0% found this document useful (0 votes)
176 views

ENI Production Logging Service Specification

This document provides specifications for production logging services. It outlines requirements for personnel, equipment, documentation, and health, safety and environmental standards. The contractor is responsible for complying with these specifications when performing production logging for ENI AGIP. Key equipment requirements include downhole instruments for measuring flowrates, pressures, temperatures, densities, and internal diameters. Personnel must include qualified production logging technicians. Documentation of operations, reports, and recorded data are also specified.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
176 views

ENI Production Logging Service Specification

This document provides specifications for production logging services. It outlines requirements for personnel, equipment, documentation, and health, safety and environmental standards. The contractor is responsible for complying with these specifications when performing production logging for ENI AGIP. Key equipment requirements include downhole instruments for measuring flowrates, pressures, temperatures, densities, and internal diameters. Personnel must include qualified production logging technicians. Documentation of operations, reports, and recorded data are also specified.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 16

SPEO ORGANIZING TYPE OF ISSUING DOC. REF. N. PAG.

1
DEPARTMENT ACTIVITY' DEPT. TYPE
ENI S.p.A.
Agip Division STAP A 1 SS 2702 OF 16

TITLE

PRODUCTION LOGGING SERVICE SPECIFICATION

DISTRIBUTION LIST

ENI AGIP Division Headquarter Drilling and Production Optimisation Units

ENI AGIP Divisions Well Operations Units for Italian Activities

ENI AGIP Division Affiliated Companies

NOTE:

This document has been prepared by the following working group:

ALBASI Giuliano ARCO

PILIA Luciano ARCO

GALLI Giuseppe SPEF

CHERRI Roberto TEOP

MASONI Roberto STAP

PARMIGIANI Angelo STAP

c General Revision Working Group Masoni Paccaloni


21/6/02 21/6/02 21/6/02
b Issued by Working Group Masoni Galletta
15/12/99 15/12/99 15/12/99

REVISIONS PREP'D CHK'D APPR'D

The present document is CONFIDENTIAL and it is the property of ENI


It shall not be shown to third parties nor shall it be used for reasons different from those owing to which it was given.
SPEO IDENTIFICATION CODE PAG 2 OF 16
ENI S.p.A.
STAP A-1-SS-2702
Agip Division REVISION
0 1

INDEX
1. SCOPE................................................................................................................................ 3

2. DEFINITIONS ..................................................................................................................... 3

3. APPLICABLE DOCUMENTS ............................................................................................. 3

4. RESPONSIBILITY .............................................................................................................. 4

5. HSE-QR .............................................................................................................................. 4

6. SERVICE REQUIREMENTS .............................................................................................. 4

7. PERSONNEL...................................................................................................................... 5

7.1 PLT SPECIALIST ............................................................................................................... 5

8. EQUIPMENT....................................................................................................................... 6

8.1 INSTRUMENTS .................................................................................................................. 6


8.1.1 FLOWRATE MEASUREMENTS WITH MECHANICAL SENSOR......................... 7
8.1.2 FLOWRATE MEASUREMENTS WITH TRACERS ............................................... 7
8.1.3 PRESSURE MEASUREMENTS ........................................................................... 7
8.1.4 TEMPERATURE MEASUREMENTS .................................................................... 7
8.1.5 DENSITY MEASUREMENTS ............................................................................... 8
8.1.6 WATER HOLD UP MEASUREMENTS ................................................................. 8
8.1.7 INTERNAL DIAMETER MEASUREMENTS OF THE HOLE ................................. 8
8.1.8 INSTRUMENT CONNECTION.............................................................................. 8
8.2 TECHNICAL NOTES OF RECORDING.............................................................................. 9

9. SERVICE BASE ................................................................................................................. 9

10. DOCUMENTATION .......................................................................................................... 10

10.1 OPERATIONS PROGRAM............................................................................................... 10


10.2 JOB REPORT ................................................................................................................... 10
10.3 RECORDED DATA........................................................................................................... 10
10.4 IMAGE FILE REQUIREMENTS ........................................................................................ 11

11. ANNEX.............................................................................................................................. 12
SPEO IDENTIFICATION CODE PAG 3 OF 16
ENI S.p.A.
STAP A-1-SS-2702
Agip Division REVISION
0 1

1. SCOPE

The scope of this specification is to define personnel, down hole equipment minimum requirements
for PRODUCTION LOGGING service.

2. DEFINITIONS

COMPANY any ENI AGIP and Affiliates Company requesting the service
invoking this specifications
CONTRACTOR any organisation performing the service to which this
specification is applied

SHALL Is used to indicate that a provision is mandatory.

STANDARD ENVIRONMENT Temperature up to 150°C (302°F) BHP up to 69 Mpa


(10.000 psi)

HOSTILE ENVIRONMENT Temperature above 150°C (302°F) BHP above 69 Mpa


(10.000 psi)
H2S and/or CO2 environment
Offshore operations with drill-ship and semi-sub

The Hostile Environment shall be considered also with only one of the above conditions

3. APPLICABLE DOCUMENTS

ENI AGIP 310520 - SG22 Integrated Hse-Qr Requirements For Drilling, Completion And
Exploration Services (if not otherwise stated in the tender
documentation)
ENI AGIP 310520 SG21 Specifica gestionale per i servizi relativi all’area pozzo (only for
Italian Activity)
ENI AGIP - LOGE Electrical Log Services Technical Specifications for Equipment
and Processing
NACE Std MR01 75 Standard Material Requirements - Sulphide Stress
Cracking Resistant Metallic Materials for Oil field equipment.
ENI AGIP STAP A-1-SS-1727 Wire Line (Slick Line) Service Technical Specifications (if not
otherwise stated in the tender documentation)
ENI AGIP STAP A-1-SS-2701 Casing Perforating and Auxiliary Services (if not otherwise
stated in the tender documentation)

All documents mentioned herein are intended as the latest revision unless otherwise stated.
SPEO IDENTIFICATION CODE PAG 4 OF 16
ENI S.p.A.
STAP A-1-SS-2702
Agip Division REVISION
0 1

4. RESPONSIBILITY

The Contractor is responsible for the compliance with the requirements set forth in this specification.
Nothing in this specification shall relieve the Contractor of the responsibility for performing, in addition
to the requirements of this specification, such analysis, tests, inspections and other activities that he
considers necessary to ensure that the product, and workmanship are satisfactory for the service
intended, or as may be required by common usage or good practice.
Modification to the requirements of this specification may be proposed by the Contractor, provided
they are submitted to Company approval, with the support of proper documentation.

5. HSE-QR

All activities carried out by Contractor shall be performed in accordance with Contractor’s written
procedures and in compliance with the Applicable Documents and Standards defined in this
document.
All the activities shall be carried out with minimum impact on the environment and maximum care of
health and safety of all concerned, directly or indirectly, with the activities.
Others requirements as per ENI AGIP 310520-SG22 (SG21).

6. SERVICE REQUIREMENTS

The Contractor shall perform the work in accordance with Company request and Contractors written
procedures utilising its own know-how and operating experience.

For the execution of the service the Contractor shall:

• Provide personnel and equipment necessary to plan and co-ordinate, supervise and perform the
services;
• Supply timely the requested types and quantity of tools and materials to perform the work;
• Provide, if request, all the quality control documents related with supplied tools, equipment and
materials;
• Carry out, co-ordinate and move all or part of contractor items to and from the wells;
• Maintain a comprehensive inventory of equipment required to successfully carry out the entire
operations;
• Provide, if request, details of ”in-house” calibration and inspection facilities, standards and
frequency; in addition, the standard type and frequency of third party inspection is to be detailed;
• Provide all consumable and spare part equipment on a consignment basis;
• Provide all the authorisation for transport and handling of dangerous material as per applicable
law;
• Prepare and submit the necessary detailed technical reports and other documentation as directed
by Company;
• Provide reporting of operation as required by Company;
SPEO IDENTIFICATION CODE PAG 5 OF 16
ENI S.p.A.
STAP A-1-SS-2702
Agip Division REVISION
0 1

as described in the following chapters.

7. PERSONNEL

The Contractor shall all time be responsible for ensuring that Personnel provided to perform the
services are appropriately qualified, hold valid certifications , are adequately trained and that the
validity of such qualifications, certifications and training are maintained throughout the Contract
Period.

In addition, for the personnel working at rig site, the following courses are requested:

Survival at Sea
All personnel, working on an offshore rig, must attend a specific “survival at sea” training course. This
course shall be held at training centres recognised by the Company.

Fire Fighting
All personnel must receive training in Basic Fire Fighting.

First Aid
All personnel must receive basic training in First Aid technique.

Basic Course H2S


All the personnel shall be trained with basic monitoring techniques, safety procedures and use of
protection equipment as breathing apparatus and escape set.

Good Health Certificate


The Contractor shall supply, on Company request, certificates of good health, qualification and
competence for each employee assigned to special works according with local laws and regulations.

The personnel shall be full knowledge of the applicable procedures and operating instructions and
must be able to speak, read and write the language indicated in the “Personnel Qualification Card”.

The Contractor shall provide to Company the professional curricula for all personnel he intends to
use, indicating background, training and work experience.

During the period of applicability of the contract, before any operative personnel are replaced, the
Contractor shall send updated Professional Curriculum(a) to the Company of said substitute(s).

7.1 PLT SPECIALIST

Engineer shall be a Technical University Degree or equivalent with an adequate skill acquired
through an appropriate training course and on the job, with field experience in this position in a
Production Logging Service Company.

He shall be responsible of:

a) on-site check, calibration, maintenance and repairing of the PLT equipment.


b) preparation of reports and documents as requested in the service.
SPEO IDENTIFICATION CODE PAG 6 OF 16
ENI S.p.A.
STAP A-1-SS-2702
Agip Division REVISION
0 1

The minimum field experience requested are:

STANDARD ENVIRONMENT 1 YEAR


HOSTILE ENVIRONMENT 3 YEARS

The Contractor shall guarantee rest shifts in case of long operations.

8. EQUIPMENT

The choice of equipment to be used in each single well operation shall be agreed between Company
and Contractor. The equipment shall be suitable to work under the environmental condition required.
Contractor shall guarantee the availability of fishing tool at rig site.

8.1 INSTRUMENTS

The instruments must be suitable to be used in conjunction with operating unit and cable defined in
the technical specification:

• ENI AGIP STAP A-1-SS-1727 Wire Line (Slick Line) Service Technical Specifications (for
slick line operation)
• ENI AGIP STAP A-1-SS-2701 Casing Perforating and Auxiliary Services (for electrical
wire slick line operation)

The instruments that can be requested are:


• memory type
• surface readout type

The surface readout type instruments must be capable of providing both independently and inter
combined simultaneous transmission of data to the surface.
For specific applications the instruments must be suitable to be run in hole by means of different
conveyed devices (coil tbg, tractor ect.)
In the following paragraph are listed the main instruments that Contractor shall provide.
Additional instruments can be requested/proposed during the bidding phase.
SPEO IDENTIFICATION CODE PAG 7 OF 16
ENI S.p.A.
STAP A-1-SS-2702
Agip Division REVISION
0 1

8.1.1 FLOWRATE MEASUREMENTS WITH MECHANICAL SENSOR

Technical characteristics of the instrument


Standard tool with maximum outside diameter of the probe 1 11/16”
Others diameters can be utilised according to well conditions

FULL BORE CONTINUOUS


Accuracy (% at full scale) +/-2 +/-3
Resolution (RPS) 0,1 0,2

8.1.2 FLOWRATE MEASUREMENTS WITH TRACERS

Technical characteristics of the instrument


Standard tool with maximum outside diameter of the probe 1 11/16”
Others diameters can be utilised according to well conditions
Tracer that can be mixed with the fluid in the well.

8.1.3 PRESSURE MEASUREMENTS

a) “Strain gauge” sensor.

Technical characteristics of the instrument


Standard tool with maximum outside diameter of the probe 1 11/16”
Others diameters can be utilised according to well conditions
Accuracy: +/- 0,5%
Resolution: 0.1 psi

b) “Quartz gauge” sensor.


Technical characteristics of the instrument
Standard tool with maximum outside diameter of the probe 1 11/16”
Others diameters can be utilised according to well conditions
Accuracy: +/- 0.025% of the measured value
Resolution: 0.01 psi

8.1.4 TEMPERATURE MEASUREMENTS

Technical characteristics of the instrument


Standard tool with maximum outside diameter of the probe 1 11/16”
Others diameters can be utilised according to well conditions
Accuracy: +/- 0,5 °C
Resolution: 0.05 °C
SPEO IDENTIFICATION CODE PAG 8 OF 16
ENI S.p.A.
STAP A-1-SS-2702
Agip Division REVISION
0 1

8.1.5 DENSITY MEASUREMENTS

Instruments capable to measure the density of the fluid in the well at measured depth
Standard tool with maximum outside diameter of the probe 1 11/16”
Others diameters can be utilised according to well conditions
Accuracy: 0,03 g/cm3
Resolution: 0,005 g/cm3
Range of measure: 0-1,6 g/cm3

8.1.6 WATER HOLD UP MEASUREMENTS

Instrument capable to measure the % of water content in the production fluid


Technical characteristics of the instrument
Standard tool with maximum outside diameter of the probe 1 11/16”
Others diameters can be utilised according to well conditions
Resolution 1% between 0-40%
Stability of water hold up 4% in the whole temperature range

8.1.7 INTERNAL DIAMETER MEASUREMENTS OF THE HOLE

Instrument consisting of at least four skids arranged orthogonal


Technical characteristics of the instrument
Accuracy: 0,1”
Resolution: 0,05”
Measurement range 2”÷9”;2”÷18”

NOTE : for instruments used as correlation log (Natural Gamma Ray and CCL) reference is made to
ENI AGIP LOGE “Electrical Log Services Technical Specifications for Equipment and Processing”

8.1.8 INSTRUMENT CONNECTION


In case the instruments will be connected to a third party slick line, electric line, coiled tubing or other
conveyed device, the Contractor shall provide an adequate connection.
The type will be defined in the bidding/planning phase.
SPEO IDENTIFICATION CODE PAG 9 OF 16
ENI S.p.A.
STAP A-1-SS-2702
Agip Division REVISION
0 1

8.2 TECHNICAL NOTES OF RECORDING

The Contractor will guarantee that the following operations are carried out
before, during and after recording :
- always carry out the calibration of the instruments before recording.
The main data of this calibration must be reported in the technical
report of the Contractor.
- Before the main recording, carry out a bottom well recording of sufficient
length to allow for correlation of depths of instruments with possible
correction of the various recorded curves. This recording in the absence of
specific indications of the operating programme, must be conducted in static
conditions.
- Record three or more passes (on the basis of the indications of the
operating program) up and down over the area to be surveyed.

9. SERVICE BASE

The Contractor shall have the availability of one or more centres in the Area Of Operations where the
Service is requested.
In these centres, the Contractor will provide for :
- ordinary maintenance after each operation;
- periodic control with possible recalibration of all instruments;
These maintenance, calibration and control operations must be certified by the Contractor and
documentation made available to the Company (on request).
SPEO IDENTIFICATION CODE PAG 10 OF 16
ENI S.p.A.
STAP A-1-SS-2702
Agip Division REVISION
0 1

10. DOCUMENTATION

10.1 OPERATIONS PROGRAM

Before starting the operation the Contractor will provide an operations program based on the
information provided by the Company.
The information provided by Company shall include basic well information, a recording program with
the reason for the recording, the minimum information/results to be obtained and all the information
necessary to ensure optimal execution of the operation. The recording program shall contain the
modalities to be used to perform the record, the number of up and down passes to conduct in the
surveyed area, the cable velocity and the recording of any stationary measures.
In the operations program the Contractor shall include the recording tool string description and
relevant specifications with recommended back up tools and suggestion for a better quality of
recording.
The operations program shall include the list of the personnel involved with shifting program in case
of long operations.

This document shall be submitted to the Company for acceptance.

10.2 JOB REPORT

At the end of the service the Contractor shall submit at Job Report.
In case a non conformance is encountered during the service, the Contractor shall submit
full explanation of the cause and corrective actions applied or plan of actions to undertake
to explain and correct the non conformance.

10.3 RECORDED DATA

At the end of each operation the Contractor must provide the Company with :

1. An original film, plus the number of copies stated in the contract, at two different scales, for
every log (scales of 1:200 and 1:1000 are usually requested);

2. A checked 4 mm DAT tape in LIS/DLIS format, with standard density (5 Giga) or a tape
LIS/DLIS format with 1600 BPI density; in case of high density it is important to specify it on the
tape header.

3. The Contractor must provide at the end of each acquisition run a 3 ½" floppy disk containing
selected measured data, defined by the Company Representative, in LAS or ASCII format.

4. A single file playback, histogram or crossplot (histograms and crossplots are limited to a
continuous interval of not more than 150 m). Single file playback is meant as a playback
obtained from a set of values measured (or recorded on tape) in a single or combined service.

5. Additional copies and/or tapes must be available on request.


SPEO IDENTIFICATION CODE PAG 11 OF 16
ENI S.p.A.
STAP A-1-SS-2702
Agip Division REVISION
0 1

10.4 IMAGE FILE REQUIREMENTS

On request the recorded log shall be also provided as Image File.

All Image Files are to be provided in Adobe Acrobat Version 5 format using the Acrobat Version
5 software. The file extension name for this type of file is *.PDF.

All logs should be output in colour.

The Adobe Acrobat PDF file should contain multiple pages with a landscape page size of 11.0 inches
or 279.4 mm width and 7.0 inches or 177.8 mm length. These dimensions must be exact and not
varied. The reason for these particular dimensions is to allow the mudlogs to be printed on multiple
pages to a single sheet A4 printer and to an Epson Stylus Colour 3000 or 1520 in a continuous plot
by selecting the page size of Long Paper 17 x 7 in for paper source Manual Feed Slot (Banner). Note
that physically the paper can be fed into the Manual Feed Slot or on sprockets through the Tractor
Feeder.

It is important that there are no margins at the top and bottom, edges of the plot as the 7 inch (177.8
mm) length pages will print continuously to an Epson printer to make a log as long as is required.

It is likely that these pages will be output first to a multiple page Postscript File and then converted to
Acrobat version 5 using the Acrobat Distiller version 5 program. It is important that the following
settings be set in Acrobat Distiller version 5.

The Job Options should be “PrintOptimised”. Select - Settings – Job Options.

On the General Tab select Compatibility Acrobat 3.0, Check Optimize, Uncheck Embed Thumbnails,
Resolution 300 dpi and Binding Left, set the default page size to 11.0" Width and 7.0" Height.

On the Compression Tab

Colour Images:
Check Bicubic Downsampling to 300 dpi
Check Compression Automatic
Quality Maximum
Grayscale Images:
Check Bicubic Downsampling to 300 dpi
Check Compression Automatic
Quality Maximum
Monochrome Images:
Check Bicubic Downsampling to 300 dpi
Check Compression with CCITT Group 4
Check Compress Text and Line Art
Leave all other settings as default.
Under the Font Tab Embed all necessary Fonts.
Under the Colour Tab leave all settings as default.
Under the Advanced Tab leave all settings as default

Other Image File can be proposed by Contractor during the bidding phase and submitted to
Company for acceptance.
SPEO IDENTIFICATION CODE PAG 12 OF 16
ENI S.p.A.
STAP A-1-SS-2702
Agip Division REVISION
0 1

11. ANNEX

ANNEX A – PERSONNEL QUALIFICATION CARDS

ANNEX B – CONTRACTOR’S BASE

ANNEX C – PLT EQUIPMENT LIST


SPEO IDENTIFICATION CODE PAG 13 OF 16
ENI S.p.A.
STAP A-1-SS-2702
Agip Division REVISION
0 1

ANNEX A – PERSONNEL QUALIFICATION CARDS

Company’s Request Contractor’s Offer


Name:
Date of birth :
Employed on :
Length of service :
Languages :
Present position :
Education :

Vocational training :

Training Basic Courses :


Basic H2S
Fire Fighting
First Aid
Training Certified Courses : Survival at Sea (in case of
Off-shore operation)

Professional experience :

Areas/Fields where he
worked
On-shore

Off-shore

Company he has worked for

This form can be used in the bidding phase


SPEO IDENTIFICATION CODE PAG 14 OF 16
ENI S.p.A.
STAP A-1-SS-2702
Agip Division REVISION
0 1

ANNEX B CONTRACTOR’S BASE

Description
Type of Facility Purpose of Facility Location
of major equipment
Warehouse • Storage of equipment and
spare parts
• Maintenance of downhole
Workshop
tools and auxiliary
equipment
Yard • Storage of spare
equipment
Calibration
• Calibration of sensors
Facility
• NDT
Electronic • Calibration and repairs of
Laboratory all electrical/electronic
equipment

This form can be used in the bidding phase


SPEO IDENTIFICATION CODE PAG 15 OF 16
ENI S.p.A.
STAP A-1-SS-2702
Agip Division REVISION
0 1

ANNEX C – EQUIPMENT LIST

PLT Equipment List Company Request Contractor Offer


8.1.1.a Flowrate measurements with mechanical
sensor
Type FULL BORE
Model
Diameter (max O.D. 1”11/16)
Accuracy (+/- 2% at full scale)
Resolution (0,1 RPS)
Technical feature (i.e. memory – SRO)
Standard / hostile environment 4) Specified tool operating
limits (temperature, pressure )
8.1.1.b Flowrate measurements with mechanical
sensor
Type CONTINUOUS
Model
Diameter (max O.D. 1”11/16)
Accuracy (+/- 3% at full scale)
Resolution (0,2 RPS)
Technical feature (i.e. memory – SRO)
Standard / hostile environment 4) Specified tool operating
limits (temperature, pressure )
8.1.2 Flowrate measurements with tracers
Type / Model
Diameter (max O.D. 1”11/16)
Technical feature (i.e. memory – SRO)
Standard / hostile environment 4) Specified tool operating
limits (temperature, pressure
Type of tracers
8.1.3.a Pressure measurements “strain gauge”
sensor
Type / Model
Diameter (max O.D. 1”11/16)
Accuracy (+/- 0,5%)
Resolution (0,01 psi)
Technical feature (i.e. memory – SRO)
Standard / hostile environment 4) Specified tool operating
limits (temperature, pressure
8.1.3.b Pressure measurements “Quartz gauge”
sensor
Type / Model
Diameter (max O.D. 1”11/16)
Accuracy (+/- 0,025 % of the measured value)
Resolution (0,01 psi)
Technical feature (i.e. memory – SRO)
Standard / hostile environment 4) Specified tool operating
limits (temperature, pressure
8.1.4 Temperature measurements
Type / Model
Diameter (max O.D. 1”11/16)
Accuracy (+/- 0,5 °C)
Resolution (0,05 °C)
SPEO IDENTIFICATION CODE PAG 16 OF 16
ENI S.p.A.
STAP A-1-SS-2702
Agip Division REVISION
0 1

Technical feature (i.e. memory – SRO)


Technical feature
Standard / hostile environment 4) Specified tool operating
limits (temperature, pressure
8.1.5 Density measurements
Type / Model
Diameter (max O.D. 1”11/16)
Accuracy (0,03 g/cm3)
Resolution (0,005 g/cm3)
Range of measure (0-1,6 g/cm3)
Technical feature (i.e. memory – SRO)
Standard / hostile environment 4) Specified tool operating
limits (temperature, pressure
8.1.6 Water hold up measurements
Type / Model
Diameter (max O.D. 1”11/16)
Resolution (1% between 0-40%)
Technical feature (i.e. memory – SRO)
Standard / hostile environment 4) Specified tool operating
limits (temperature, pressure
8.1.7 Internal diameter measurements of the hole
Type / Model
Diameter (max O.D. 1”11/16)
Accuracy (0,1”)
Resolution (0,05”)
Range of measure 2”÷9” & 2”÷18”
Technical feature (i.e. memory – SRO)
Standard / hostile environment 4) Specified tool operating
limits (temperature, pressure
8.1.8 Instrument Connection

Notes : (1) Contractor shall provide copy of the technical specification sheet for all equipment offered.
(2) If not defined by Company, to be suggested by Contractor according to the “PLT Program”
during the planing phase.
(3 Contractor shall acknowledge and state compliance with technical requirements as per
applicable Technical Specifications document. In case, Contractor shall clearly indicate non
conformance or alternative.
4) Specified tool operating limits (temperature, pressure etc.)

(+) To be specified by Contractor.


This form can be used in the bidding or planning phase