax or email, with the aim of making the data entered
homogeneous and controlled.
1.1 Definitions
- Contract: is the essential element that governs the entire supply (from manufacturing
and control plans to testing and offline testing) A contract between ENEL and a supplier
entails the procurement of a set of products that ENEL, in relation to a series of
conditions, must test to check quality of supply.
- Testing category: ENEL has classified materials, grouping them into "Testing
categories", in order to identify the priorities at stake: e.g. products belonging to the
"Testing category 1" must be systematically tested, while those of "Testing Category 2"
are materials that must be subjected to first supply testing.
- First supply: The materials within the scope of a contract that have not been tested yet
and are considered First Supply.
- Manufacturing and Control Plan: document issued by the Supplier and to be sent to
Enel, uploading them to the Internet site, describing the production process phases,
performed controls, sampling plans, adopted instruments and control responsible.
- Production plans: data set that indicates the production lot in terms of quantity per
product and production time schedule (date of production start and end).
- Factory Acceptance Test: the process includes:
1. Testing notice sent to Enel by the Supplier
2. Test scheduling by ENEL
3. Test execution with definition of results for each material
4. Issue of a PDF module containing all outcomes, any non-conformities and remarks
associated with testing.
- Offline Test: starting from a Factory Acceptance Test, Enel can decide whether to plan
an offline test session at the facilities of the supplier, independent of the Factory
Acceptance Test, by sampling materials. The supplier can subsequently arrange an
Offline Testing session, entering the time bracket for all tests.
2 FUNCTIONAL ARCHITECTURE
The interactions between information entered by the Supplier and those entered and
subsequently managed by Enel personnel constitute the following configuration:
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 3/63
Scope: CQF User Manual for Suppliers
http://cqf.cesi.it
Enel
Personnel
Internet footprint
Production Plans checks
schedule
Manufacturing and Offline testing schedule
control plans Reports, testing, Offline
Production plans testing schedule
Testing notices Issues PDF reports
Offline testing
For a correct use of the web application, use preferably Internet Explorer 8 or higher as
browser.
The application opens pop-up windows, meaning that the pop-up blocker must not be enabled.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 4/63
Scope: CQF User Manual for Suppliers
3 CQF HOMEPAGE
The homepage language can be modified by clicking the flag symbols on top right corner of
the site. The site is available in Italian, English and Spanish.
The CQF logo is shown on the bottom along with a banner that will contain messages entered
by the site Administrator.
The Supplier can access the platform only if the access credentials (Username and Password)
has been previously required to Enel and if Enel issued and sent them to the Supplier. Enabled
users can access the functions associated with their profiles by entering their credentials and
clicking the “Login” button (attention: letter case sensitive).
Suppliers that have not been enabled can use the function “Contact us”. Enel authorized
personnel will create a user profile.
Note: Different profiles can be created for the same user (Supplier, Tester, Administrator of the
site).
After being enabled for access to the website, the Supplier will receive Username and
Password via email: the latter is generated automatically and randomly by the software and is
encrypted in the data archive. The Supplier can edit it later.
A single Supplier could have several users enabled, accessing the same information such as
contracts, manufacturing and control plans; testing notices, etc. but this does not concern
access profile data that remain exclusive to the user.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 5/63
Scope: CQF User Manual for Suppliers
The application will send an email to the Enel personnel site administrators by clicking the
"Enter" button, making sure that all fields have been filled in.
Contacts
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 6/63
Scope: CQF User Manual for Suppliers
Press the "Login" button after entering your personal access credentials to log into your
dedicated functional area.
- The Username appears in the top right corner, the profile is below the user's email
address;
- A toolbar containing all of the menu options to access the various functions is displayed
at the bottom in the middle;
- A message in Italian and English (which can be set by the site admin. during setup) is
displayed in the functional area.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 7/63
Scope: CQF User Manual for Suppliers
The following menu sub-items appear when moving the cursor over "My profile":
After filling in the fields in white, press "Save" and the data archive will be updated with the
information provided by the supplier.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 8/63
Scope: CQF User Manual for Suppliers
In case of forgotten password, in the site homepage it is possible to click on “Have you forgot
the password? Click here.”
Insert the username and click on “Reset password”. The platform will issue and send a new
password to the username e-mail address, with which, through a link, the password can be
modified.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 9/63
Scope: CQF User Manual for Suppliers
To enter a new Manufacturing and Control Plan (MCP), select the "PFC" menu item and then
the sub-item “New”:
The purchase contract number should be available in the Suppliers contracts list. In case the
purchase contract is not available in the contracts list, the Supplier has to require to Enel the
contract uploading.
By typing “%” in the Contract field accesses the complete list of the Supplier's contracts:
The contract can be selected by clicking the following icon in the last column on the right.
Once the contract has been selected, the user accesses the web page from which the file will
be loaded.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 10/63
Scope: CQF User Manual for Suppliers
in which the user can add a Manufacturing and Control Plan title and its description, and above
all, upload a file using the button “Browse”.
Maximum file size is <= 5 MBytes. The extension must be standard (pdf, xls, doc, ppt) in order
to open it in the web browser, otherwise it must be downloaded (as for a .zip file) and opened
by using a tool on the user's PC.
Once the file has been selected, press “enter” to load the sheet and the physical file onto the
server of the Internet CQF (the file upload date is archived automatically).
A manufacturing and control plan sheet can be modified until it has not been imported into the
Enel Intranet by authorised Enel personnel.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 11/63
Scope: CQF User Manual for Suppliers
The manufacturing and control plan is not subjected to any particular workflow, and is only a
document connected to a purchase contract.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 12/63
Scope: CQF User Manual for Suppliers
To enter a new Production Plan select the "PDC" menu item and then the sub-item “New”.
Now enter the contract code to which the Production Plan is associated with, or % to visualize
all of the supplier's contracts associated with the user.
Information on active blocks may appear below the title "Enter a new Production Plan" on the
top, i.e. in the example above:
The production end date of the Production Plan (that will be determined as
maximum date among the product end date of production) must be in compliance
with the applicable contractual annexes.
The production start date of the Production Plan (that will be determined as
minimum date among the product start date of production) must be in compliance
with the applicable contractual annexes.
The user must then select (mandatory fields):
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 13/63
Scope: CQF User Manual for Suppliers
The user can also select a PO (Purchase Order) and enter notes.
Once a Production Plan has been entered, an email will be sent to Enel as notice of the new
entry.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 14/63
Scope: CQF User Manual for Suppliers
In the case of Production Plans that have not yet been imported by Enel, the object will appear
with the "Oper" column with two icons, as shown in the following image:
The unique number of the Production Plan is shown along with the date, the user who
uploaded the Plan and the revision number.
The other information can be edited. A new product can be added, or the user can edit the
quantity and the date of production of a product that has already been entered.
The “Log” of the actions performed on the Production Plan can be accessed.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 15/63
Scope: CQF User Manual for Suppliers
A Production Plan can be deleted, until being imported, by using the icon .-
Once a Production Plan has been deleted, an email will be sent to Enel as notice of the
deletion.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 16/63
Scope: CQF User Manual for Suppliers
Before entering a testing notice, a contract and one of the PO (purchase orders) correlated to it
must be selected. The Supplier selects "Notices" and the sub-item "New" from the task bar to
access the following mask:
Now the supplier must enter the alphanumeric code corresponding to the contract with Enel
into the "Contract" field. The user can also enter part of the contract's code, or a time bracket
in which the "issue date" of the contract is included. Leaving the criteria blank and by clicking
the "Search" button, will call up the complete list of contracts that Enel has taken out with the
Supplier. Once the search criteria has been entered, a list of contracts that satisfies the
selection criteria will be shown:
To select a contract click the icon to select the PO to which the testing notice must be
attached. If the PO does not exist in the list, the Supplier can create a new one by pressing
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 17/63
Scope: CQF User Manual for Suppliers
The date can be selected from a calendar by pressing the icon next to the date field.
Use the top left arrows to browse the months, or select a month by clicking on the arrow next
to the name of the month so that a month dropdown menu appears.
The year can be selected by pressing the arrow to the right of the year so that a dropdown
menu opens to select a year.
Lastly, the user must select a day by clicking the desired number: at this point, the calendar
will disappear, and the "date" field will appear automatically filled in the correct format
"dd/mm/yyyy."
The date of the PO must be equal to or later than the issue date of the contract.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 18/63
Scope: CQF User Manual for Suppliers
A summarising row will appear at the top in read-only mode, which indicates the active blocks
(in the illustration above the test must have a testing start date > 14/07); the contract date, the
category and the PO code all follow on the row below.
The testing notice input fields will appear below:
“Notice ID” – code that the supplier uses to identify the document of reference; it must
be unique and not exist in the archive.
“Testing Dt” – period scheduled for the testing composed by two dates that can be
selected through the calendar selected with the icon
“Production Factory” – name of the plant selectable from a list; if this is a plant not in
the list, the user can create a new one by selecting the icon next to the dropdown menu
“Email send testing report if different” – alphanumeric field in which the user must enter
an email address in the format [email protected] if Enel must send the testing report
to an email different from the email address of the supplier or contact person.
“In plant", the name of the plant must be entered in the "plant" field if the test must be
performed in the plant
“Liaison officer” – selectable from a list, but a new liaison officer can be entered by
clicking on the icon next to the menu.
“Testing notice notes” – alphanumeric field in which the supplier can enter free-format
text.
The "Notice date" is a field managed by the SW and indicates the date of entry of the
notification, while "Revision No." increases automatically after every change.
Attention: The testing start date must be equal to or later than the current date plus the
advance notice period that depends on the testing category assigned by Enel personnel to the
relative contract. The user must pay close attention when entering this date. All exceptions
must be established with an Enel liaison officer to correctly complete the testing notice
process.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 19/63
Scope: CQF User Manual for Suppliers
The example shows a product related to the supplier linked to the selected contract. Those
already selected in the test will not have the "Select" button, while all of the others will. The
columns indicate:
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 20/63
Scope: CQF User Manual for Suppliers
The First Supply is automatically managed by the platform, as is the unit of measurement if
dealing with a unified product (meaning that it is associated with an Enel code).
Once entered these information, press "Save" otherwise the data will not be archived. After
data has been saved, the testing notice template will appear again with the list of products
updated.
Aside from the information entered, an "S" will appear under the "First Supply" column for a
First Supply product.
A product entered by mistake can be deleted by pressing the icon to the right, under the
"Operations" column.
At this point, the testing notice filling is completed: by clicking on “Save”, two different screens
depending on the material category. After this phase that requires confirmations to the
Supplier, the testing notice will be archived and sent to the Enel personnel to be managed.
The Testing Notice uploading process in the CQF Internet website (cqf.cesi.it) has been
modified. The steps required by the CQF Internet are unmodified until the Testing Notice
saving step, through the “Save” button.
In the saving phase, the CQF Internet (following named as system), requires to confirm that
the Factory is Qualified by Enel, if required and that for all the materials for which it is required
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 21/63
Scope: CQF User Manual for Suppliers
the Technical Conformity Assessment, the documents approved by the Enel Group companies
are available for the possible Enel Inspectors verification.
Click check box “The Supplier has read and understood this declaration about the Testing
Notice”.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 22/63
Scope: CQF User Manual for Suppliers
The Testing Notice uploading process in the CQF Internet website (cqf.cesi.it) has been
modified. The steps required by the CQF Internet are unmodified until the Testing Notice
saving step, through the “Save” button.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 23/63
Scope: CQF User Manual for Suppliers
The Suppliers declares that at the at the proposed starting date factory/site acceptance test::
All the components/materials (types and quantities) will be available for the repetition of
acceptance tests;
All acceptance tests required by Enel technical contractual specifications were carried
out correctly and positively passed;
All test reports are filed and available for the Inspectors Enel;
The factory is qualified by Enel, if required;
For all the materials for which it is required Technical Conformity Assessment, the
documents approved by the Enel Group companies will be available for the possible
CMQ Inspectors verification
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 24/63
Scope: CQF User Manual for Suppliers
Click check box “The Supplier has read and understood this declaration about the Testing
Notice”.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 25/63
Scope: CQF User Manual for Suppliers
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 26/63
Scope: CQF User Manual for Suppliers
The name of the person along with their phone number or email address must be entered in
the "Contact information" field.
The "Operations" column allows the user to edit and delete only notices that
The test modification will allow the user to make any changes.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 27/63
Scope: CQF User Manual for Suppliers
Enel reserves the right to activate an Off Line Test procedure (OLT), planning the material
selection in the Supplier production plant. Once Enel has created the OLT, the Supplier can
communicate to Enel the period in which perform the tests.
By accessing the “PFL” item, in the sub-item “Nuovo” the list of OLT created by Enel appears,
this list can be managed by the Supplier in order to assign the testing dates:
By clicking on the icon the user can access the following menu:
The date information can be inserted directly in the input field in the dd.mm.yyyy format or by
using the calendar through the icon .
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 28/63
Scope: CQF User Manual for Suppliers
In case the OLT has not yet been managed and reported by Enel, the user can to modify the
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 29/63
Scope: CQF User Manual for Suppliers
9 REPORT
The search criteria are useful for the user in order to filter the testing notices extraction:
Time bracket in which the tests start date is included
Time bracket in which the testing notice date of issue is included
Material testing category, linked to contract
Status: to treat (means that Enel personnel has not completed testing management),
treated by Enel (means that the process has been completed)
Production Plant selectable from the list
Contract: text, even partial, to help selecting the contacts concerning to the entered testing
notices
Pressing "Search" calls up the report as shown above: this list also contains the date of the
last changes uploaded in the platform by the supplier.
This report can be printed by pressing “Print" or can be downloaded as a Microsoft Excel file.
The presence of a date in the column “Supplier outcome” means that the Supplier correctly
uploaded the tests outcome in the platform.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 30/63
Scope: CQF User Manual for Suppliers
The search criteria support the user to filter the extraction information as targeted by the user:
By clicking "Search”, the above-shown report is available: this list shows the number of testing
notices entered by the Supplier (by one or more users correlated to the same Supplier),
expired testing notices (that have test end date previous to the current date) and tests
scheduled by Enel personnel as well as those reported. Lastly, tests are shown divided by
positive and negative results.
This report can be printed by pressing “Print" or downloaded as a Microsoft Excel file.
The "Status" allows the user to visualize the Manufacturing and Control plans that can be
edited (not imported by Enel) as well as those already imported. The icon in the last column
allows the user access to the document attached to the Manufacturing and Control Plan.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 31/63
Scope: CQF User Manual for Suppliers
By clicking on the icon in the first column, the Production Plan detail is available in read-only.
The folders containing the documents will appear beneath the title "Documents"; the example
folder is called "test". Clicking on “+” opens the list of documents belonging to the folder.
In the example, the folder “test” contains only one document, the file “titolo”. Aside from the
name of the document, the size in kilobytes and the date in which the file was uploaded to the
folder will be shown.
The document can be downloaded by the user for use and consultation.
10 QUALITY APPROVAL
The new implementations available on cqf.cesi.it system require to the Supplier to print a
document (Quality Approval) and to attach it to the transport documents of components and
materials supplied to Enel.
At the end of the components and materials testing process, the Supplier declares that all the
acceptance tests required by Enel contractual technical specifications were performed with
positive outcome in accordance with the ENEL technical specifications and proceed with the
following steps:
- Upload in the system the tests outcome (EF) performed with or without the Enel
Inspectors presence;
- Save the Quality Approval document, confirming the uploaded results (EF) (for tests
performed without the Enel Inspectors presence and not subject to Documental
Verification;
- Print the Quality Approval (QA) document and to attach it to the transport documents.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 32/63
Scope: CQF User Manual for Suppliers
The present user manual provides the information and the main steps to follow in order to
complete the above tasks and to obtain the Quality Approval.
At the end of the Factory/Site Acceptance Test (during the last day noticed in the Testing
Notice), if all the tests required in the Enel Contractual Specification, applicable Annexes and
in the Contract have been performed with positive outcome, click on the symbol “EF”:
The Supplier will fulfill in the “SO” column, for each material ID included in the Testing Notice,
the Factory Acceptance Test outcome (OK/KO).
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 33/63
Scope: CQF User Manual for Suppliers
The Supplier can add an optional text with eventual comments or clarification related to the
factory or site acceptance test, in the “Note Outcome Supplier” field. The system requires the
correct tests execution confirmation.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 34/63
Scope: CQF User Manual for Suppliers
Click on “OK”.
Subsequently, the Supplier has to click on the following button, with which the Supplier
communicates to the Enel Group distribution company owner of the contract, the tests
completion.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 35/63
Scope: CQF User Manual for Suppliers
The system requires to confirm the correct execution of the tests and to Click on "Confirm and
save".
Click on “OK”.
The Supplier will receive an e-mail (to the e-mail address provided to Enel in the CQF
registration phase), in which the system provides the information related to the test reports
recipient (Enel references) in order to allow the Enel verification.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 36/63
Scope: CQF User Manual for Suppliers
The system highlights the factory acceptance tests for which the test report transmission to
Enel is required, with the following symbol:
The Supplier has to wait the Documental Verification outcome performed by Enel.
At the end of the Documental Verification, Enel issues the document attesting the positive
outcome (ATR form), the Supplier can print the Quality Approval for components and materials
with positive Enel verification outcome (OK).
The factory or site acceptance with Quality Approval available and printable is highlighted with
the following symbol:
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 37/63
Scope: CQF User Manual for Suppliers
The system prints the identification data of the factory or site acceptance test in two or more
pages. This document must be attached to the components and materials transport
documents.
The system prints the components and materials serial numbers uploaded by the Supplier
during the Testing Notice generation and uploading. All components and materials with
serial numbers different from those indicated in the Quality Approval will not be
accepted in the inbound control phase in the Enel warehouses.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 38/63
Scope: CQF User Manual for Suppliers
In case of Factory/Site Acceptance Test performed in the presence of Enel Inspectors, the
Supplier waits the ATR form issued by Enel.
Only after receiving the ATR form, the supplier can print the QA for the components and
materials with quality control positive outcome (OK).
The system prints the identification data of the factory or site acceptance test in two or more
pages. This document must be attached to the components and materials transport
documents.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 39/63
Scope: CQF User Manual for Suppliers
The system prints the components and materials serial numbers uploaded by the Supplier
during the Testing Notice generation and uploading. All components and materials with
serial numbers different from those indicated in the Quality Approval will not be
accepted in the inbound control phase in the Enel warehouses.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 40/63
Scope: CQF User Manual for Suppliers
Click on “OK” if no notes need to be uploaded, otherwise click on “Annulla” and upload the
“Note quality approval”.
Click on “OK”.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 41/63
Scope: CQF User Manual for Suppliers
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 42/63
Scope: CQF User Manual for Suppliers
10.2.1 Factory/Site Acceptance Tests not First Supplies performed without the presence
of Enel Inspectors
In case of Second Category materials not First Supplies, the Supplier, in case of Factory/Site
Acceptance Test performed without the presence of Enel Inspectors, after 10:00 a.m. can
confirm the tests outcome (EF) and print the Quality Approval. The system registers the
Quality Approval print data and time.
The systems highlights the Factory/Site Acceptance Test for which the tests outcome must be
uploaded through the following button:
Click on .
The system requires to the Supplier to upload the test outcome (EF) for each material ID
noticed in the related Testing Notice.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 43/63
Scope: CQF User Manual for Suppliers
All the acceptance tests required by Enel contractual technical specifications were
performed in accordance with the Enel technical specifications;
For material batches declared as compliant, all the acceptance tests required by Enel
contractual technical specifications were positively passed;
For material batches declared as compliant, all the test reports are recorded and
available for the Enel Inspectors verification.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 44/63
Scope: CQF User Manual for Suppliers
Click on “OK”.
Click on .
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 45/63
Scope: CQF User Manual for Suppliers
The Supplier can add an optional text with eventual comments or clarification:
Click on “OK” if no notes need to be uploaded, otherwise click on “Annulla” and upload the
“Note quality approval”.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 46/63
Scope: CQF User Manual for Suppliers
Click on “Print QA” and proceed with the QA printing as indicated in the chapter 2.
10.2.2 Factory/Site Acceptance Tests in First Supplies performed without the presence
of Enel Inspectors
In case of Second and Third Categories materials First Supplies, the Supplier, in case of
Factory/Site Acceptance Test performed without the presence of Enel Inspectors, after 10:00
a.m. can confirm the tests outcome (EF) and print the Quality Approval. The system registers
the Quality Approval print data and time.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 47/63
Scope: CQF User Manual for Suppliers
The Supplier will fulfill in the “SO” column, for each material ID included in the Testing Notice,
the Factory Acceptance Test result (OK/KO).
The Supplier can add an optional text with eventual comments or clarification related to the
factory or site acceptance test, in the “Note Outcome Supplier” field. The system requires the
correct tests execution confirmation.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 48/63
Scope: CQF User Manual for Suppliers
Click on “OK”.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 49/63
Scope: CQF User Manual for Suppliers
with this button the Supplier communicates to the Enel Group distribution company owner of
the contract, the tests completion.
The system requires to confirm the correct tests execution and to click “Confirm and save”.
Click on “OK”.
The Supplier will receive an e-mail (to the e-mail address provided to Enel in the CQF
registration phase), in which the system provides the information related to the test reports
recipient (Enel references) in order to allow the Enel verification.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 50/63
Scope: CQF User Manual for Suppliers
The system highlights the factory acceptance tests for which the test report transmission to
Enel is required, with the following symbol:
The Supplier has to wait the Documental Verification outcome performed by Enel.
At the end of the Documental Verification, Enel issues the document attesting the positive
outcome (ATR form), the Supplier can print the Quality Approval for components and materials
with positive Enel verification outcome (OK).
The factory or site acceptance with Quality Approval available and printable is highlighted with
the following symbol:
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 51/63
Scope: CQF User Manual for Suppliers
The system prints the identification data of the factory or site acceptance test in two or more
pages. This document must be attached to the components and materials transport
documents.
The system prints the components and materials serial numbers uploaded by the Supplier
during the Testing Notice generation and uploading. All components and materials with
serial numbers different from those indicated in the Quality Approval will not be
accepted in the inbound control phase in the Enel warehouses.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 52/63
Scope: CQF User Manual for Suppliers
Click on “Print QA” and proceed with the document printing as indicated in the previous
paragraph 2.
In case of Factory/Site Acceptance Test performed in the presence of Enel Inspectors, at the
end of the tests, the Supplier waits for the ATR form issue.
Only after receiving the ATR form, the supplier can print the QA for the components and
materials with quality control positive outcome (OK).
The system prints the identification data of the factory or site acceptance test in two or more
pages. This document must be attached to the components and materials transport
documents.
The system prints the components and materials serial numbers uploaded by the Supplier
during the Testing Notice generation and uploading. All components and materials with
serial numbers different from those indicated in the Quality Approval will not be
accepted in the inbound control phase in the Enel warehouses.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 53/63
Scope: CQF User Manual for Suppliers
The system allow the Supplier to upload eventual notes or comments (not mandatory).
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 54/63
Scope: CQF User Manual for Suppliers
Click on “OK” if no notes need to be uploaded, otherwise click on “Annulla” and upload the
“Note quality approval”.
Click on “OK”.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 55/63
Scope: CQF User Manual for Suppliers
Click on “Print QA” and proceed with the QA printing as indicated in the chapter 2.
10.2.4 Factory/Site Acceptance Test not First Supplies with Documental Verification
In case of Factory/Site Acceptance Tests of Second Category components and materials not
First Supplies, Enel can plan a Documental Verifications of the test reports related to materials
under test.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 56/63
Scope: CQF User Manual for Suppliers
Insert eventual notes or comments related to the tests in the “Note Outcome Supplier” field.
All the acceptance tests required by Enel contractual technical specifications were
performed in accordance with the ENEL technical specifications;
For material batches declared as compliant, all the acceptance tests required by Enel
contractual technical specifications were positively passed;
For material batches declared as compliant, all the test reports are recorded and
available for the Enel Inspectors verification.
Click on “OK”.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 57/63
Scope: CQF User Manual for Suppliers
with this button the Supplier communicates to the Enel Group distribution company owner of
the contract, the tests completion. In the screen, there is the indication that Enel is performing
a Documental Verification.
The system requires to the Supplier another confirmation about the correct tests execution and
to click on “Confirm and save”.
Click on “OK”.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 58/63
Scope: CQF User Manual for Suppliers
The Supplier will receive an e-mail (to the e-mail address provided to Enel in the CQF
registration phase), in which the system provides the information related to the test reports
recipient (Enel references) in order to allow the Enel verification.
The system highlights the factory acceptance tests for which the test report transmission to
Enel is required, with the following symbol:
The Supplier has to wait the Documental Verification outcome performed by Enel.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 59/63
Scope: CQF User Manual for Suppliers
At the end of the Documental Verification, Enel issues the document attesting the positive
outcome (ATR form), the Supplier can print the Quality Approval for components and materials
with positive Enel verification outcome (OK).
The factory or site acceptance with Quality Approval available is highlighted with the following
symbol:
The system prints the identification data of the factory or site acceptance test in two or more
pages. This document must be attached to the components and materials transport
documents.
The system prints the components and materials serial numbers uploaded by the Supplier
during the Testing Notice generation and uploading. All components and materials with
serial numbers different from those indicated in the Quality Approval will not be
accepted in the inbound control phase in the Enel warehouses.
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 60/63
Scope: CQF User Manual for Suppliers
Click on “Print QA” and proceed with the QA printing as indicated in the chapter 2.
In case of Factory/Site Acceptance Test with negative outcome performed in the presence of
Enel Inspectors or in case of a Documental Verification with negative outcome, the Supplier
cannot print the Quality Approval for all materials with KO outcome and cannot ship
components and materials to destination.
The Supplier can print the Quality Approval for eventual components and material with positive
outcome (OK). The Quality Approval can be printed in case of materials with a reissue of the
ATR form (following a negative one) with positive outcome (OK).
The CQF Internet IT platform allows to the Supplier to perform specific search on Testing
Notice, according to their state, as shown in the filter below:
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 61/63
Scope: CQF User Manual for Suppliers
- Set/Edit SO: the Factory/Site Acceptance Tests for which it is possible to upload
or modify the Supplier tests outcome (ES), are extracted;
The presence of the symbols identifies the Testing Notices for which the “SO”
has been uploaded, but can be modified, because the Quality Approval has not been
saved.
The presence of the symbol identifies the Testing Notices for which the Suppliers
tests outcome EF has not been uploaded.
- With SO: the Factory/Site Acceptance Tests for which the Supplier tests outcome
(ES) has been uploaded, are extracted;
The presence of the symbols identifies the Testing Notices for which the Supplier
tests outcome EF has been uploaded, but can be modified, because the Quality
Approval has not been saved.
The presence of the symbol identifies the Testing Notices for which the Quality
Approval has been saved and that cannot be modified. The Quality Approval can be
printed.
The presence of the symbol identifies the Testing Notices for which the Supplier
sent to Enel the test reports. Enel will perform a Documental Verification and an ATR
form will be issued.
- Print QA: the Factory/Site Acceptance Tests for which is possible to print the
Quality Approval, are extracted;
CQF User Manual for Suppliers - Issue 01 – September 2017 Page 62/63
Scope: CQF User Manual for Suppliers
In case of Factory/Site Acceptance Test with negative outcome performed in the presence of
Enel Inspectors or in case of a Documental Verification with negative outcome, the Supplier
cannot print the Quality Approval for all materials with KO outcome and cannot ship
components and materials to destination.